Khe Than Bridge construction stopped
(Baonghean.vn) - Khe Than Bridge, Tien Ky Commune (Tan Ky) started construction in April 2015. After completing some bridge piers, the construction unit had to stop working because the locality had not yet cleared the land.
![]() |
After the construction unit completed 2 piers and 1 abutment, Khe Than Bridge had to stop construction because the district had not yet cleared the land. |
Khe Than Bridge is built according to the standard of permanent bridge with prestressed reinforced concrete, the bridge is more than 112 m long, 7 m wide and the road at both ends of the bridge is built according to the standard of grade V mountainous road, the roadbed is 6.5 m wide, the road surface is 3.5 m wide. The bridge consists of 3 spans with a total investment of more than 42 billion VND, of which the construction cost is more than 33 billion VND.
The project is being undertaken by a joint venture between Minh Sang Construction Joint Stock Company and Dai Son Construction Investment and Consulting Joint Stock Company with a construction schedule of 24 months from the date of commencement. Up to now, 22 months have passed and only 2 piers have been constructed on the bridge. The contractors claim that the locality has not yet cleared the land, so construction cannot continue.
![]() |
The GPMT area has been measured and marked but compensation has not been paid to the people. |
According to the Tan Ky District Project Management Board, up to now, the project has received 9 billion 700 million VND in capital, including: Construction cost 8 billion 550 million VND; Project management cost 349 million VND; Construction investment consulting cost 751 million VND; Bomb and mine clearance cost 50 million VND.
The compensation area for site clearance of this project alone is 10,053 m2, costing 2 billion VND, but up to now, capital has not been allocated, so Tan Ky District People's Committee has not yet compensated for site clearance for the contractor to continue construction.