Chairman of the Provincial People's Committee inspects the progress of some key projects
(Baonghean.vn) - On March 5, a working delegation of the Provincial People's Committee led by Mr. Nguyen Xuan Duong - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee inspected the progress of a number of key industrial and infrastructure projects of the province in Hoang Mai Town and Quynh Luu and Nghia Dan districts.
Accompanying were Vice Chairmen of the Provincial People's Committee: Huynh Thanh Dien, Le Ngoc Hoa; representatives of the Provincial People's Committee Office, Southeast Economic Zone Management Board, Department of Transport, Finance, Natural Resources and Environment, Industry and Trade, Construction, Planning and Investment, Nghe An Electricity Company, etc.
Hoa Sen Nghe An Factory Project of Hoa Sen Nghe An One Member Co., Ltd. is located in Dong Hoi Industrial Park, Hoang Mai on a total area of 35 hectares. Currently, the compensation, support and resettlement of the project land has been basically completed and handed over to the investor to implement the project.The investor is actively implementing investment and construction of projects according to detailed planning and selected technological lines to strive forPhase 1 put into operation June 2016.
![]() |
Chairman of the Provincial People's Committee Nguyen Xuan Duong listened to the leader of Hoa Sen Nghe An One Member Co., Ltd. report on the progress of the project implementation at Dong Hoi Industrial Park, Hoang Mai. |
![]() |
Comrade Nguyen Xuan Duong discussed the removal of some recommendations of the Hoa Sen Nghe An Factory project. |
Also in Dong Hoi Industrial Park, the Quynh Lap 1 Thermal Power Plant project invested by the Vietnam National Coal - Mineral Industries Group with a total investment of 2.2 billion USD has been approved for detailed planning with a total area of over 143.5 hectares. Up to now, although the investor is waiting for approval to change technology, the site clearance and resettlement work for the project is still being carried out.
The investor has approved the compensation, site clearance and resettlement project for Quynh Lap 1 Thermal Power Plant with a total cost of nearly 443 billion VND. The Management Board of the Southeast Economic Zone, Hoang Mai Town and the investor are carrying out the necessary procedures to successfully implement this work.
![]() |
Comrade Nguyen Xuan Duong inspected the construction progress of the road connecting National Highway 1A with Nghia Dan and Thai Hoa. |
![]() |
The contractor is urgently constructing the road connecting National Highway 1A with Nghia Dan and Thai Hoa. |
The Chairman of the Provincial People's Committee and the delegation also inspected the construction progress of the road connecting National Highway 1A with Nghia Dan District and Thai Hoa Town. The 29 km long road is being constructed by the Ministry of National Defense's 36 Corporation. This is a very important road, creating a connection between the Northwest and Northern Nghe An.
In addition, the route also meets the requirements for transporting raw materials and products for many large projects such as Tan Thang Cement Factory. Therefore, the investor is very interested in urging the contractor to speed up the implementation progress. Also this morning, comrade Nguyen Xuan Duong and the working group also visited the site of the Hoang Mai Water Plant project.
![]() |
Comrade Nguyen Xuan Duong inspected the Hoang Mai Water Plant project site. This is an important project that not only supplies domestic water to Hoang Mai Town but also industrial production projects such as Hoa Sen Steel. Therefore, the Chairman of the Provincial People's Committee requested the contractor to urgently implement the project. |
At the Tan Thang Cement Plant project (Quynh Luu), Tan Thang Cement Joint Stock Company has completed the financial arrangements for the project and is implementing the bidding package for equipment procurement; design and construction of the plant. Currently, the site clearance work is being urgently deployed to start construction in June 2016 and strive to put the cement plant with a capacity of 2 million tons of cement/year into operation by the end of 2017 and early 2018.
The road project from Hoang Mai 2 Industrial Park to Tan Thang Cement Factory, with a length of 7.3 km, passing through Quynh Vinh commune, Hoang Mai town and Tan Thang commune (Quynh Luu), serving the construction of the cement factory and transporting products, is also under construction.
![]() |
The Chairman of the Provincial People's Committee directed Quynh Luu district to remove obstacles and clear remaining land to facilitate the implementation of the Tan Thang Cement Factory project. |
At the end of the working program, the Chairman of the Provincial People's Committee inspected the progress of the MDF wood and fiberboard processing factory invested by May Forestry Joint Stock Company in Nghia Hoi commune, Nghia Dan district. Currently, in the first phase, the finger joint board production line has been put into operation and produced products; the MDF plywood production line is being installed, striving to be completed in May 2016.
![]() |
The Chairman of the Provincial People's Committee viewed the laminated board products produced at the factory. |
At the above working locations, after listening to the investor's report on the project progress, the Chairman of the Provincial People's Committee requested that investors and contractors actively implement construction and equipment installation according to plan, putting factories and works into operation on schedule. Comrade Nguyen Xuan Duong also listened to the investor's recommendations such as implementing electricity, water, traffic infrastructure, etc. and directed relevant departments, branches and localities to actively coordinate with investors and the Central Government to promptly resolve the issues./.
Thanh Duy