CIENCO 4: Focusing resources on implementing Nghi Son - Dien Chau expressway

Le Thanh DNUM_CFZAHZCACB 08:00

(Baonghean.vn) - These days, at the construction site of package XL04 of the Nghi Son - Dien Chau section investment project under the project to build a number of road sections on the North - South expressway in the East, the staff, engineers of the Executive Board, and workers of CIENCO4 Group are working hard to speed up the project progress with an excited and urgent spirit to complete the workload according to the set schedule.

Taking us to visit the construction site, Mr. Tran Viet Son - Director of the Executive Board of Package XL04, Investment and Construction Component Project of SectionNghi Son - Dien Chaubelonging to the Project to build some road sections on the North-South Expressway in the East phase 2017-2020 said: Currently, the GroupCIENCO4is actively taking advantage of favorable weather to speed up the progress of the frontage road project at Km 49+600 to Km 424+800 in Dien Dong commune (Dien Chau). Despite working in difficult and arduous conditions, especially the impact of the Covid-19 epidemic, the project is determined not only to be important to the province and the whole country but also to further affirm the Group's brand with enthusiasm and determination, the staff and workers of the unit strive to complete the project on schedule.

Cán bộ Ban Quản lý điều hành dự án bám sát công trường chỉ đạo thi công.
Project Management Board staff closely follow the construction site to direct the construction.

The Ministry of Transport has just issued a decision approving the results of contractor selection for package XL04: Construction of section Km419+600 - Km430+000 (including survey, design of construction drawings), North-South expressway component project, Nghi Son - Dien Chau section.

According to the approval decision of the Ministry of Transport, the winning contractor is the consortium of CIENCO4 Group Joint Stock Company - Tan Nam Construction Joint Stock Company - Truong Son Construction Investment Joint Stock Company. The winning bid value of the package is 1,139.53 billion VND (including contingency and 10% VAT). The contract type is based on combined unit price (survey part: According to fixed unit price; Construction drawing design: Lump sum; Construction and installation: according to adjusted unit price). This package uses State budget capital, the contract implementation period is 24 months. This is the second package out of 4 construction and installation packages of the North-South Expressway component project, Nghi Son - Dien Chau section, to complete the contractor selection.

The North-South Expressway is a national key project, so right from the initial selection of bidding documents, the Ministry of Transport required contractors to meet the requirements on capacity, machinery, equipment, finance, especially experience in highway construction... to ensure the progress, quality and efficiency of the project. This means that only contractors with real capacity can participate in the construction of this project. This is an opportunity for CIENCO4 Group Joint Stock Company and a number of other large transport enterprises to participate in most of the North-South Expressway component projects in the East in the period of 2017-2020.

Currently, the construction sites of these projects are being vigorously deployed across the country, with CIENCO4 Group contributing as both contractor and investor.

CIENCO4 is a familiar name in the field of construction of transport projects. In the field of highway construction alone, CIENCO4 has been undertaking the construction of a series of large packages belonging to key national projects, including: North-South Expressway, Cam Lo - La Son section, Phan Thiet - Dau Giay section; My Thuan - Can Tho, Noi Bai - Lao Cai, Hanoi - Hai Phong, Ho Chi Minh City - Long Thanh - Dau Giay, Mai Dich - Nam Thang Long expressways... CIENCO4 is one of the units trusted and highly appreciated by the Ministry of Transport in the component projects of the construction of the North-South Expressway in the East.

Along with having the best financial plan, experience and outstanding construction capacity proven in major projects in recent years are factors that make CIENCO4 trusted to "choose the right place to entrust gold". In 2020, the Covid-19 pandemic caused difficulties for most economic sectors of the country; including the field of transport infrastructure construction. However, CIENCO4 Group still completed and won many key transport projects, which affirmed the brand position as well as the sustainable development policies and directions of this enterprise.

Thi công nền đường gom tại Km 49+600 đến Km 424+800 tại xã Diễn Đồng (Diễn Châu).
Construction of the roadbed from Km 49+600 to Km 424+800 in Dien Dong commune (Dien Chau).

According to Mr. Nguyen Viet Huy - Deputy Director of the Department of Public-Private Partnership - PPP (Ministry of Transport), CIENCO4 is constructing major projects in the transport infrastructure sector such as: CP1A package of the Ho Chi Minh City Urban Railway Project No. 1, Ben Thanh - Suoi Tien route; airport packages such as: Cat Bi airport, Phu Cat airport, Tan Son Nhat airport runway renovation project. CIENCO4 has now completed the Tan Vu Lach Huyen project - the longest sea-crossing bridge in Southeast Asia. In the field of highway construction alone, CIENCO4 has undertaken a series of major packages of previous national key projects, including Noi Bai - Lao Cai highway, Hanoi - Hai Phong highway, Ho Chi Minh City - Long Thanh - Dau Giay highway and the most recent project put into operation since the end of 2020 is Hanoi Ring Road 3, Mai Dich - Nam Thang Long section...

Up to now, the whole country has more than 1,000 km of roads.highwayput into operation. The CIENCO4 brand is associated with many projects on this route. With good financial preparation, experience and outstanding construction capacity, CIENCO4 was chosen to implement the North - South expressway projects.

Thi công nền đường gom Ttại Km 49+600 đến Km 424+800 tại xã Diễn Đồng (Diễn Châu).
Construction of the roadbed from Km 49+600 to Km 424+800 in Dien Dong commune (Dien Chau).

Mr. Nguyen Tuan Huynh - General Director of CIENCO4 Group shared that although we are at the peak of the impact of the 4th Covid-19 epidemic, these days, at the construction sites of expressway projects, the Group's staff and engineers regularly urge and direct units to implement epidemic prevention and control solutions while applying many construction measures to "overcome the sun and overcome the rain" to complete the workload according to the set schedule.

“With the capacity, experience and reputation in the field of investment and construction of transport infrastructure that has been affirmed in the past time, the unit commits to focus all resources, innovate and be creative in management and operation to complete the project and put into operation the Nghi Son - Dien Chau expressway according to the required schedule” - General Director of CIENCO4 Group Nguyen Tuan Huynh affirmed.

The North-South Expressway component project, Nghi Son - Dien Chau section, is 50km long, passing through Thanh Hoa and Nghe An provinces. In the completion phase, the project will have a scale of 6 lanes, a 32.25m roadbed, and a design speed of 100 - 120km/h. In the immediate future, in the phased phase, the project will have a scale of 4 lanes, a 17m roadbed, and a design speed of 80km/h. The project has a total investment of about 7,293 billion VND, using the State budget, and the project construction period is about 2 years.