(Baonghean.vn) - The Ke Tat resettlement project in Thach Ngan Commune (Con Cuong) is more than 3 years behind schedule and has not yet been completed. In particular, some items have been severely damaged.
 |
This Ke Tat resettlement site is part of the Project to Preserve and Develop the Dan Lai ethnic group living in the core zone of Pu Mat - Con Cuong National Park. According to the plan, the project was started in early 2012, completed in 2014 and relocated people to this new place. Photo: Ho Phuong |
 |
Ke Tat resettlement area was approved for construction investment in 2010, including 35 houses and accompanying auxiliary works such as schools, teachers' housing, community cultural houses, medical stations... on an area of 100 hectares with a total capital of over 36.8 billion. Photo: Dao Tho |
 |
Currently, the project has disbursed more than 34 billion VND. The system of houses, schools, medical stations, water pipes... are all available. However, these items all show signs of deterioration. Photo: Ho Phuong |
 |
The total area of this project is 100 hectares, and will arrange for more than 35 households of the Dan Lai ethnic group in Co Phat village, Mon Son commune (Con Cuong) to live here. However, currently, grass and trees grow over people's heads, many houses are damaged and people still cannot move to this new place. Photo: Dao Tho |
 |
The bamboo panels and planks of the old houses were almost completely damaged. Photo: Ho Phuong |
 |
Underneath the stilt houses is an ideal shelter for buffaloes and cows from neighboring villages. Photo: Dao Tho |
 |
The medical station project has grass growing taller than people. According to the representative of the Con Cuong District Project Management Board, this project has many items and many contractors. Photo: Ho Phuong |
 |
All the water tanks built more than 4 years ago have not been used even once. Mr. Tran Anh Tuan - Head of the Project Management Board of Con Cuong district said: Currently, the entire infrastructure of the project has been basically completed. However, the capital to support production and relocate people of about 7 billion has not been arranged so it cannot be implemented. The project has also been extended until the end of 2017. Photo: Dao Tho |
Ho Phuong - Dao Tho