(Baonghean.vn) - According to the report of the Department of Agriculture and Rural Development, this spring crop is likely to suffer from water shortage due to drought on more than 21,300 hectares. Localities in the province are mobilizing capital sources to focus on building and solidifying the canal system.
 | The project “Restoration and upgrading of the Northern Nghe An irrigation system (JICA2)” started construction on January 10, 2016 with 8 packages, total value of over 400 billion VND, concentrated in Do Luong and Dien Chau districts. In the photo: Construction of the canal section through Dien Dong commune, Dien Chau. |
|
 |
Workers are preparing steel for pouring concrete in Dien Dong commune, Dien Chau. |
 |
Iron formwork system for pouring concrete in Dien Hanh commune canal section (Dien Chau). |
 |
Workers are pouring concrete in Yen Son commune, Do Luong. |
 |
Up to now, the whole province has solidified nearly 4,900 km of canals serving rice cultivation and short-term industrial crops. In the photo: Some branch canals in Yen Son and Do Luong have been put into effective irrigation for the spring rice crop. |
Van Truong