Speed ​​up the renovation of Vinh ancient citadel

DNUM_CGZAFZCABG 15:53

(Baonghean.vn) - Project to renovate and upgrade the ditch around Vinh Citadel (Nghe An)is being implemented very slowly due to problems with site clearance.

Thi công Hào Thành cổ
Construction of dredging the ancient citadel moat.

On the Vinh Citadel moat, the Hoa Hiep - Thinh Hung joint venture is constructing the embankment and the bottom of the citadel, and dredging the citadel lake. However, the construction volume has only reached about 15%, much slower than the set schedule due to many problems in site clearance. Some households in Cua Nam and Quang Trung Doi Cung wards have not agreed with the compensation plan.

Các đơn
Workers are making stone embankments under the lake.

Specifically, Cua Nam ward still has 45 households whose compensation plan has not been approved, Quang Trung ward still has 3 households who have not accepted the compensation plan, Doi Cung ward still has 5 households who have not accepted the plan due to low compensation prices for land and assets, and are applying for resettlement land.

The city has currently arranged 100 resettlement lots in Quan Bau for households.

Discussing the progress of site clearance, Mr. Ha Thanh Tinh - Vice Chairman of Vinh City People's Committee said: The city is re-planning the area of ​​resettlement plots to match the area of ​​land recovered from the affected people. The city always creates conditions for the resettled people to have better conditions than their old place of residence.

Kè
Pour concrete into the bottom of the lake (water storage sections).

The project to renovate and upgrade the Citadel Moat is expected to be completed in the first quarter of 2017 with the main items: Dredging, building retaining walls along both banks of the ditch, building a sewer line to collect wastewater, building a new ditch line inside the Citadel and a ditch line outside the Citadel, building 6 discharge gates and 6 wastewater separation manholes.

To separate domestic wastewater from residential areas outside from flowing into the ditch around the Citadel, the project will build along the length of the ditch around the Citadel a sewer line with a diameter of DN300-D800 to collect wastewater to a newly built wastewater pumping station with a capacity of 3,100 m3/day/night at Cua Nam Lake.

Phối cảnh dự án cải tạo, nâng cấp Hào thành cổ
Perspective of the project to renovate and upgrade the ancient citadel