Economy

Focus efforts on repairing the cracked road along the Vinh riverbank as soon as possible.

Quang An October 1, 2025 13:00

By noon on October 1st, forces were still working diligently to implement various solutions to address the road cracks along Vinh Giang riverbank in Truong Vinh ward, determined to ensure the safety of the residential area further inland.

Clip: Quang An
bna_5(1).jpg
On the morning of October 1st, due to the influence of the remnants of Typhoon No. 10, the Vinh River's water level rose, causing a large crack to appear on the Vinh Giang road along the Vinh River, in the Truong Vinh ward. Photo: Quang An
bna_4a.jpg
Immediately after the incident occurred, local authorities, in coordination with relevant agencies, mobilized forces to erect barricades and warning signs, and temporarily halted traffic on this section of road to ensure safety. Photo: Quang An
bna_2(1).jpg
Simultaneously, all available resources and personnel are being mobilized to rectify the problem as quickly as possible. Mr. Hoang Quoc Truong, Director of the Road Maintenance Management Board, Nghe An Department of Construction, stated: The immediate plan is to block the flow of water from the Vinh River into the reservoir of the southern pumping station and the residential area, reinforcing it with rocks, soil, sand, and concrete blocks to prevent water from overflowing. At the same time, water will be pumped out of the reservoir to limit flooding in the Vinh Tan and former Trung Do areas. (Photo: Quang An)
bna_3(1).jpg
Mr. Truong also stated that, in the long term, the unit will study options for investing in rebuilding the drainage system and restoring the road surface to its original condition to ensure sustainability and prevent further erosion and cracking. Photo: Quang An
bna_2b.jpg
Truong Vinh ward also mobilized more than 200 officials, workers, and militia members along with heavy machinery to reinforce the area. Photo: Quang An
bna_3a.jpg
Bags of soil and sand are being continuously supplied to prevent water from flowing into residential areas. Photo: Quang An
bna_3b.jpg
Militia forces used netting to reinforce the embankment of rocks and soil, ensuring its stability. Photo: Quang An
bna_7.jpg
Numerous excavators and cranes were deployed to the scene, speeding up the remediation process. Photo: Quang An
bna_9.jpg
Trucks carrying rocks are continuously being supplied to the fracture site. Alongside the repair work, authorities are also advising people to avoid walking or gathering near the fractured area to prevent danger. Photo: Quang An
bna_1b(1).jpg
Due to the temporary closure of the road, vehicles had to use alternative routes, complying with traffic diversion instructions from authorities. Photo: Quang An
Đồng chí Hoàng Phú Hiền - Phó Chủ tịch UBND tỉnh trực tiếp chỉ đạo phương án khắc phục. Ảnh: Quang An
On the morning of October 1st, Mr. Hoang Phu Hien, Vice Chairman of the Provincial People's Committee, directly supervised the remediation efforts at the scene. By noon the same day, the Vinh Giang road crack incident was still being addressed by various forces, determined to ensure the safety of the residential area. Photo: Quang An
0 0 0