Two key projects in Nghe An have good disbursement progress
(Baonghean.vn) - In the first 6 months of the year, Nghe An's public investment disbursement rate is still low, only reaching 30.27% of the plan, however, there are two key projects with good disbursement rates.
The report of the Provincial People's Committee said: As of June 20, 2022, the total public investment plan has disbursed VND 2,841,985 billion, reaching 30.27% of the plan.
Specifically, each source of capital is as follows:Public investment capitalCentralized provincial management: Disbursed 1,536,696 billion VND, reaching 26.36% of the plan. Of which: Central budget disbursed 1,313,118 billion VND, reaching 30.74% of the plan. (Domestic capital disbursed 1,274,693 billion VND, reaching 33.64%; Foreign capital disbursed 38,425 billion VND, reaching 7.97%); Local budget disbursed 223,578 billion VND, reaching 14.35% of the plan.
Land use revenue from district and commune budgets according to decentralization and provincial budgets to allocate funds for site clearance, debt repayment, and projects re-borrowed from foreign government loans: Disbursed 1,305,289 billion VND, reaching 40.22% of the plan.
The total capital plan of previous years extended to 2022 is 569.99 billion VND. As of June 20, 2022, the extended capital plan has disbursed 117.301 billion VND, reaching 20.58% of the extended plan.
According to the report, there are two key projects with good disbursement progress, namely the Coastal Road Project and the Muong Xen - Ta Do - Khe Kien Road Project.
![]() |
Construction of coastal road through Nghi Loc. Photo: Tran Chau |
Coastal Road Project from Nghi Son (Thanh Hoa) to Cua Lo (Nghe An) from Km7 - Km76, site clearance work has been handed over 29.76 km/59.9 km, reaching 49.68%. Construction work is focusing on implementing, speeding up the progress of sections with available site clearance, currently 7/8 bridges, sea walls, roadbeds, structural components have been constructed,...
The total capital allocated to this project is 1,620 billion VND, of which: The concentrated public investment plan for 2022 is 1,070 billion VND, the plan for 2021 extended to 2022 is 450 billion VND. As of June 20, 2022, 1,029.16 billion VND has been disbursed, reaching 63.53%; of which: The disbursement plan for 2022 is 892.1 billion VND, reaching 83.37% (central budget 822.063 billion VND, reaching 82.20%; local budget 70 billion VND, reaching 100%); The disbursement plan for 2021 extended to 2022 is 109.834 billion VND, reaching 24.41%.
Department of Transport said:Coastal roadis a key project, expected to complete site clearance for agricultural land in June 2022, the section through forest land in July 2022, residential land, garden land without relocation and resettlement arrangement in September 2022 and focus on directing contractors to speed up construction progress of sections with available site.
The second best disbursement project is the Muong Xen - Ta Do - Khe Kien road. The project has currently implemented site clearance for the Km7 - Km26 section, with the site handed over reaching 17.3 km/18 km, reaching 96.11%. The contractors have handed over the project for use in December 2021. The remaining sections have been completed, and are currently completing the paperwork for acceptance and handover of the project to prepare for use.
![]() |
Since the beginning of the year, the price of iron and steel materials has continuously increased, affecting the progress of many basic construction projects. Photo: Thanh Yen |
Regarding the disbursement of the 2022 capital plan for Muong Xen - Ta Do - Khe Kien road: The assigned plan is 175.23 billion VND, as of June 20, 2022, 74.789 billion VND has been disbursed from the central budget, reaching 42.68%.
In some localities, disbursement has been given attention. For Nghi Loc district, disbursement is considered an important task, so the district has strengthened public debt control, continued to mobilize internal resources and other resources to invest in building infrastructure projects, and integrated the construction of new rural projects.
The total construction investment value in the first 6 months of 2022 of Nghi Loc district reached 405 billion VND, of which the estimated concentrated construction investment value is 199 billion VND (with over 130 projects, transitional project items, and newly started projects).
The leader of Nghi Loc District People's Committee said: The district focuses on directing the acceleration of the implementation of projects that have been allocated capital according to the plan. Continue to accelerate the construction progress of some transitional works such as: The road from hamlet 2 to hamlet 6, Nghi Thuan commune, the district stadium, the main road of Quan Hanh town, My Hoa spillway, Nghi My commune; land infrastructure in Nghi Thuan, Nghi Yen, Nghi Tien, Nghi Phong communes,...
In Nghia Dan, in the first 6 months of the year, the construction of construction projects was accelerated. The district organized the acceptance and handover of 48 projects, including: 6.3 km of asphalt roads, 32 km of cement concrete roads, etc. Construction of a number of projects was organized such as: Road for economic development in the Western Nghe An region - phase 2; Road for flood relief, ensuring security and defense in communes from Nghia Lam to Nghia Binh, Nghia Dan district - phase 3; Road for transportation and development of raw material areas in Nghia Dan district (ADB).
As of June 20, 2022, there are still 17 districts and towns and 37 investment units disbursing below the average level of the province (26.36%), of which 01 district and 27 investment units have not disbursed.
Notably, there are a number of agencies and units that have not yet disbursed funds, including Do Luong district and 27 investment units.
Many districts have low disbursement rates: Quynh Luu (16.69%), Quy Hop (14.49%), Vinh City (14.03%), Tuong Duong (12.73%), Hung Nguyen (10.35%), Thanh Chuong (8.6%), Nam Dan (6.67%), Cua Lo Town (6.67%), Quy Chau (4.6%), Dien Chau (4.31%), Thai Hoa Town (3.1%)...