(Baonghean.vn) - The construction of the high-end residential and commercial service building project by Bao Son Construction and Tourism Group at 126 Nguyen Sy Sach Street, Hung Phuc Ward, Vinh City has caused cracks and subsidence in the houses of some households in Vinh Phuc block. Faced with this reality, the investor has coordinated with relevant levels and sectors to organize surveys, field investigations, and meetings with households to support nearly 3.2 billion VND.

Dự án bảo Sơn
Construction of a high-end residential and commercial service building at 126 Nguyen Sy Sach Street, Hung Phuc Ward - Vinh City.

Mr. Nguyen Trong Dan - Head of Vinh Phuc Block said: "The 31-storey building project of Bao Son Group started in March 2016 and during the construction process, especially in July - August 2016, the basement foundation stage, bored pile drilling and water pumping... affected many houses of people in the area adjacent to the project. The investor coordinated with related departments to organize meetings, dialogue with people and agreed on a very satisfactory support and compensation plan, which was highly approved by the people".

Đại diện chủ đầu tư, đơn vị thi công và khối Vinh Phúc bàn phương án hỗ trợ cho người dân
Representatives of the investor, the construction unit and Vinh Phuc block discussed support plans for people affected by project construction.

It is known that during the construction of the project, 21 households were affected, so based on the actual situation of each household, the investor and the residents negotiated and proposed a support plan. However, because 6 households were severely affected, the investor coordinated with the Construction Quality Inspection Center (Nghe An Department of Construction) to conduct an on-site inspection.

  v
After receiving support money, households in Vinh Phuc block proceeded to repair affected items.

Mr. Tran Quoc Bao - Director of the Construction Quality Inspection Center said: "Immediately after the investor raised the issue of assessing the quality of 6 houses of people affected by the architecture and structure of the housing project, the Center focused on human resources and modern equipment to conduct inspection and assess the level of impact.

Accordingly, the Center conducted surveys, made outlines, made estimates... according to the correct procedures and used modern equipment and machinery such as: concrete reinforcement ultrasound machine, total station, centrifuge, three-link throwing machine, multi-function testing machine... After 14 days of implementation, the Center had the results sent to the investor and this is the basis for implementing support and compensation work for households affected by the architecture and structure of housing projects.

Khách hàng đến Sàn giao dịch BĐS Phú Đạt mua nhà ở tại dự án của Bảo Sơn
Customers come to Phu Dat Real Estate Exchange to buy houses at Bao Son project.

After agreeing on the support plan and completing the procedures in accordance with regulations, the investor proceeded to support the people and the first household received the support money on November 22, 2016 and the last household received the support money on December 15, 2016. Thus, in a very short time, the investor completed the support payment for 21 affected households with a total amount of nearly 3.2 billion VND.

Mr. Nguyen Trung Son at No. 3, Lane 169, Hecman Street, Hung Phuc Ward said: “My family’s house is near the project, so the foundation and walls are cracked. After the investor and my family agreed on a support plan, on November 23, my family received 100 million VND. The investor fulfilled its commitment very well, providing timely and adequate support to the people.”