Checking the progress of Yen Xuan bridge construction investment project
(Baonghean.vn) - On the afternoon of October 30, comrade Le Ngoc Hoa, Vice Chairman of the Provincial People's Committee, worked with Hung Nguyen and Nam Dan districts and Traffic Construction Corporation 4 on the construction progress of the Yen Xuan bridge project.
![]() |
Comrade Le Ngoc Hoa, Vice Chairman of the Provincial People's Committee, inspected the project's construction progress at the site.South and North banks of Yen Xuan bridge project. |
Up to this point, the site preparation work has been completed, including: mine clearance, traffic regulation and assurance on waterways; construction units have also gathered equipment, machinery and human resources to the site and implemented a number of items such as geological survey drilling.
To construct Yen Xuan Bridge, it will be necessary to clear the land with a total area of nearly 14 hectares. Currently, the construction unit is facing some problems in the work of clearing the land, building public roads...
![]() |
Comrade Le Ngoc Hoa, Vice Chairman of the Provincial People's Committee, requested relevant levels, sectors and localities to create favorable conditions for investors to speed up project progress. |
![]() |
Investor representative reports on project implementation process. |
At the working session with the leaders of Nam Dan and Hung Nguyen districts and Traffic Construction Corporation 4 (investor and contractor), Mr. Le Ngoc Hoa, Vice Chairman of the Provincial People's Committee, acknowledged and highly appreciated the active coordination between the local government and the investor in implementing the project, especially the site clearance work.
![]() |
Nam Dan district leaders report on land acquisition and clearance |
In order to complete the Yen Xuan bridge construction project and put it into use by the end of 2016, the Vice Chairman of the Provincial People's Committee requested the Traffic Construction Corporation 4 - the investor and contractor - to mobilize maximum human resources and modern machinery and equipment to speed up the construction progress. The investor needs to continue to promote site clearance, promptly resolve difficulties and problems of the people and localities, and promptly support affected projects. During the construction process, it is necessary to comply with security and order, labor safety, and ensure the quality of the project...
Hoang Vinh