Society

Hanoi power outage schedule on November 15, 2024

Quoc Duong November 14, 2024 15:37

According to Hanoi Electricity, there is a scheduled power outage in districts in Hanoi on November 15, 2024.

The latest information on power outage schedule in Hanoi areas on Friday, November 15, 2024 is updated from the Hanoi Electricity portal.

There can be many reasons for power outages in Hanoi. Factors that can cause power outages include natural disasters, floods, storms, or the management unit carrying out repairs and maintenance of power grid lines.

Lịch cúp điện hà nội

This is the power outage schedule in the plan of the power companies. Depending on the weather situation, the plan of the power units... the power outage schedule can be adjusted and postponed in some places.

Hanoi power outage schedule on November 15, 2024

ElectricityTimeAreaReasonStatus
Long Bien Electricity
From 07:30 to 14:30
Customer of Residential Group No. 17, Gia Thuy Ward
Serving the renovation and upgrading of the power grid
Approved
Gia Lam Electricity
From 09:00 to 11:00
Thanh Dong Tien Company Limited
Serving the renovation and upgrading of the power grid
Approved
Gia Lam Electricity
From 09:30 to 11:30
Hanoi Mining Chemical Materials Company
Serving the renovation and upgrading of the power grid
Approved
Gia Lam Electricity
From 09:00 to 11:00
Center for testing, verification and consulting on the quality of agricultural, forestry and fishery products
Serving the renovation and upgrading of the power grid
Approved
Ba Dinh Electricity
From 13:00 to 14:00
No (low voltage transmission)
Serving the renovation and upgrading of the power grid
Approved
Ba Dinh Electricity
From 14:00 to 15:00
No (low voltage transmission)
Serving the renovation and upgrading of the power grid
Approved
Ba Dinh Electricity
From 15:00 to 16:30
No (low voltage transmission)
Serving the renovation and upgrading of the power grid
Approved
Ba Dinh Electricity
From 08:00 to 12:00
No (low voltage transmission)
Serving the renovation and upgrading of the power grid
Approved
Ba Dinh Electricity
From 14:00 to 15:30
No (low voltage transmission)
Serving the renovation and upgrading of the power grid
Approved
Ba Dinh Electricity
From 16:00 to 17:30
No (low voltage transmission)
Serving the renovation and upgrading of the power grid
Approved
Hoan Kiem Electricity
From 05:00 to 06:30
From number 1 to number 21, from number 2 to number 24 Lo Ren street; from number 3 to number 85, from number 4 to number 86 Thuoc Bac street.
Serving the renovation and upgrading of the power grid
Approved
Hoan Kiem Electricity
From 06:30 to 08:00
From number 13 to 79, from number 22 to 76 Hang Non, 36 to 66,49 to 71 Hang Thiec, 48 to 52, 41, 47, 65 Hang Dieu, 33 to 43 Hang Thiec, 38 Hang Thiec
Serving the renovation and upgrading of the power grid
Approved
Hoan Kiem Electricity
From 11:00 to 12:30
From number 41 to number 59, from number 48 to number 78 Bat Su street, from number 85 to number 95, from number 54 to number 72, from number 79 to number 81 Hang Ga street; from number 89 to number 91 Thuoc Bac. Hang Phen street.
Serving the renovation and upgrading of the power grid
Approved
Hoan Kiem Electricity
From 09:30 to 11:00
From No. 1 to No. 21, from No. 2 to No. 10 + 20 Hang Bo Street. From No. 1 to No. 35, from No. 2 to No. 58 Hang Dao Street, from No. 145 to No. 179, from No. 112 to No. 142 Hang Bac Street
Serving the renovation and upgrading of the power grid
Approved
Hoan Kiem Electricity
From 14:30 to 16:00
From No. 1 to No. 15, from No. 2 to No. 26 Hang Quat Street. From No. 23 to No. 37, from No. 40 to No. 56 Hang Can Street; From No. 1 to No. 31, from No. 2 to No. 48 Luong Van Can Street; from No. 23 to No. 35 Hang Bo Street, No. 47, 51 Hang Bo Street.
Serving the renovation and upgrading of the power grid
Approved
Hoan Kiem Electricity
From 08:00 to 09:30
From No. 2 to No. 70 Hang Buom Street
Serving the renovation and upgrading of the power grid
Approved
Hai Ba Trung Electricity
From 07:30 to 09:30
No - Low voltage load transferred to Dai Co Viet 1A station
Serving the renovation and upgrading of the power grid
Approved
Hai Ba Trung Electricity
From 08:00 to 10:00
No - Low voltage load transferred to Tran Binh Trong station
Serving the renovation and upgrading of the power grid
Approved
Hai Ba Trung Electricity
From 08:30 to 10:30
No - Low voltage load transferred to Hue 14 station
Serving the renovation and upgrading of the power grid
Approved
Hai Ba Trung Electricity
From 14:30 to 17:30
No - Low voltage load transferred to Lac Trung 1 station
Serving the renovation and upgrading of the power grid
Approved
Hai Ba Trung Electricity
From 14:00 to 16:00
No - Low voltage load transferred to Minh Khai 12 station
Serving the renovation and upgrading of the power grid
Approved
Hai Ba Trung Electricity
From 14:00 to 16:00
No - Low voltage load transferred to Thanh Luong 20 station
Serving the renovation and upgrading of the power grid
Approved
Dong Da Electricity
From 16:00 to 18:00
+ Hanoi Medical University-1 Ton That Tung (Student Dormitory) + Hanoi Medical University-1 Ton That Tung
Serving the renovation and upgrading of the power grid
Approved
Bac Tu Liem Electricity
From 07:00 to 11:00
All stations TT2 Giao Luu City, TT3 Giao Luu City, TT4 Giao Luu City
Serving the renovation and upgrading of the power grid
Approved
Thanh Xuan Electricity
From 07:00 to 09:00
House B8 Thanh Xuan Bac Collective, House B7 Thanh Xuan Bac Collective, 101 to 112 House B8 Thanh Xuan Bac Collective (4 stairs B8), Staircase 1 + Staircase 3 House B7 Thanh Xuan Bac Collective
Serving the renovation and upgrading of the power grid
Approved
Thanh Xuan Electricity
From 09:00 to 11:00
Alley 86/16 To Vinh Dien street. School 10 (Capital Military Region). Alley 86 To Vinh Dien street. Alley 63, from year 78 to year 84, year 48 to year 60 + beginning of alley 48 To Vinh Dien street
Serving the renovation and upgrading of the power grid
Approved
Thanh Xuan Electricity
From 14:00 to 16:00
Sn 21 Nguyen Viet Xuan to column XT station Hoang Van Thai 4. Alley 2, lane 2/10 + column before Sn 14, lane 20/8 Nguyen Viet Xuan. Alley 149 Nguyen Ngoc Nai + lane 20/8 Nguyen Viet Xuan. Alley 62 Nguyen Viet Xuan
Serving the renovation and upgrading of the power grid
Approved
Thanh Xuan Electricity
From 12:00 to 14:00
Vietnam Puppetry Theater No. 361 Truong Chinh
Serving the renovation and upgrading of the power grid
Approved
Hoang Mai Electricity
From 05:30 to 12:30
Part of Vinh Hung ward, Hoang Mai, Hanoi
Serving the renovation and upgrading of the power grid
Approved
Ha Dong Electricity
From 05:30 to 12:30
Song Nhue Apartment Building
Serving the renovation and upgrading of the power grid
Approved
Ha Dong Electricity
From 06:00 to 13:00
Song Da 2 Joint Stock Company, Song Da 11-3 Factory, 7-storey Building, Lane 1 Nguyen Khuyen, Branch of Song Da Trading and Transport Joint Stock Company in Ha Tay
Serving the renovation and upgrading of the power grid
Approved
Son Tay Power
From 07:00 to 12:00
Part of Son Dong Commune
Serving the renovation and upgrading of the power grid
Approved
Son Tay Power
From 10:00 to 12:00
Part of Xuan Khanh ward
Serving the renovation and upgrading of the power grid
Approved
Son Tay Power
From 08:30 to 10:00
Part of Son Dong commune
Serving the renovation and upgrading of the power grid
Approved
Ba Vi Electricity
From 06:30 to 14:30
Customers in Tien Phong commune
Serving the renovation and upgrading of the power grid
Approved
Ba Vi Electricity
From 06:30 to 14:30
Part of customers belong to Tay Dang Town (Lai Bo 3), Tien Phong (Kim Bi 1+2)
Serving the renovation and upgrading of the power grid
Approved
Ba Vi Electricity
From 07:00 to 15:00
Part of customers in Tong Bat commune, Son Da
Serving the renovation and upgrading of the power grid
Approved

Above is the power outage schedule for areas in Hanoi on November 15, 2024. Currently, there is no information about power outages in some other locations. Nghe An Newspaper will regularly update the latest and most accurate information about the power outage schedule in Hanoi for readers to follow.