According to Nghe An Electricity, there is a scheduled power outage in districts and cities in Nghe An province on December 21, 2024.
The latest information on power outage schedule in Nghe An on Saturday, December 21, 2024 is updated from the Northern Electricity portal.
There can be many reasons for power outages in Nghe An. Factors that can cause power outages include natural disasters, floods, storms, or the management unit carrying out repairs and maintenance of power grid lines.

This is the power outage schedule in the plan of the power companies. Depending on the weather situation, the plan of the power units... the power outage schedule can be adjusted and postponed in some places.
Nghe An power outage schedule on December 21, 2024
Electricity:Cua Lo Town Electricity
Time:From 07:00 to 15:00
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nam Dan Power
Time:From 06:00 to 18:00
Area:Nam Giang Commune
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nam Dan Power
Time:From 06:00 to 07:30
Area:Nam Giang Commune
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nam Dan Power
Time:From 16:00 to 18:00
Area:Nam Giang Commune
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghia Dan - Thai Hoa Power Company
Time:From 08:00 to 10:00
Area:Nghia Loc 16
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghia Dan - Thai Hoa Power Company
Time:From 08:00 to 10:00
Area:Hong Thang
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghia Dan - Thai Hoa Power Company
Time:From 10:00 to 12:00
Area:Quang Phong 3
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghia Dan - Thai Hoa Power Company
Time:From 10:00 to 12:00
Area:Nghia Loc 19
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghia Dan - Thai Hoa Power Company
Time:From 13:00 to 15:00
Area:Nghia Loc 20
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghia Dan - Thai Hoa Power Company
Time:From 13:00 to 15:00
Area:Quang Phong 5
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghia Dan - Thai Hoa Power Company
Time:From 15:00 to 17:00
Area:Boi Village 2
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Hung Nguyen Electricity
Time:From 05:30 to 06:00
Area:TTHN, Hung Thai, Hung Tan, Hung Thong, Hung Xa, Hung Long
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Hung Nguyen Electricity
Time:From 05:30 to 18:00
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Hung Nguyen Electricity
Time:From 05:30 to 06:30
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Hung Nguyen Electricity
Time:From 05:30 to 18:00
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Hung Nguyen Electricity
Time:From 08:00 to 11:00
Area:KH after TBA No. 2 Hung Chinh
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Hung Nguyen Electricity
Time:From 17:00 to 18:00
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Hung Nguyen Electricity
Time:From 17:30 to 18:00
Area:TTHN, Hung Thai, Hung Tan, Hung Thong, Hung Xa, Hung Long
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghi Loc Power
Time:From 06:00 to 15:30
Area:Nghi Xa, Nghi Tan, Nghi Quang, Khanh Hop
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghi Loc Power
Time:From 06:30 to 08:30
Area:Nghi Hop 5 Substation Road 480E15. 8
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghi Loc Power
Time:From 07:00 to 12:00
Area:Substation No. 7 Nghi Quang Road 480 E15. 8
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghi Loc Power
Time:From 07:00 to 14:00
Area:Nghi Quang 1 Substation Line 480E15.8
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghi Loc Power
Time:From 07:00 to 14:00
Area:Nghi Quang 7 Substation Line 480E15.8
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghi Loc Power
Time:From 07:30 to 11:30
Area:TBA No. 2 Nghi Lam DZ373E15. 1
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghi Loc Power
Time:From 08:30 to 10:00
Area:At Sunny 2 Substation Road 483E15. 51
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghi Loc Power
Time:From 08:30 to 10:00
Area:Nghi Kieu 9 Station Road 376E15. 4
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghi Loc Power
Time:From 13:30 to 17:00
Area:Substation No. 3 Nghi Quang Road 480 E15. 8
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Nghi Loc Power
Time:From 15:30 to 16:00
Area:Khanh Hop
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Chau Electricity
Time:From 08:00 to 11:00
Area:Lam Village
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Chau Electricity
Time:From 08:00 to 17:00
Area:Chau Binh
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Chau Electricity
Time:From 09:30 to 12:00
Area:Tri Le Market
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Hop Electricity
Time:From 07:00 to 07:30
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Hop Electricity
Time:From 07:00 to 07:30
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Hop Electricity
Time:From 07:30 to 10:30
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Hop Electricity
Time:From 07:30 to 10:30
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Hop Electricity
Time:From 10:30 to 11:30
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Hop Electricity
Time:From 10:30 to 11:30
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Hop Electricity
Time:From 13:30 to 16:30
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quy Hop Electricity
Time:From 13:30 to 16:30
Area:Power outage in some areas
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quynh Luu Electricity
Time:From 06:00 to 14:00
Area:Quynh Hong and Cau Giat area
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Quynh Luu Electricity
Time:From 06:00 to 14:00
Area:Quynh Tho commune
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
------------------------------------------------------
Electricity:Vinh City Electricity
Time:From 05:00 to 17:30
Area:Nghi Phu
Reason:Testing, repairing and maintaining medium and low voltage power grid lines
Status:Approved
Above is the power outage schedule for areas in Nghe An province on December 21, 2024. Currently, some other locations have no information about power outages. Nghe An Newspaper will regularly update the latest and accurate information about the power outage schedule in Nghe An for readers to follow.
Instructions for looking up power outage schedule in Nghe An
There are many ways to look up power outage schedules, including the following:
Follow Nghe An power outage schedule at Nghe An newspaper
Nghe An Newspaper will regularly update the latest and accurate information about power outage schedule in Nghe An for readers' convenience.
Look up power outage schedule on EVN Northern website
To look up the power outage schedule in Nghe An today and the coming days, everyone can access the Northern EVN website at the linkhttps://cskh.npc.com.vn/. Select itemSearch -> Power outage schedule -> Search by power company - Electricityto capture information
.png)
Search on EVN Customer Service application
Everyone downloads the EVN Customer Service application to their phone and registers for an account. Next, select the “Power outage schedule” section to see the exact Hanoi power outage schedule right on your phone.