Nghe An power outage schedule on November 5, 2024
According to Nghe An Electricity, there is a scheduled power outage in districts and cities in Nghe An province on November 5, 2024.
The latest information on power outage schedule in Nghe An on Tuesday, November 5, 2024 is updated from the Central Electricity portal.
There can be many reasons for power outages in Nghe An. Factors that can cause power outages include natural disasters, floods, storms, or the management unit carrying out repairs and maintenance of power grid lines.

This is the power outage schedule planned by the power companies. Depending on the weather, the power unit's plans... the power outage schedule can be adjusted and postponed in some places.
Nghe An power outage schedule on November 5, 2024
Unit | Time | Area | Reason | Status |
Nghia Dan-Thai Hoa Power Company | From 05:30 to 07:30 | Nghia Thuan, Nghia Loc | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Nghia Dan-Thai Hoa Power Company | From 05:30 to 19:00 | Nghia Loc commune | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Nghia Dan-Thai Hoa Power Company | From 08:00 to 10:00 | Nghia Thinh Commune | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Nghia Dan-Thai Hoa Power Company | From 08:00 to 10:00 | Society | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Nghia Dan-Thai Hoa Power Company | From 08:30 to 17:00 | Tan Son Commune | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Nghia Dan-Thai Hoa Power Company | From 09:30 to 12:00 | Nghia Thinh Commune | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Nghia Dan-Thai Hoa Power Company | From 09:30 to 12:00 | Nghia Phu Commune | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Nghia Dan-Thai Hoa Power Company | From 17:00 to 19:00 | Nghia Thuan, Nghia Loc | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Hung Nguyen Electricity | From 07:30 to 11:00 | TBA KCL X5 HUNG CHINH | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Hung Nguyen Electricity | From 08:00 to 09:30 | TBA T2 HUNG TAN | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Hung Nguyen Electricity | From 10:00 to 11:30 | TBA T7 HUNG LONG | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Hung Nguyen Electricity | From 13:30 to 15:00 | TBA T7 HUNG PHUC | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Hung Nguyen Electricity | From 15:30 to 17:00 | TBA DC T9 HUNG THINH | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Do Luong Electricity | From 07:30 to 13:00 | Customer TBA VAN SON 4 | Testing, repairing and maintaining medium and low voltage power grid lines | Approved |
Above is the power outage schedule for areas in Nghe An province on November 5, 2024. Currently, some other locations have no information about power outages. Nghe An Newspaper will regularly update the latest and accurate information about the power outage schedule in Nghe An for readers to follow.