Power outage schedule in Hanoi on December 10, 2024
According to Hanoi Electricity, there is a scheduled power outage in districts in Hanoi on December 10, 2024.
The latest information on power outage schedule in Hanoi areas on Sunday, December 10, 2024 is updated from the Hanoi Electricity portal.
There can be many reasons for power outages in Hanoi. Factors that can cause power outages include natural disasters, floods, storms, or the management unit carrying out repairs and maintenance of power grid lines.

This is the power outage schedule in the plan of the power companies. Depending on the weather situation, the plan of the power units... the power outage schedule can be adjusted and postponed in some places.
Hanoi power outage schedule on December 10, 2024
Electricity:Soc Son Power Company
Time:From 08:30 to 09:45
Area:Part of Thanh Xuan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 09:30 to 10:45
Area:Part of Thanh Xuan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 06:45 to 12:15
Area:Part of Phu Linh commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 06:45 to 12:15
Area:Part of Phu Linh commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 05:00 to 06:30
Area:Part of Tien Duong commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 14:30 to 16:15
Area:Part of Tien Duong commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 05:00 to 06:30
Area:Part of Tien Duong commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 14:30 to 16:15
Area:Part of Tien Duong commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 05:00 to 06:30
Area:Part of Tien Duong commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 14:30 to 16:15
Area:Part of Tien Duong commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 05:00 to 06:30
Area:Part of Tien Duong commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 06:30 to 14:30
Area:At BT Binh Duong company
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 14:30 to 16:15
Area:Part of Tien Duong commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 05:00 to 06:30
Area:Part of Tien Duong commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Anh Electricity Company
Time:From 14:30 to 16:15
Area:Part of Tien Duong commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Gia Lam Power Company
Time:From 09:00 to 11:00
Area:Vinh Oanh Company Limited
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Gia Lam Power Company
Time:From 09:30 to 11:00
Area:Minh Thang Steel Production and Trading Company Limited
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Gia Lam Power Company
Time:From 08:00 to 10:00
Area:277 Hanoi Packaging Joint Stock Company
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Gia Lam Power Company
Time:From 10:00 to 12:00
Area:277 Hanoi Packaging Joint Stock Company
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Tri Power Company
Time:From 09:00 to 10:15
Area:Artificial particle board manufacturing company
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Tri Power Company
Time:From 12:00 to 13:15
Area:Huong Dung Company Customer
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Tri Power Company
Time:From 07:30 to 08:45
Area:Dai Thanh Company Customer
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Tri Power Company
Time:From 09:00 to 10:15
Area:Artificial particle board manufacturing company
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Tri Power Company
Time:From 10:30 to 11:45
Area:Freight Transport Company
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 05:00 to 12:00
Area:Part of Mai Dong ward, Hoang Mai district
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 16:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 15:30 to 18:30
Area:From number 2 to number 30 Ba Trieu street, number 23 Ba Trieu street.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 15:30 to 18:30
Area:From number 2 to number 30 Ba Trieu street, number 23 Ba Trieu street.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 15:30 to 18:30
Area:From number 2 to number 30 Ba Trieu street, number 23 Ba Trieu street.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 15:30 to 18:30
Area:From number 2 to number 30 Ba Trieu street, number 23 Ba Trieu street.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 12:30 to 15:30
Area:No. 64 Luong Van Can Street. From No. 5 to No. 37 Hang Hanh Street. No. 11 Bao Khanh Alley
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 08:00 to 11:00
Area:From house number 1 to house number 11, from house number 2 to house number 6 Ly Quoc Su street, from house number 1 to house number 67 Hang Bong street; From house number 1 to house number 11, from house number 6 to house number 26 Chan Cam street
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 08:00 to 11:00
Area:From house number 1 to house number 11, from house number 2 to house number 6 Ly Quoc Su street, from house number 1 to house number 67 Hang Bong street; From house number 1 to house number 11, from house number 6 to house number 26 Chan Cam street
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 12:30 to 15:30
Area:No. 64 Luong Van Can Street. From No. 5 to No. 37 Hang Hanh Street. No. 11 Bao Khanh Alley
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 05:00 to 10:00
Area:The whole Tho Xuong Street; From house number 2 to number 40 Au Trieu Street474E1.52
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 08:00 to 11:00
Area:From house number 1 to house number 11, from house number 2 to house number 6 Ly Quoc Su street, from house number 1 to house number 67 Hang Bong street; From house number 1 to house number 11, from house number 6 to house number 26 Chan Cam street
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoan Kiem Electricity Company
Time:From 12:30 to 15:30
Area:No. 64 Luong Van Can Street. From No. 5 to No. 37 Hang Hanh Street. No. 11 Bao Khanh Alley
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hai Ba Trung Power Company
Time:From 08:00 to 10:00
Area:No - Low voltage load switched to generator
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hai Ba Trung Power Company
Time:From 14:00 to 15:30
Area:No - Low voltage load switched to generator
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Da Electricity Company
Time:From 07:00 to 12:00
Area:Building B1, B2, B3, B4, University of Medicine and Pharmacy, Ton That Tung Street
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Da Electricity Company
Time:From 07:00 to 12:00
Area:Building B1, B2, B3, B4, University of Medicine and Pharmacy, Ton That Tung Street
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dong Da Electricity Company
Time:From 07:00 to 12:00
Area:Building B1, B2, B3, B4, University of Medicine and Pharmacy, Ton That Tung Street
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 09:45 to 10:45
Area:From 163 to 233 Pham Van Dong, Mai Dich ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 11:00 to 12:00
Area:Apartment N105 Nguyen Phong Sac - Dich Vong ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 14:00 to 15:00
Area:2.5ha resettlement area, Dich Vong Hau ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 15:15 to 16:15
Area:Lane 130 Xuan Thuy, Phan Van Truong Street, Dich Vong Hau Ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 09:45 to 10:45
Area:From 163 to 233 Pham Van Dong, Mai Dich ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 09:45 to 10:45
Area:From 163 to 233 Pham Van Dong, Mai Dich ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 11:00 to 12:00
Area:Apartment N105 Nguyen Phong Sac - Dich Vong ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 14:00 to 15:00
Area:2.5ha resettlement area, Dich Vong Hau ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 15:15 to 16:15
Area:Lane 130 Xuan Thuy, Phan Van Truong Street, Dich Vong Hau Ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 11:00 to 12:00
Area:Apartment N105 Nguyen Phong Sac - Dich Vong ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 11:00 to 12:00
Area:Apartment N105 Nguyen Phong Sac - Dich Vong ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 14:00 to 15:00
Area:2.5ha resettlement area, Dich Vong Hau ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Cau Giay Power Company
Time:From 15:15 to 16:15
Area:Lane 130 Xuan Thuy, Phan Van Truong Street, Dich Vong Hau Ward - CG - HN
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 05:30 to 12:00
Area:Part of Hong Ky commune
Reason:Serving the renovation and upgrading of the power grid
Status:Postpone
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 06:45 to 12:15
Area:Part of Phu Linh commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 07:30 to 08:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 07:30 to 08:45
Area:Part of Thanh Xuan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 08:30 to 09:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 15:30 to 16:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 05:30 to 12:00
Area:Part of Hong Ky commune
Reason:Serving the renovation and upgrading of the power grid
Status:Postpone
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 06:45 to 12:15
Area:Part of Phu Linh commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 08:30 to 09:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 08:30 to 09:45
Area:Part of Thanh Xuan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 09:30 to 10:45
Area:Part of Thanh Xuan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 10:30 to 11:45
Area:Part of Tan Dan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 13:30 to 14:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 14:30 to 15:45
Area:Part of Tan Dan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 10:30 to 11:45
Area:Part of Tan Dan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 13:30 to 14:45
Area:Part of Tan Dan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 07:30 to 08:45
Area:Part of Thanh Xuan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 08:30 to 09:45
Area:Part of Thanh Xuan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 09:30 to 10:45
Area:Part of Thanh Xuan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 05:00 to 12:00
Area:Part of Mai Dong ward, Hoang Mai district
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:30 to 11:30
Area:MBA1, MBA2 Dinh Cong 12
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 16:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 12:00
Area:MBA1, MBA2 Mai Dong College
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 13:30 to 16:30
Area:DIZEL Thanh Lan
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 14:00 to 17:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 16:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:00 to 11:00
Area:MBA1, MBA2 Dinh Cong 2
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:30 to 11:30
Area:MBA1, MBA2 Dinh Cong 12
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 12:00
Area:MBA1, MBA2 Mai Dong College
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 16:30
Area:Part of Tuong Mai ward, Hoang Mai district
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 05:00 to 12:00
Area:Part of Mai Dong ward, Hoang Mai district
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:00 to 11:00
Area:MBA1, MBA2 Dinh Cong 2
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:30 to 11:30
Area:MBA1, MBA2 Dinh Cong 12
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 16:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 12:00
Area:MBA1, MBA2 Mai Dong College
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 12:00
Area:A part of Kim Giang
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 14:00 to 17:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 14:00 to 17:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:00 to 11:00
Area:MBA1, MBA2 Dinh Cong 2
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:30 to 11:30
Area:MBA1, MBA2 Dinh Cong 12
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 12:00
Area:MBA1, MBA2 Mai Dong College
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 16:30
Area:Part of Tuong Mai ward, Hoang Mai district
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 14:00 to 17:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 05:00 to 12:00
Area:Part of Mai Dong ward, Hoang Mai district
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:00 to 11:00
Area:MBA1, MBA2 Dinh Cong 2
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:30 to 11:30
Area:MBA1, MBA2 Dinh Cong 12
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 14:00 to 17:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:00 to 11:00
Area:MBA1, MBA2 Dinh Cong 2
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 16:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 07:30 to 11:30
Area:MBA1, MBA2 Dinh Cong 12
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 16:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 16:00
Area:Part of Mai Dong
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoang Mai Power Company
Time:From 08:00 to 12:00
Area:MBA1, MBA2 Mai Dong College
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hai Ba Trung Power Company
Time:From 08:00 to 10:00
Area:No - Low voltage load switched to generator
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 14:30 to 15:45
Area:Part of Tan Dan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 08:30 to 09:45
Area:Part of Thanh Xuan commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 05:30 to 12:00
Area:Part of Hong Ky commune
Reason:Serving the renovation and upgrading of the power grid
Status:Postpone
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 07:30 to 08:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 08:30 to 09:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 13:30 to 14:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 15:30 to 16:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 07:30 to 08:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 08:30 to 09:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 13:30 to 14:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 14:30 to 15:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Soc Son Power Company
Time:From 15:30 to 16:45
Area:Part of Trung Gia commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 5, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 14:00 to 17:00
Area:Part of residential group 6, Phu Lam ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:part of residential group 10, Yen Nghia ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 4, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:part of residential group 6, 8 Yen Nghia ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 14:00 to 17:00
Area:Part of residential group 4, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 06:30 to 08:00
Area:State Treasury Ha Dong.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 06:30 to 14:30
Area:Pham Hong Thai Street, Pham Ngu Lao Street, Trung Vuong Street, Magi Center
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 07:00 to 15:00
Area:Part of Duong Lam commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 06:30 to 14:30
Area:Pham Hong Thai Street, Pham Ngu Lao Street, Trung Vuong Street, Magi Center
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 07:00 to 15:00
Area:Part of Duong Lam commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 06:30 to 14:30
Area:Pham Hong Thai Street, Pham Ngu Lao Street, Trung Vuong Street, Magi Center
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 06:30 to 14:30
Area:Pham Hong Thai Street, Pham Ngu Lao Street, Trung Vuong Street, Magi Center
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 07:00 to 15:00
Area:Part of Duong Lam commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 07:00 to 15:00
Area:Part of Duong Lam commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 07:00 to 15:00
Area:Part of Duong Lam commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 07:45 to 10:45
Area:Part of Rubber Company 75
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 07:00 to 15:00
Area:Part of Duong Lam commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Son Tay Power Company
Time:From 07:00 to 15:00
Area:Part of Duong Lam commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phuc Tho Power Company
Time:From 06:00 to 09:00
Area:Part of Long Xuyen commune, Thuong Coc
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phuc Tho Power Company
Time:From 06:00 to 09:00
Area:Part of Long Xuyen commune, Thuong Coc
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phuc Tho Power Company
Time:From 06:00 to 09:00
Area:Part of Long Xuyen commune, Thuong Coc
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phuc Tho Power Company
Time:From 06:00 to 09:00
Area:Part of Long Xuyen commune, Thuong Coc
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phuc Tho Power Company
Time:From 06:00 to 09:00
Area:Part of Long Xuyen commune, Thuong Coc
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phuc Tho Power Company
Time:From 06:00 to 09:00
Area:Part of Long Xuyen commune, Thuong Coc
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phuc Tho Power Company
Time:From 06:00 to 09:00
Area:Part of Long Xuyen commune, Thuong Coc
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phuc Tho Power Company
Time:From 06:00 to 09:00
Area:Part of Long Xuyen commune, Thuong Coc
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phuc Tho Power Company
Time:From 06:00 to 09:00
Area:Part of Long Xuyen commune, Thuong Coc
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dan Phuong Power Company
Time:From 07:00 to 15:00
Area:Part of Tan Tay Do urban area; Phung town
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dan Phuong Power Company
Time:From 07:00 to 15:00
Area:Part of Tan Tay Do urban area; Phung town
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dan Phuong Power Company
Time:From 07:00 to 15:00
Area:Part of Tan Tay Do urban area; Phung town
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dan Phuong Power Company
Time:From 07:00 to 15:00
Area:Part of Tan Tay Do urban area; Phung town
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dan Phuong Power Company
Time:From 07:00 to 15:00
Area:Part of Tan Tay Do urban area; Phung town
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dan Phuong Power Company
Time:From 07:00 to 15:00
Area:Part of Tan Tay Do urban area; Phung town
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dan Phuong Power Company
Time:From 07:00 to 15:00
Area:Part of Tan Tay Do urban area; Phung town
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thach That Power Company
Time:From 07:00 to 15:00
Area:Huong Ngai Commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 06:30 to 10:30
Area:Part of Thach Than Commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 06:30 to 10:30
Area:Part of Thach Than Commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ung Hoa Power Company
Time:From 08:00 to 16:00
Area:Part of Vien Noi commune, Cao Thanh commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ung Hoa Power Company
Time:From 08:00 to 16:00
Area:Part of Vien Noi commune, Cao Thanh commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phu Xuyen Power Company
Time:From 08:00 to 16:00
Area:0.4kV power grid after T4 Nam Trieu Pump Substation
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phu Xuyen Power Company
Time:From 08:00 to 16:00
Area:0.4kV power grid after T4 Nam Trieu Pump Substation
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phu Xuyen Power Company
Time:From 08:00 to 16:00
Area:0.4kV power grid after T4 Nam Trieu Pump Substation
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phu Xuyen Power Company
Time:From 08:00 to 16:00
Area:0.4kV power grid after T4 Nam Trieu Pump Substation
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phu Xuyen Power Company
Time:From 08:00 to 16:00
Area:0.4kV power grid after T4 Nam Trieu Pump Substation
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Phu Xuyen Power Company
Time:From 08:00 to 16:00
Area:0.4kV power grid after T4 Nam Trieu Pump Substation
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoai Duc Electricity Company
Time:From 07:00 to 15:00
Area:Part of Van Con commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoai Duc Electricity Company
Time:From 07:30 to 13:30
Area:part of Lai Xa commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Dan Phuong Power Company
Time:From 07:00 to 15:00
Area:Part of Tan Tay Do urban area; Phung town
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoai Duc Electricity Company
Time:From 07:30 to 13:30
Area:part of Lai Xa commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoai Duc Electricity Company
Time:From 07:00 to 15:00
Area:Part of Van Con commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoai Duc Electricity Company
Time:From 07:00 to 15:00
Area:Part of Van Con commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoai Duc Electricity Company
Time:From 07:00 to 15:00
Area:Part of Van Con commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoai Duc Electricity Company
Time:From 07:00 to 15:00
Area:Part of Van Con commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Hoai Duc Electricity Company
Time:From 07:00 to 15:00
Area:Part of Van Con commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 07:00 to 13:00
Area:Part of Tan Phu Commune, Dai Thanh
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 06:00 to 07:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 15:00 to 16:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 06:00 to 07:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 15:00 to 16:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 06:00 to 07:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 07:00 to 15:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 15:00 to 16:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 06:00 to 07:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 07:00 to 15:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 15:00 to 16:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 06:00 to 07:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 15:00 to 16:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 06:00 to 07:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thanh Oai Power Company
Time:From 15:00 to 16:00
Area:Chau Mai Village
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thuong Tin Power Company
Time:From 06:00 to 14:00
Area:Ha Binh Phuong Industrial Park
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thuong Tin Power Company
Time:From 06:00 to 14:00
Area:Ha Binh Phuong Industrial Park
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thuong Tin Power Company
Time:From 06:00 to 14:00
Area:Ha Binh Phuong Industrial Park
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Thuong Tin Power Company
Time:From 06:00 to 14:00
Area:Ha Binh Phuong Industrial Park
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 15:00
Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 09:00
Area:Van Duc village, An Phu commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 13:00 to 15:00
Area:Doi Dung village, An Phu commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 13:00 to 17:00
Area:Part of Viem Khe village, Hop Tien commune and Quan Son Tourism Joint Stock Company
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 15:00
Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 11:00 to 13:00
Area:Phu Thanh village, An Phu commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 15:00
Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 15:00
Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 15:00
Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 11:00
Area:Phu Duy village, An Tien commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 11:00
Area:Van Thang village, An Tien commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 15:00
Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 13:00 to 17:00
Area:Dong My village, An Tien commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 15:00
Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 11:00
Area:Phu Duy village, An Tien commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 13:00 to 17:00
Area:Part of Viem Khe village, Hop Tien commune and Quan Son Tourism Joint Stock Company
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 15:00
Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 07:00 to 09:00
Area:Van Duc village, An Phu commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 09:00 to 11:00
Area:Phu Thanh village, An Phu commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 11:00 to 13:00
Area:Phu Thanh village, An Phu commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 13:00 to 15:00
Area:Doi Dung village, An Phu commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:My Duc Power Company
Time:From 15:00 to 17:00
Area:Part of Bo Moi village, An Phu commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ung Hoa Power Company
Time:From 08:00 to 16:00
Area:Part of Vien Noi commune, Cao Thanh commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ung Hoa Power Company
Time:From 08:00 to 16:00
Area:Part of Vien Noi commune, Cao Thanh commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ung Hoa Power Company
Time:From 08:00 to 16:00
Area:Part of Vien Noi commune, Cao Thanh commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ung Hoa Power Company
Time:From 08:00 to 16:00
Area:Part of Vien Noi commune, Cao Thanh commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Me Linh Power Company
Time:From 06:30 to 16:30
Area:Part of Lien Mac commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Me Linh Power Company
Time:From 06:30 to 16:30
Area:Part of Lien Mac commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Me Linh Power Company
Time:From 06:30 to 16:30
Area:Part of Lien Mac commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Me Linh Power Company
Time:From 06:30 to 16:30
Area:Part of Lien Mac commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Me Linh Power Company
Time:From 06:30 to 16:30
Area:Part of Lien Mac commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Me Linh Power Company
Time:From 06:30 to 16:30
Area:Part of Lien Mac commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Me Linh Power Company
Time:From 06:30 to 16:30
Area:Part of Lien Mac commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 5, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 14:00 to 17:00
Area:Part of residential group 6, Phu Lam ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 17:00 to 19:00
Area:Dai Nam University.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 17:00 to 19:00
Area:Dai Nam University.
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 06:00 to 09:00
Area:Rural Development Power Construction and Services Company
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 4, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 5, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 5, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 14:00 to 17:00
Area:Part of residential group 4, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 4, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 5, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 5, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 14:00 to 17:00
Area:Part of residential group 4, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Quoc Oai Power Company
Time:From 06:30 to 10:30
Area:Part of Thach Than Commune
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 4, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:part of residential group 10, Yen Nghia ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:Part of residential group 5, Phu Luong ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:part of residential group 6, 8 Yen Nghia ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Ha Dong Electricity Company
Time:From 08:00 to 12:00
Area:part of residential group 1,4 Yen Nghia ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Bac Tu Liem Power Company
Time:From 06:00 to 12:00
Area:No information yet
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Bac Tu Liem Power Company
Time:From 10:00 to 13:00
Area:No information yet
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Bac Tu Liem Power Company
Time:From 14:00 to 15:30
Area:Group 17, Group 18 Phu Dien
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Bac Tu Liem Power Company
Time:From 16:00 to 17:30
Area:Group 16 Phu Dien Ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Nam Tu Liem Power Company
Time:From 09:00 to 13:00
Area:Click to download a part of Vinhomes Gardnia Cau Dien Low-rise Area - Cau Dien Ward - Nam Tu Liem District - Hanoi
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Bac Tu Liem Power Company
Time:From 10:00 to 13:00
Area:No information yet
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Bac Tu Liem Power Company
Time:From 06:00 to 12:00
Area:No information yet
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Bac Tu Liem Power Company
Time:From 10:00 to 13:00
Area:No information yet
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Bac Tu Liem Power Company
Time:From 14:00 to 15:30
Area:Group 17, Group 18 Phu Dien
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Bac Tu Liem Power Company
Time:From 16:00 to 17:30
Area:Group 16 Phu Dien Ward
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
-----------------------------------------------
Electricity:Bac Tu Liem Power Company
Time:From 10:00 to 13:00
Area:No information yet
Reason:Serving the renovation and upgrading of the power grid
Status:Approved
Above is the power outage schedule for areas in Hanoi on December 10, 2024. Currently, there is no information about power outages in some other locations. Nghe An Newspaper will regularly update the latest and most accurate information about the power outage schedule in Hanoi for readers to follow.
Instructions for looking up power outage schedule in Hanoi
There are many ways to look up power outage schedules, including the following:
Follow Hanoi power outage schedule at Nghe An newspaper
Nghe An Newspaper will regularly update the latest and accurate information about power outage schedule in Hanoi for readers' convenience.
Look up power outage schedule on EVN Hanoi website
To look up the power outage schedule in Hanoi today and the coming days, everyone can access the EVN Hanoi website at the linkhttps://evnhanoi.vn/search/power-cut. Select itemDistrict -> Ward -> From date, To dateto capture information

Search on EVN Customer Service application
Everyone downloads the EVN Customer Service application to their phone and registers for an account. Next, select the “Power outage schedule” section to see the exact Hanoi power outage schedule right on your phone.