Quoc DuongDNUM_BAZBCZCACE 06:00

According to Hanoi Electricity, there is a scheduled power outage in districts in Hanoi on December 10, 2024.

The latest information on power outage schedule in Hanoi areas on Sunday, December 10, 2024 is updated from the Hanoi Electricity portal.

There can be many reasons for power outages in Hanoi. Factors that can cause power outages include natural disasters, floods, storms, or the management unit carrying out repairs and maintenance of power grid lines.

Lịch cúp điện hà nội

This is the power outage schedule in the plan of the power companies. Depending on the weather situation, the plan of the power units... the power outage schedule can be adjusted and postponed in some places.

Hanoi power outage schedule on December 10, 2024

Electricity:Soc Son Power Company

Time:From 08:30 to 09:45

Area:Part of Thanh Xuan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 09:30 to 10:45

Area:Part of Thanh Xuan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 06:45 to 12:15

Area:Part of Phu Linh commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 06:45 to 12:15

Area:Part of Phu Linh commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 05:00 to 06:30

Area:Part of Tien Duong commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 14:30 to 16:15

Area:Part of Tien Duong commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 05:00 to 06:30

Area:Part of Tien Duong commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 14:30 to 16:15

Area:Part of Tien Duong commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 05:00 to 06:30

Area:Part of Tien Duong commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 14:30 to 16:15

Area:Part of Tien Duong commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 05:00 to 06:30

Area:Part of Tien Duong commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 06:30 to 14:30

Area:At BT Binh Duong company

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 14:30 to 16:15

Area:Part of Tien Duong commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 05:00 to 06:30

Area:Part of Tien Duong commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Anh Electricity Company

Time:From 14:30 to 16:15

Area:Part of Tien Duong commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Gia Lam Power Company

Time:From 09:00 to 11:00

Area:Vinh Oanh Company Limited

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Gia Lam Power Company

Time:From 09:30 to 11:00

Area:Minh Thang Steel Production and Trading Company Limited

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Gia Lam Power Company

Time:From 08:00 to 10:00

Area:277 Hanoi Packaging Joint Stock Company

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Gia Lam Power Company

Time:From 10:00 to 12:00

Area:277 Hanoi Packaging Joint Stock Company

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Tri Power Company

Time:From 09:00 to 10:15

Area:Artificial particle board manufacturing company

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Tri Power Company

Time:From 12:00 to 13:15

Area:Huong Dung Company Customer

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Tri Power Company

Time:From 07:30 to 08:45

Area:Dai Thanh Company Customer

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Tri Power Company

Time:From 09:00 to 10:15

Area:Artificial particle board manufacturing company

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Tri Power Company

Time:From 10:30 to 11:45

Area:Freight Transport Company

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 05:00 to 12:00

Area:Part of Mai Dong ward, Hoang Mai district

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 16:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 15:30 to 18:30

Area:From number 2 to number 30 Ba Trieu street, number 23 Ba Trieu street.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 15:30 to 18:30

Area:From number 2 to number 30 Ba Trieu street, number 23 Ba Trieu street.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 15:30 to 18:30

Area:From number 2 to number 30 Ba Trieu street, number 23 Ba Trieu street.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 15:30 to 18:30

Area:From number 2 to number 30 Ba Trieu street, number 23 Ba Trieu street.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 12:30 to 15:30

Area:No. 64 Luong Van Can Street. From No. 5 to No. 37 Hang Hanh Street. No. 11 Bao Khanh Alley

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 08:00 to 11:00

Area:From house number 1 to house number 11, from house number 2 to house number 6 Ly Quoc Su street, from house number 1 to house number 67 Hang Bong street; From house number 1 to house number 11, from house number 6 to house number 26 Chan Cam street

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 08:00 to 11:00

Area:From house number 1 to house number 11, from house number 2 to house number 6 Ly Quoc Su street, from house number 1 to house number 67 Hang Bong street; From house number 1 to house number 11, from house number 6 to house number 26 Chan Cam street

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 12:30 to 15:30

Area:No. 64 Luong Van Can Street. From No. 5 to No. 37 Hang Hanh Street. No. 11 Bao Khanh Alley

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 05:00 to 10:00

Area:The whole Tho Xuong Street; From house number 2 to number 40 Au Trieu Street474E1.52

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 08:00 to 11:00

Area:From house number 1 to house number 11, from house number 2 to house number 6 Ly Quoc Su street, from house number 1 to house number 67 Hang Bong street; From house number 1 to house number 11, from house number 6 to house number 26 Chan Cam street

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoan Kiem Electricity Company

Time:From 12:30 to 15:30

Area:No. 64 Luong Van Can Street. From No. 5 to No. 37 Hang Hanh Street. No. 11 Bao Khanh Alley

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hai Ba Trung Power Company

Time:From 08:00 to 10:00

Area:No - Low voltage load switched to generator

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hai Ba Trung Power Company

Time:From 14:00 to 15:30

Area:No - Low voltage load switched to generator

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Da Electricity Company

Time:From 07:00 to 12:00

Area:Building B1, B2, B3, B4, University of Medicine and Pharmacy, Ton That Tung Street

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Da Electricity Company

Time:From 07:00 to 12:00

Area:Building B1, B2, B3, B4, University of Medicine and Pharmacy, Ton That Tung Street

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dong Da Electricity Company

Time:From 07:00 to 12:00

Area:Building B1, B2, B3, B4, University of Medicine and Pharmacy, Ton That Tung Street

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 09:45 to 10:45

Area:From 163 to 233 Pham Van Dong, Mai Dich ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 11:00 to 12:00

Area:Apartment N105 Nguyen Phong Sac - Dich Vong ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 14:00 to 15:00

Area:2.5ha resettlement area, Dich Vong Hau ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 15:15 to 16:15

Area:Lane 130 Xuan Thuy, Phan Van Truong Street, Dich Vong Hau Ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 09:45 to 10:45

Area:From 163 to 233 Pham Van Dong, Mai Dich ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 09:45 to 10:45

Area:From 163 to 233 Pham Van Dong, Mai Dich ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 11:00 to 12:00

Area:Apartment N105 Nguyen Phong Sac - Dich Vong ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 14:00 to 15:00

Area:2.5ha resettlement area, Dich Vong Hau ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 15:15 to 16:15

Area:Lane 130 Xuan Thuy, Phan Van Truong Street, Dich Vong Hau Ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 11:00 to 12:00

Area:Apartment N105 Nguyen Phong Sac - Dich Vong ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 11:00 to 12:00

Area:Apartment N105 Nguyen Phong Sac - Dich Vong ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 14:00 to 15:00

Area:2.5ha resettlement area, Dich Vong Hau ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Cau Giay Power Company

Time:From 15:15 to 16:15

Area:Lane 130 Xuan Thuy, Phan Van Truong Street, Dich Vong Hau Ward - CG - HN

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 05:30 to 12:00

Area:Part of Hong Ky commune

Reason:Serving the renovation and upgrading of the power grid

Status:Postpone

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 06:45 to 12:15

Area:Part of Phu Linh commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 07:30 to 08:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 07:30 to 08:45

Area:Part of Thanh Xuan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 08:30 to 09:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 15:30 to 16:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 05:30 to 12:00

Area:Part of Hong Ky commune

Reason:Serving the renovation and upgrading of the power grid

Status:Postpone

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 06:45 to 12:15

Area:Part of Phu Linh commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 08:30 to 09:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 08:30 to 09:45

Area:Part of Thanh Xuan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 09:30 to 10:45

Area:Part of Thanh Xuan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 10:30 to 11:45

Area:Part of Tan Dan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 13:30 to 14:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 14:30 to 15:45

Area:Part of Tan Dan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 10:30 to 11:45

Area:Part of Tan Dan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 13:30 to 14:45

Area:Part of Tan Dan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 07:30 to 08:45

Area:Part of Thanh Xuan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 08:30 to 09:45

Area:Part of Thanh Xuan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 09:30 to 10:45

Area:Part of Thanh Xuan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 05:00 to 12:00

Area:Part of Mai Dong ward, Hoang Mai district

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:30 to 11:30

Area:MBA1, MBA2 Dinh Cong 12

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 16:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 12:00

Area:MBA1, MBA2 Mai Dong College

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 13:30 to 16:30

Area:DIZEL Thanh Lan

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 14:00 to 17:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 16:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:00 to 11:00

Area:MBA1, MBA2 Dinh Cong 2

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:30 to 11:30

Area:MBA1, MBA2 Dinh Cong 12

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 12:00

Area:MBA1, MBA2 Mai Dong College

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 16:30

Area:Part of Tuong Mai ward, Hoang Mai district

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 05:00 to 12:00

Area:Part of Mai Dong ward, Hoang Mai district

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:00 to 11:00

Area:MBA1, MBA2 Dinh Cong 2

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:30 to 11:30

Area:MBA1, MBA2 Dinh Cong 12

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 16:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 12:00

Area:MBA1, MBA2 Mai Dong College

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 12:00

Area:A part of Kim Giang

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 14:00 to 17:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 14:00 to 17:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:00 to 11:00

Area:MBA1, MBA2 Dinh Cong 2

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:30 to 11:30

Area:MBA1, MBA2 Dinh Cong 12

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 12:00

Area:MBA1, MBA2 Mai Dong College

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 16:30

Area:Part of Tuong Mai ward, Hoang Mai district

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 14:00 to 17:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 05:00 to 12:00

Area:Part of Mai Dong ward, Hoang Mai district

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:00 to 11:00

Area:MBA1, MBA2 Dinh Cong 2

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:30 to 11:30

Area:MBA1, MBA2 Dinh Cong 12

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 14:00 to 17:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:00 to 11:00

Area:MBA1, MBA2 Dinh Cong 2

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 16:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 07:30 to 11:30

Area:MBA1, MBA2 Dinh Cong 12

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 16:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 16:00

Area:Part of Mai Dong

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoang Mai Power Company

Time:From 08:00 to 12:00

Area:MBA1, MBA2 Mai Dong College

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hai Ba Trung Power Company

Time:From 08:00 to 10:00

Area:No - Low voltage load switched to generator

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 14:30 to 15:45

Area:Part of Tan Dan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 08:30 to 09:45

Area:Part of Thanh Xuan commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 05:30 to 12:00

Area:Part of Hong Ky commune

Reason:Serving the renovation and upgrading of the power grid

Status:Postpone

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 07:30 to 08:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 08:30 to 09:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 13:30 to 14:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 15:30 to 16:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 07:30 to 08:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 08:30 to 09:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 13:30 to 14:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 14:30 to 15:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Soc Son Power Company

Time:From 15:30 to 16:45

Area:Part of Trung Gia commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 5, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 14:00 to 17:00

Area:Part of residential group 6, Phu Lam ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:part of residential group 10, Yen Nghia ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 4, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:part of residential group 6, 8 Yen Nghia ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 14:00 to 17:00

Area:Part of residential group 4, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 06:30 to 08:00

Area:State Treasury Ha Dong.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 06:30 to 14:30

Area:Pham Hong Thai Street, Pham Ngu Lao Street, Trung Vuong Street, Magi Center

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 07:00 to 15:00

Area:Part of Duong Lam commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 06:30 to 14:30

Area:Pham Hong Thai Street, Pham Ngu Lao Street, Trung Vuong Street, Magi Center

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 07:00 to 15:00

Area:Part of Duong Lam commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 06:30 to 14:30

Area:Pham Hong Thai Street, Pham Ngu Lao Street, Trung Vuong Street, Magi Center

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 06:30 to 14:30

Area:Pham Hong Thai Street, Pham Ngu Lao Street, Trung Vuong Street, Magi Center

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 07:00 to 15:00

Area:Part of Duong Lam commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 07:00 to 15:00

Area:Part of Duong Lam commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 07:00 to 15:00

Area:Part of Duong Lam commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 07:45 to 10:45

Area:Part of Rubber Company 75

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 07:00 to 15:00

Area:Part of Duong Lam commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Son Tay Power Company

Time:From 07:00 to 15:00

Area:Part of Duong Lam commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phuc Tho Power Company

Time:From 06:00 to 09:00

Area:Part of Long Xuyen commune, Thuong Coc

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phuc Tho Power Company

Time:From 06:00 to 09:00

Area:Part of Long Xuyen commune, Thuong Coc

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phuc Tho Power Company

Time:From 06:00 to 09:00

Area:Part of Long Xuyen commune, Thuong Coc

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phuc Tho Power Company

Time:From 06:00 to 09:00

Area:Part of Long Xuyen commune, Thuong Coc

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phuc Tho Power Company

Time:From 06:00 to 09:00

Area:Part of Long Xuyen commune, Thuong Coc

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phuc Tho Power Company

Time:From 06:00 to 09:00

Area:Part of Long Xuyen commune, Thuong Coc

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phuc Tho Power Company

Time:From 06:00 to 09:00

Area:Part of Long Xuyen commune, Thuong Coc

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phuc Tho Power Company

Time:From 06:00 to 09:00

Area:Part of Long Xuyen commune, Thuong Coc

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phuc Tho Power Company

Time:From 06:00 to 09:00

Area:Part of Long Xuyen commune, Thuong Coc

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dan Phuong Power Company

Time:From 07:00 to 15:00

Area:Part of Tan Tay Do urban area; Phung town

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dan Phuong Power Company

Time:From 07:00 to 15:00

Area:Part of Tan Tay Do urban area; Phung town

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dan Phuong Power Company

Time:From 07:00 to 15:00

Area:Part of Tan Tay Do urban area; Phung town

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dan Phuong Power Company

Time:From 07:00 to 15:00

Area:Part of Tan Tay Do urban area; Phung town

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dan Phuong Power Company

Time:From 07:00 to 15:00

Area:Part of Tan Tay Do urban area; Phung town

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dan Phuong Power Company

Time:From 07:00 to 15:00

Area:Part of Tan Tay Do urban area; Phung town

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dan Phuong Power Company

Time:From 07:00 to 15:00

Area:Part of Tan Tay Do urban area; Phung town

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thach That Power Company

Time:From 07:00 to 15:00

Area:Huong Ngai Commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 06:30 to 10:30

Area:Part of Thach Than Commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 06:30 to 10:30

Area:Part of Thach Than Commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ung Hoa Power Company

Time:From 08:00 to 16:00

Area:Part of Vien Noi commune, Cao Thanh commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ung Hoa Power Company

Time:From 08:00 to 16:00

Area:Part of Vien Noi commune, Cao Thanh commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phu Xuyen Power Company

Time:From 08:00 to 16:00

Area:0.4kV power grid after T4 Nam Trieu Pump Substation

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phu Xuyen Power Company

Time:From 08:00 to 16:00

Area:0.4kV power grid after T4 Nam Trieu Pump Substation

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phu Xuyen Power Company

Time:From 08:00 to 16:00

Area:0.4kV power grid after T4 Nam Trieu Pump Substation

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phu Xuyen Power Company

Time:From 08:00 to 16:00

Area:0.4kV power grid after T4 Nam Trieu Pump Substation

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phu Xuyen Power Company

Time:From 08:00 to 16:00

Area:0.4kV power grid after T4 Nam Trieu Pump Substation

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Phu Xuyen Power Company

Time:From 08:00 to 16:00

Area:0.4kV power grid after T4 Nam Trieu Pump Substation

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoai Duc Electricity Company

Time:From 07:00 to 15:00

Area:Part of Van Con commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoai Duc Electricity Company

Time:From 07:30 to 13:30

Area:part of Lai Xa commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Dan Phuong Power Company

Time:From 07:00 to 15:00

Area:Part of Tan Tay Do urban area; Phung town

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoai Duc Electricity Company

Time:From 07:30 to 13:30

Area:part of Lai Xa commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoai Duc Electricity Company

Time:From 07:00 to 15:00

Area:Part of Van Con commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoai Duc Electricity Company

Time:From 07:00 to 15:00

Area:Part of Van Con commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoai Duc Electricity Company

Time:From 07:00 to 15:00

Area:Part of Van Con commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoai Duc Electricity Company

Time:From 07:00 to 15:00

Area:Part of Van Con commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Hoai Duc Electricity Company

Time:From 07:00 to 15:00

Area:Part of Van Con commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 07:00 to 13:00

Area:Part of Tan Phu Commune, Dai Thanh

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 06:00 to 07:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 15:00 to 16:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 06:00 to 07:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 15:00 to 16:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 06:00 to 07:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 07:00 to 15:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 15:00 to 16:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 06:00 to 07:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 07:00 to 15:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 15:00 to 16:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 06:00 to 07:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 15:00 to 16:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 06:00 to 07:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thanh Oai Power Company

Time:From 15:00 to 16:00

Area:Chau Mai Village

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thuong Tin Power Company

Time:From 06:00 to 14:00

Area:Ha Binh Phuong Industrial Park

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thuong Tin Power Company

Time:From 06:00 to 14:00

Area:Ha Binh Phuong Industrial Park

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thuong Tin Power Company

Time:From 06:00 to 14:00

Area:Ha Binh Phuong Industrial Park

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Thuong Tin Power Company

Time:From 06:00 to 14:00

Area:Ha Binh Phuong Industrial Park

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 15:00

Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 09:00

Area:Van Duc village, An Phu commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 13:00 to 15:00

Area:Doi Dung village, An Phu commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 13:00 to 17:00

Area:Part of Viem Khe village, Hop Tien commune and Quan Son Tourism Joint Stock Company

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 15:00

Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 11:00 to 13:00

Area:Phu Thanh village, An Phu commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 15:00

Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 15:00

Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 15:00

Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 11:00

Area:Phu Duy village, An Tien commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 11:00

Area:Van Thang village, An Tien commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 15:00

Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 13:00 to 17:00

Area:Dong My village, An Tien commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 15:00

Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 11:00

Area:Phu Duy village, An Tien commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 13:00 to 17:00

Area:Part of Viem Khe village, Hop Tien commune and Quan Son Tourism Joint Stock Company

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 15:00

Area:Part of Te Tieu Residential Group, Dai Nghia Town (TBA Bom Tieu, Te Tieu Village), part of Ha Xa Village, Dai Hung Commune (TBA Ha Xa 4), part of An Tien Commune (TBA Hien Luong, An Tien, An Tien 2, Phu Duy, Phu Duy 2, Dong My), Unit K5 and Individual Household Nguyen Van The.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 07:00 to 09:00

Area:Van Duc village, An Phu commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 09:00 to 11:00

Area:Phu Thanh village, An Phu commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 11:00 to 13:00

Area:Phu Thanh village, An Phu commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 13:00 to 15:00

Area:Doi Dung village, An Phu commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:My Duc Power Company

Time:From 15:00 to 17:00

Area:Part of Bo Moi village, An Phu commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ung Hoa Power Company

Time:From 08:00 to 16:00

Area:Part of Vien Noi commune, Cao Thanh commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ung Hoa Power Company

Time:From 08:00 to 16:00

Area:Part of Vien Noi commune, Cao Thanh commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ung Hoa Power Company

Time:From 08:00 to 16:00

Area:Part of Vien Noi commune, Cao Thanh commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ung Hoa Power Company

Time:From 08:00 to 16:00

Area:Part of Vien Noi commune, Cao Thanh commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Me Linh Power Company

Time:From 06:30 to 16:30

Area:Part of Lien Mac commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Me Linh Power Company

Time:From 06:30 to 16:30

Area:Part of Lien Mac commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Me Linh Power Company

Time:From 06:30 to 16:30

Area:Part of Lien Mac commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Me Linh Power Company

Time:From 06:30 to 16:30

Area:Part of Lien Mac commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Me Linh Power Company

Time:From 06:30 to 16:30

Area:Part of Lien Mac commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Me Linh Power Company

Time:From 06:30 to 16:30

Area:Part of Lien Mac commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Me Linh Power Company

Time:From 06:30 to 16:30

Area:Part of Lien Mac commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 5, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 14:00 to 17:00

Area:Part of residential group 6, Phu Lam ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 17:00 to 19:00

Area:Dai Nam University.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 17:00 to 19:00

Area:Dai Nam University.

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 06:00 to 09:00

Area:Rural Development Power Construction and Services Company

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 4, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 5, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 5, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 14:00 to 17:00

Area:Part of residential group 4, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 4, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 5, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 5, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 14:00 to 17:00

Area:Part of residential group 4, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Quoc Oai Power Company

Time:From 06:30 to 10:30

Area:Part of Thach Than Commune

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 4, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:part of residential group 10, Yen Nghia ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:Part of residential group 5, Phu Luong ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:part of residential group 6, 8 Yen Nghia ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Ha Dong Electricity Company

Time:From 08:00 to 12:00

Area:part of residential group 1,4 Yen Nghia ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Bac Tu Liem Power Company

Time:From 06:00 to 12:00

Area:No information yet

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Bac Tu Liem Power Company

Time:From 10:00 to 13:00

Area:No information yet

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Bac Tu Liem Power Company

Time:From 14:00 to 15:30

Area:Group 17, Group 18 Phu Dien

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Bac Tu Liem Power Company

Time:From 16:00 to 17:30

Area:Group 16 Phu Dien Ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Nam Tu Liem Power Company

Time:From 09:00 to 13:00

Area:Click to download a part of Vinhomes Gardnia Cau Dien Low-rise Area - Cau Dien Ward - Nam Tu Liem District - Hanoi

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Bac Tu Liem Power Company

Time:From 10:00 to 13:00

Area:No information yet

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Bac Tu Liem Power Company

Time:From 06:00 to 12:00

Area:No information yet

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Bac Tu Liem Power Company

Time:From 10:00 to 13:00

Area:No information yet

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Bac Tu Liem Power Company

Time:From 14:00 to 15:30

Area:Group 17, Group 18 Phu Dien

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Bac Tu Liem Power Company

Time:From 16:00 to 17:30

Area:Group 16 Phu Dien Ward

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

-----------------------------------------------

Electricity:Bac Tu Liem Power Company

Time:From 10:00 to 13:00

Area:No information yet

Reason:Serving the renovation and upgrading of the power grid

Status:Approved

Above is the power outage schedule for areas in Hanoi on December 10, 2024. Currently, there is no information about power outages in some other locations. Nghe An Newspaper will regularly update the latest and most accurate information about the power outage schedule in Hanoi for readers to follow.

Instructions for looking up power outage schedule in Hanoi

There are many ways to look up power outage schedules, including the following:

Follow Hanoi power outage schedule at Nghe An newspaper

Nghe An Newspaper will regularly update the latest and accurate information about power outage schedule in Hanoi for readers' convenience.

Look up power outage schedule on EVN Hanoi website

To look up the power outage schedule in Hanoi today and the coming days, everyone can access the EVN Hanoi website at the linkhttps://evnhanoi.vn/search/power-cut. Select itemDistrict -> Ward -> From date, To dateto capture information

image.png

Search on EVN Customer Service application

Everyone downloads the EVN Customer Service application to their phone and registers for an account. Next, select the “Power outage schedule” section to see the exact Hanoi power outage schedule right on your phone.

Featured Nghe An Newspaper

Latest

x
Power outage schedule in Hanoi on December 10, 2024
POWERED BYONECMS- A PRODUCT OFNEKO