Nghe An urges and requests signing of commitment on progress of public investment disbursement
(Baonghean.vn) - In the context that the disbursement progress of public investment capital in 2022 in the province is still behind schedule and the national average, the Provincial People's Committee has just issued Document No. 6055/UBND-KT dated August 10 to departments, branches, and People's Committees of districts and cities, urging and requesting units to sign commitments on the disbursement progress of public investment capital in 2022.
Specifically, according to the document, the disbursement data of the State Treasury, as of July 31, 2022, the resultspublic investment disbursementIn 2022, according to the report of the Provincial Treasury, the whole province only reached 32.26%, lower than the national average of 34.7%.
![]() |
The project to upgrade shrimp farming infrastructure according to VietGAP standards in Quynh Bang commune, Quynh Luu district was formed from public investment capital in 2021. Photo: Nguyen Hai |
Therefore, to ensure 100% disbursement of the 2022 plan, the Chairman of the Provincial People's Committee requests directors of departments, branches and sectors; Chairmen of People's Committees at district, city and town levels; Directors of project management boards and investors to report on the implementation progress of each project under the 2022 public investment plan; difficulties and obstacles in the implementation process and propose specific solutions for each difficulty and obstacle...
![]() |
Construction of Mo River dike in Quynh Yen and Quynh Doi communes, Quynh Luu district. Photo: Nguyen Hai |
In particular, for newly started projects and transitional projects with new bidding packages, the province requires specific reports on the investment procedures being implemented; expected time to complete construction bidding procedures, sign construction contracts and start construction; expected disbursement capacity by January 31, 2023.
![]() |
Lach Quen Bridge, part of the coastal highway project connecting Quynh Thuan and Tien Thuy communes, is making good progress. Photo: Nguyen Hai |
In addition, the Provincial People's Committee requires units toSign progress commitmentimplement and disburse for each project according to the form; at the same time, be responsible for the content of the commitment; periodically report the results to the Department of Planning and Investment every 10 days to synthesize and report to the Chairman of the Provincial People's Committee. The results of the implementation of the progress commitments of agencies and units are the basis for consideration.group and individual ratingHeads of agencies and units in 2022 and make adjustments to assigned capital plans.
Require heads of agencies and units to seriously review project progress, send reports and progress commitments to the Provincial People's Committee (through the Department of Planning and Investment) before August 15, 2022.