Nghe An completed construction of 76.51% of poor housing in the whole province.
In week 2, May 2025 (from May 2 to 8, 2025), the whole province continued to start construction of 353 houses and completed, handed over, and put into use 679 houses in the whole province; bringing the total number of houses built to 76.51% of the total housing demand that needs to be reviewed and approved.

According to the update from the Vietnam Fatherland Front Committee of Nghe An province in 20 districts, cities and towns; in week 2, May 2025 (from May 2 to 8, 2025), the whole province continued to start construction of 353 houses (198 new houses, 155 houses repaired).
Of which, the Program supports 79 houses from socialized sources (49 new houses, 30 houses repaired); two National Target Programs support 73 houses (52 new houses, 21 houses repaired); the Program supports houses for people with meritorious services 201 houses (97 new houses, 104 houses repaired).

Details of the number of new houses started during the week in 14 localities (data from high to low): Tuong Duong district started construction of 56 houses (16 new houses, 40 repaired houses); Ky Son district started construction of 46 houses (43 new houses, 3 repaired houses); Thai Hoa town started construction of 43 houses (16 new houses, 27 repaired houses); Tan Ky district started construction of 41 houses (14 new houses, 27 repaired houses).

Nam Dan district started construction of 35 houses (29 new houses, 6 repaired houses); Vinh city started construction of 32 houses (12 new houses, 20 repaired houses); Yen Thanh district started construction of 25 houses (16 new houses, 9 repaired houses); Anh Son district started construction of 25 houses (10 new houses, 15 repaired houses); Con Cuong district started construction of 17 new houses; Dien Chau district started construction of 16 houses (15 new houses, 1 repaired house).
Nghi Loc district started construction of 7 houses (6 new houses, 1 house repaired); Nghia Dan district started construction of 6 houses (2 new houses, 4 houses repaired); Do Luong district started construction of 2 houses (1 new house, 1 house repaired); Hung Nguyen district started construction of 2 houses (1 new house, 1 house repaired).

Also in week 2, May 2025, the total number of houses completed, handed over and put into use in the whole province was 679 (347 newly built houses, 332 repaired houses).
Of which, the Program supports 246 houses from socialized sources (140 new houses, 106 houses repaired); two National Target Programs support 216 houses (139 new houses, 77 repaired); the Program supports houses for people with meritorious services 217 houses (68 new houses, 149 houses repaired).

Details of the number of houses completed during the week in 19 localities (data from high to low): Quy Chau district completed 132 houses (107 new houses, 25 repaired houses); Ky Son district completed 125 houses (67 new houses, 58 repaired houses); Tuong Duong district completed 112 houses (32 new houses, 80 repaired houses); Quy Hop district completed 94 houses (93 new houses, 1 repaired house).
Tan Ky district completed 57 houses (16 new houses, 41 repaired houses); Anh Son district completed 44 houses (8 new houses, 36 repaired houses); Yen Thanh district completed 29 houses (24 new houses, 5 repaired houses); Quynh Luu district completed 28 houses (24 new houses, 4 repaired houses); Do Luong district completed 26 houses (11 new houses, 15 repaired houses); Dien Chau district completed 23 houses (21 new houses, 2 repaired houses); Nam Dan district completed 21 houses (7 new houses, 14 repaired houses).

Hung Nguyen district completed 20 houses (5 new houses, 15 repaired houses); Nghi Loc district completed 19 houses (10 new houses, 9 repaired houses); Vinh city completed 19 houses (5 new houses, 14 repaired houses); Con Cuong district started construction of 17 new houses; Thai Hoa town completed 14 houses (3 new houses, 11 repaired houses); Nghia Dan district completed 5 houses (3 new houses, 2 repaired houses); Con Cuong district completed 3 new houses; Hoang Mai town completed 1 new house.

Cumulative results from the implementation of the program to mobilize and support housing construction for the poor and households with housing difficulties launched by the province from February 2023 to May 8, 2025, the whole province has built and repaired 16,202 houses (11,642 new houses, 4,560 houses repaired).
Of which, the Program supports 9,405 houses from socialized sources (7,815 new houses, 1,590 houses are repaired); two National Target Programs support 5,728 houses (3,477 new houses, 2,251 houses are repaired); the Program supports houses for people with meritorious services 1,069 houses (350 new houses, 719 houses are repaired).

Thus, compared with the total need for support in building and repairing houses in the 2023 - 2025 period reviewed at 21,176 units (14,655 new units, 6,521 units repaired) and the result of 16,202 units; Nghe An has completed 76.51% of houses for the poor and households with housing difficulties in the whole province.

The total number of remaining houses to be completed before July 31, 2025 is 4,974 (3,013 new houses, 1,961 repaired houses). Of which, the socialized source program is 1,313 houses (862 new houses, 451 repaired houses); two National Target Programs are 1,128 houses (662 new houses, 466 repaired houses); the Housing Support Program for people with revolutionary contributions is 2,533 houses (1,489 new houses, 1,044 repaired houses).

Details of the remaining housing needs in 20 district-level units (from high to low): Tuong Duong district 858 houses (409 new houses, 449 repaired houses); Dien Chau district 808 houses (618 new houses, 190 repaired houses); Yen Thanh district 490 houses (334 new houses, 156 repaired houses); Con Cuong district 436 houses (287 new houses, 149 repaired houses).
Ky Son district 353 houses (313 newly built, 40 repaired); Quy Chau district 339 houses (252 newly built, 87 repaired); Que Phong district 312 houses (83 newly built, 229 repaired); Vinh city 294 houses (122 newly built, 172 repaired); Hung Nguyen district 231 houses (106 newly built, 125 repaired).
Tan Ky district 167 houses (84 newly built, 83 repaired); Thanh Chuong district 225 houses (107 newly built, 118 repaired); Anh Son district 104 houses (61 newly built, 43 repaired); Nghi Loc district 84 houses (55 newly built, 29 repaired); Nghia Dan district 74 houses (51 newly built, 23 repaired).
Do Luong district: 58 houses (41 newly built, 17 repaired); Thai Hoa town: 57 houses (22 newly built, 35 repaired); Nam Dan district: 47 houses (41 newly built, 6 repaired); Quy Hop district: 14 houses (7 newly built, 7 repaired); Quynh Luu district: 13 newly built houses; Hoang Mai town: 10 houses (7 newly built, 3 repaired.

In week 2, May 2025, the result of receiving support for housing construction at the provincial level was more than 668 million VND; the result of disbursing support for housing construction at the district level was nearly 13 billion VND from socialized sources.