Nghe An strives to resolve problems for investors

Pearl DNUM_BJZAEZCABJ 09:33

(Baonghean) - After a meeting with investors about key projects in the area, Chairman of the Provincial People's Committee Thai Thanh Quy concluded and directed sectors and localities to immediately take action to resolve the issues raised.

From specific projects

The road project to the DKC Petroleum Depot aims to transport petroleum for the DKC Group in Nghi Thiet, Nghi Loc with a length of about 1.45 km; roadbed width of 12 m; road surface of 11 m. The project on the route is designed to be permanent, with lighting systems on both sides of the road, drainage systems and other auxiliary items.

The project aims to renovate the existing road surface connecting D4 to the DKC oil depot and port to serve the DKC project, with a total investment of 70.3 billion VND. The Southeast Economic Zone Management Board has completed the renovation of the existing road surface in Nghi Thiet commune connecting D4 to the DKC oil depot and port.

Currently, the Board is taking the next steps to organize bidding to select contractors to implement the packages when capital conditions are met.

Existing road connecting D4 to DKC Petroleum Depot and Port. Graphics: Lam Tung

At a recent meeting with provincial leaders about key projects in the area, Ms. Chu Thi Thanh - Chairman of DKC Group said that slow project implementation affects production and business.

Regarding this issue, the Chairman of the Provincial People's Committee, Thai Thanh Quy, has directed the Department of Finance to, while waiting for the central budget reserve to be allocated for the project, balance the provincial budget, and advise on the allocation of about 1.2 billion VND to carry out the procedures for selecting a contractor to design and construct construction drawings to ensure progress.

Tổng kho xăng dầu DKC đi vào hoạt động từ tháng 2/2019. Ảnh: Lâm Tùng
DKC petroleum depot has been in operation since February 2019. Photo: Lam Tung

The Management Board of the Southeast Economic Zone is assigned to preside over and coordinate with local authorities to develop a plan to ensure safety on the current road to serve the project. At the same time, the Provincial People's Committee has also issued Decision No. 517/QD-UBND approving the addition of the D4 road project in the Southeast Economic Zone.

Regarding the Nghe An MDF Wood Fiberboard Factory, the investor also said that there is no access road (the road connecting National Highway 7 to Tri Le Industrial Park, Anh Son) while this is a large project, creating motivation for the forestry industry in many districts in Western Nghe An.

Perspective of MDF Wood Factory of Thanh Thanh Dat Company Limited in Anh Son, started construction on April 30, 2018.

Regarding this issue, Chairman of the Provincial People's Committee Thai Thanh Quy directed the Department of Planning and Investment and the Department of Finance to work again to unify the capital source plan for the project connecting National Highway 7 to Tri Le Industrial Park, and advise the Provincial People's Committee.

The above are two examples showing Nghe An's timely intervention in solving practical problems, which are highly appreciated by investors.

Assign a deadline for each project

Immediately after the meeting with investors, implementing the direction of the Provincial Party Secretary, the People's Committee of Nghe An province issued a conclusion notice, assigning tasks to sectors and levels to immediately resolve problems for the projects.

For the WHA Hemaraj Industrial Park project, the Chairman of the Provincial People's Committee assigned the Nghi Loc District People's Committee to hand over the site to the investor before March 30, 2019. Accelerate the relocation of scattered graves outside the project area; Urgently complete the relocation of the existing 0.4kV and 35kV power lines in the project, requiring the relocation to be completed before March 31, 2019.

Road N5 does not have an electric lighting system. Photo: Lam Tung

Propose Nghe An Electricity to coordinate and support Nghi Loc district in the procedures for handover and exploitation of electricity management. Assign the Department of Agriculture and Rural Development to submit to the Provincial People's Committee a decision to convert the purpose of using protective forest land for the raw material area at location No. 1, advise the Provincial People's Committee on the procedures for converting the planning from protective forest to other land for 2 new raw material areas to ensure convenience for investors; Assign the Management Board of the Southeast Economic Zone to continue completing the following procedures to deploy the lighting system along N5 road in April 2019, drainage ditches along N5...

For the VSIP Nghe An Industrial, Urban and Service Park project, the province assigned Vinh city and Hung Nguyen district People's Committee to hand over the site to the investor before April 30, 2019.

A corner of VSIP project in Hung Nguyen. Photo by Tran Chau

As for FLC Group projects, the relevant departments, branches, sectors, and People's Committees of districts are assigned to coordinate with investors to effectively implement the contents of Notice No. 144/2019 of the Provincial People's Committee on the Conclusion of the Chairman of the Provincial People's Committee at the working session with FLC Group Joint Stock Company on proposed investment projects in the province.

With the FLC Nghe An Eco-tourism and Entertainment Complex project in Nghi Tien commune, Nghi Loc district: The Management Board of the Southeast Economic Zone actively worked with the Ministry of Construction to submit to the Prime Minister for approval of local adjustments to the Southeast Economic Zone Master Plan in April 2019.

Regarding the proposed investment project to explore and exploit limestone mines for common construction materials in Tan Ky district: Assign the Department of Agriculture and Rural Development to urgently work with the Ministry of Agriculture and Rural Development to submit to the Prime Minister for approval on converting natural forests to mineral exploitation purposes as a basis for implementing the next steps.

Perspective of amusement parks on Ngu Island.

As for the Cua Hoi entertainment area project, the Chairman of the Provincial People's Committee assigned relevant departments, branches and the People's Committee of Cua Lo town to carry out procedures and coordinate with investors to start construction in May 2019.

With strong direction, the projects are currently making positive progress, especially in terms of site clearance and supporting the completion of procedures for investors.