Nghe An is about to inaugurate 2 huge projects

April 13, 2017 18:14

(Baonghean.vn) - In order for the two projects of Road N5 and Nghi Thiet Grinding Station to be inaugurated on schedule, Chairman of the Provincial People's Committee Nguyen Xuan Duong requested the construction units and investors to work continuously to ensure safety.

These two projects have a total investment of more than 2,300 billion VND.

On the afternoon of April 13, comrade Nguyen Xuan Duong - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee led a working delegation of the province to inspect and work on the progress and preparations for the inauguration ceremony of the Song Lam cement grinding station project in Nghi Thiet, Nghi Loc and the technical opening of National Highway 7 - N5 - Nghi Thiet.

Also attending were Mr. Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee; leaders of relevant departments and branches; Song Lam Cement Joint Stock Company.

The N5 route connecting the Southeast Economic Zone to Hoa Son, Do Luong district, is 29.1km long and has been approved as two specific projects with a total capital of over VND1,265 billion. Up to now, after nearly a year of construction, the main route passing through two districts, Nghi Loc and Do Luong, has been handed over to the construction unit.

Regarding the construction volume, as of April 13, 2017, the roadbed, bridges, culverts, and crushed stone foundations have been completed 100%, cement reinforcement has been completed 95%, and the first layer of asphalt has been completed 19/29.1km, reaching 65% of the total project length.

Đoàn công tác kiểm tra thực địa tuyến đường N5. Ảnh: Thu Huyền
The working group inspected the construction status of N5 road. Photo: Thu Huyen

The Department of Transport is directing contractors to focus resources to speed up the construction progress of project items, arranging 3 asphalt concrete construction teams (minimum construction of 1km per day) to ensure completion of layer 1 asphalt concrete before April 28, 2017 and completion of the entire project before June 30, 2017.

Regarding Nghi Thiet Cement Grinding Station (total investment of 1,100 billion VND, designed capacity of phase 1 is 4 million tons/year), according to the report of Song Lam Cement Joint Stock Company, the cement plant has reached 99%, expected to be completed by the end of April 2017. The cement grinding machine has completed half of the grinding machine - ending phase 1. Phase 2 is installing cement grinding machine No. 2 and is expected to be completed in July 2017. The silos containing feed for the grinding machine have reached 99%, expected to be completed in April.

Đến nay, tuyến N5 cơ bản đã thông tuyến, thảm nhựa bê tông. Ảnh: Thu Huyền
Up to now, route N5 has basically been opened and paved with concrete. Photo: Thu Huyen

Auxiliary works such as central control house, conveyor belt, and import funnel have reached 99% and are expected to be completed in April 2017. Equipment for the cement grinding mill has been installed at 97% and is undergoing calibration and trial run. Expected to operate with load at the end of April 2017...

Through on-site inspection, Chairman of the Provincial People's Committee Nguyen Xuan Duong highly appreciated the efforts of investors and contractors and agreed to inaugurate the factory, cement grinding station and open road N5 on April 29 in Nghi Thiet, Nghi Loc.

Chủ tịch UBND tỉnh kiểm tra tiến độ thi công trạm nghiền xi măng. Ảnh: Thu Huyền
Chairman of the Provincial People's Committee inspects the construction progress of the cement grinding station. Photo: Thu Huyen

To ensure that these two projects are completed on schedule and inaugurated before April 30, the Chairman of the Provincial People's Committee requested the Department of Transport and the Management Board of the Southeast Economic Zone to direct contractors to arrange regular construction forces on the route, striving to complete the first layer of asphalt before April 30; the construction must ensure safety and efficiency...