Quickly complete the second cement grinding line at Nghi Thiet Grinding Station

DNUM_AHZBBZCABH 11:06

(Baonghean) - Along with effectively exploiting completed projects, Song Lam Cement Joint Stock Company under The Vissai Cement Group is speeding up the construction progress of the second line of Nghi Thiet Cement Grinding Station. Up to now, the infrastructure items have been basically completed and are entering the stage of installing equipment imported from Germany.

Công nhân lắp đặt thiết bị dây chuyền trạm nghiền. Ảnh: Nguyên Sơn
Workers install equipment on the crushing station line. Photo: Nguyen Son

Since the end of April 2017, the first line of Nghi Thiet Cement Grinding Station (Nghi Loc) of Song Lam Cement Joint Stock Company - The Vissai Cement Group has officially come into operation. Immediately after that, this line has been operating stably, supplying cement for this unit to accelerate the construction of Vissai International Wharf and the second cement grinding line along with many other auxiliary works. In particular, when Vissai Wharf came into operation (October 21, 2017), Song Lam Cement Joint Stock Company has supplied the domestic market and exported hundreds of thousands of tons of cement and clinker by waterway.

By mobilizing maximum human resources and focusing on each item, up to now, the second cement grinding line of Song Lam Cement Joint Stock Company has basically completed the construction of the factory and is installing equipment that has just been imported from Germany.

According to Mr. Nguyen Quoc Tai - Director of Nghi Thiet Grinding Station and Seaport, "According to the plan, the second cement grinding line will officially operate in January 2018. To ensure progress, we urge contractors to mobilize more human resources and machinery to speed up construction progress. During the construction process, the Group's viewpoint is to strive to put the projects into operation in the shortest time to shorten construction time, promote investment efficiency... If favorable, the second line can be put into trial operation at the end of December 2017".

Công nhân đang lắp đặt thiết bị dây chuyền trạm nghiền xi măng ở Nghi Thiết- Nghi Lộc- Nghệ An. Ảnh: Nguyên Sơn
Workers are installing equipment at the Cement Grinding Plant in Nghi Thiet- Nghi Loc- Nghe An. Photo: Nguyen Son

At the same time, the third cement grinding line is leveling the ground adjacent to line 2 and is expected to be built in the second quarter of 2018. All 3 lines of Nghi Thiet Cement Grinding Station have a clinker grinding capacity of 300 tons/hour/line. Always closely following the construction site, Mr. Nguyen Ngoc Oanh - General Director of The Vissai Cement Group, Chairman of the Board of Directors of Song Lam Cement Joint Stock Company shared: "The clusters of projects in Nghe An such as: Cement factory in Do Luong, cement grinding stations and Vissai - Nghi Thiet International Seaport are the new mark of the group.

In addition to improving production capacity for enterprises, the project also creates more jobs and accompanying services, contributing to the overall development of Nghe An and the whole country...". According to Mr. Nguyen Ngoc Oanh, for a long time, all levels, sectors and people of Nghe An have actively accompanied The Vissai Cement Group to quickly put the projects into operation. Currently, the Group is continuing to complete other projects.

Therefore, Song Lam Cement Joint Stock Company proposes to the Management Board of the Southeast Economic Zone and the departments and branches of Nghe An province to continue to support and promptly approve the appropriate adjustment and expansion of the planning as reported many times at the locations of the port entrance (10,338 m2), interspersed residential areas (about 9,000 m2) and the beach area protecting the bridgehead leading to the port (33,000 m2).

At the same time, the cemetery area at the gate must be cleared soon (Nghi Loc District Land Acquisition and Clearance Board has counted) to open the road for the construction of the 3rd crushing line. At the same time, the compensation regime for Mrs. Phan's household at the port entrance (between the land of Mr. Thanh and Mr. Loc in Nghi Thiet commune) must be resolved so that the Company can speed up the construction progress and complete the works according to the planning and design.

Một góc công trình thứ 2, Trạm nghiền xi măng Nghi Thiết. Ảnh: Nguyên Sơn
A corner of the second project, Nghi Thiet Cement Grinding Station. Photo: Nguyen Son

At the opening ceremony of Vissai - Nghi Thiet International Port in late October 2017, Mr. Hoang Manh Truong - Chairman of The Vissai Cement Group excitedly shared: “The cluster of projects including Song Lam Cement Factory and the Nghi Thiet Grinding Station and Seaport system is a key cluster of projects of the Group and the whole country. The rapid commissioning of the projects is even more important in enhancing the position and brand of the Group and promoting the socio-economic development of the provinces in the North Central region. This is one of the strategies for us to reach out to the big sea…”.

Mr. Truong also affirmed that during the construction of the projects, the Group received timely attention and support from the leaders and people of Nghe An province, and effective support from credit institutions inside and outside the province, especially BIDV Nghe An Bank. That is an important factor for the projects to be completed and put into use, promoting their effectiveness. Therefore, the Group hopes to continue to receive that valuable support so that the entire project can be completed soon, creating new momentum for development.

» Deputy Prime Minister Vuong Dinh Hue pressed the button to operate Vissai port, welcoming a 70,000-ton ship

Nguyen Son

RELATED NEWS

Featured Nghe An Newspaper

Latest

x
Quickly complete the second cement grinding line at Nghi Thiet Grinding Station
POWERED BYONECMS- A PRODUCT OFNEKO