Many key projects in Nghe An have quite good disbursement progress.
(Baonghean.vn) - As of August 2020, the disbursement progress of some key projects in Nghe An province is quite positive.
The report of the Provincial People's Committee shows:By August 2020, for the provincial budget, as of August 15, 2020, disbursement was 4,850.754 billion VND/plan assigned by the province 8,350.724 billion VND, reaching 58.09%, of which:
Concentrated investment sources in 2020 have disbursed VND 4,070,257 billion/plan assigned VND 6,857,733 billion, reaching 59.35%.
Investment in local budget balance, disbursed 2,790,228 billion VND/plan assigned 3,976,763 billion VND, reaching 70.16%.
Investment from the central budget, disbursed 1,280.029 billion VND/plan assigned 2,880.97 billion VND, reaching 44.43%.
For the projectCoastal road from Nghi Son (Thanh Hoa) to Cua Lo(Nghe An) - section from the intersection of National Highway 46 to Provincial Road 535 (Km76+00 - Km83+500):The capital plan for 2020 is 125 billion VND, up to now the capital paid according to the report of the State Treasury is 74 billion VND, the disbursement rate reached 59.33%.
![]() |
Traffic route connecting National Highway 1A - Nghia Dan district - Thai Hoa town. Photo: Quang An |
Traffic Road Project connecting National Highway 1A - Nghia Dan District - Thai Hoa Town:The 2020 plan is 55 billion VND, the paid capital according to the State Treasury's report is 36,755 billion VND, reaching 66.83%.
Connecting Road ProjectN5 roadSoutheast Economic Zone to Hoa Son, Do Luong (Km0 - Km15):The 2020 plan is 13,150 billion VND, the paid capital according to the State Treasury's report is 4,292 billion VND, reaching a rate of 32.64%. Currently, the project is auditing the final settlement and adjusting the price for payment.
Road connecting N5 Road of Southeast Economic Zone to Hoa Son, Do Luong (Km15 - Km28+500): 2020 plan 11.85 billion VND, paid capital according to the report of the State Treasury 4.369 billion VND, reaching 36.87%. Currently, the project is auditing the final settlement, adjusting the price for payment.
Muong Xen - Ta Do - Khe Kien Road Project:The 2020 plan is 100 billion VND, the paid capital according to the State Treasury's report is 4,644 billion VND, the disbursement rate is 4.64% (the source of the central budget allocated at the beginning of the year is 40 billion VND).
The reason for this project's low disbursement is that since March 2020, there has been a decision to adjust the project to add the Km51 - Km58 section to phase 1 as a basis for arranging additional medium-term investment plans for the period 2016 - 2020 from the general reserve fund for implementation and it was not until June 2020 that the capital plan (60 billion VND) was assigned; It was not until August 2020 that there was a notice to amend the schedule in the allocated capital plan.
![]() |
Road D4 connects to Nghi Thiet port. Photo: Nguyen Le |
Nghe An is focusing on directing the promotion of disbursement.public investment,consider this a solution to stimulate investment, stimulate socio-economic development and support other economic sectors affected by Covid-19.
Nghe An assigns leaders of departments, branches and localities to be responsible for monitoring the progress of each project; assigns investors to register and commit to specific and detailed disbursement plans for each project every quarter, especially large and key projects. At meetings of the Provincial People's Committee, Chairman of the Provincial People's Committee Nguyen Duc Trung also proposed considering the disbursement target of investment capital as a target to evaluate the year-end competition./.

North-South Expressway section through Dien Chau crosses Than Vu mountain and has 2 bridges
(Baonghean.vn) - The North-South Expressway through Dien Chau is currently being urgently cleared, including a tunnel through the mountain through Than Vu mountain called Than Vu tunnel.