Bottlenecks that need to be removed on the coastal road project
(Baonghean.vn) - After basically completing the section from Cua Hoi to Nam Cam intersection, Nghe An is currently focusing on speeding up the progress of the coastal road from Nghi Son to Nghi Loc. However, in reality, the implementation has encountered problems that have prevented localities from reclaiming and handing over the land for the project.
![]() |
The shrimp pond location of Mr. Tran Ngoc Khoa in Thanh Vinh 2 hamlet, Nghi Quang commune (Nghi Loc) is expected to be reclaimed about 2,700 m2 to build a bridge pier, but according to the reflection, the compensation and support level is still low, so the land acquisition and handover cannot be carried out yet. Photo: Nguyen Hai |
![]() |
The location of 8 households in the North of Lach Quen bridge, Tien Thuy commune will be relocated to build pier M1 to pier T3. Due to problems related to land origin and compensation items and the locality has not completed the resettlement area, the handover of the site is very difficult. According to the plan, the location from pier M1 to pier T3 has a deadline of November 30, 2023. Photo: Nguyen Hai |
![]() |
Due to site clearance issues, the construction progress of the northern pier of Lach Quen Bridge in Tien Thuy Commune (Quynh Luu) has been delayed, equivalent to a volume of nearly 60 billion VND. Photo: Nguyen Hai |
![]() |
While waiting for the handover of the site for the pillars from T1 to T3, Trung Nam 18 E&C Construction Joint Stock Company drilled and surveyed and built pillar M1 from the top of the mountain north of Lach Quen bridge. Photo: Nguyen Hai |
![]() |
Along with organizing the movement to hand over the site of the northern pillar of Lach Quen bridge, Quynh Luu district also had to relocate dozens of medium voltage electric poles south of Lach Quen bridge. Photo: Nguyen Hai |
![]() |
While Nghi Loc and Quynh Luu districts are having some problems, in Dien Chau district, the land acquisition and compensation work is basically going smoothly. In the photo: After counting and counting the area for crop cultivation and aquaculture, the construction unit built a road leading from the North to Lach Van bridge. Photo: Nguyen Hai |
![]() |
The location of 2 out of 7 households that have not agreed to hand over the land for construction of the route from Quynh Lien to Quynh Bang to connect to Quynh Luong - Quynh Minh. The representative of Quynh Bang Commune People's Committee said: After reviewing and determining the origin of the land again, the commune and district will consider and mobilize the people; strive to hand over the land for the project by the end of March. Photo: Nguyen Hai |
![]() |
The location of the illegally built shrimp pond of Ms. Pham Thi Van, Quynh Lien commune (Hoang Mai town) was administratively fined so there was no compensation when it was cleared. Along with that, because she did not agree to the support level of 30% of the architectural assets on the land rented from the commune, the family did not agree to hand over the site. Photo: Nguyen Hai |
![]() |
Mr. Pham Van Hao - Vice Chairman of Hoang Mai Town People's Committee said: Compared to other localities, Hoang Mai Town has 2.38 km/101 plots, so the volume of land that needs to be recovered and handed over is larger. Although there are still many difficulties, Hoang Mai Town is committed to handing over as committed to the Chairman of the Provincial People's Committee. |