Strive to complete site clearance for Vinh Urban Development Sub-project next month
(Baonghean.vn) -""Must complete site clearance within the next month and speed up construction progress" - that is the direction ofVice Chairman of Provincial People's CommitteeHuynh Thanh Dien at the progress inspection of Vinh urban development sub-project on the morning of September 20.
Accompanying the delegation were leaders of the departments: Finance, Construction, Natural Resources and Environment, Vinh City Party Committee, People's Committee and a number of related departments.
![]() |
Comrade Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee inspected the site clearance work at Xuan Dong hamlet, Nghi Duc commune (Vinh city). Photo: Xuan Hoang |
According to data from Vinh City People's Committee, up to now, there are still 41 households that have not received compensation for land clearance on the road connecting from National Highway 46 to the Lam River road.
Inspecting the site clearance and construction progress on the road connecting National Highway 46 to the Lam River road, the regulating lake and Vinh Citadel moat, Mr. Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee assigned the Vinh City People's Committee to resolve the site clearance work on the agricultural land area of 3 households in Hung Hoa commune to carry out the regulating lake project.
![]() |
Comrade Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee met and discussed with people of Nghi An commune to listen to their concerns when constructing works in the commune. Photo: Xuan Hoang |
In Nghi Duc commune, after inspection, it was found that although the site clearance work had been completed, the contractor had not yet started construction on this road section of more than 500 m. Comrade Huynh Thanh Dien requested: It is necessary to review the contractor's capacity. If it does not meet the requirements, the contractor can be replaced to ensure progress.
The areas where the site clearance has not been completed because the households have not yet received compensation, such as: 8 households in Xuan Dong hamlet, Nghi Duc commune, 14 households in Hung Tay commune (Hung Nguyen), 5 households at the site of Vinh ancient citadel moat... are assigned to local ministries to continue to propagate and mobilize the people, trying to complete the clearance within the next month.
During the inspection, local departments and units presented difficulties and obstacles in site clearance. The biggest difficulty was determining the origin of the land, so many households did not agree with the compensation plans for site clearance.
![]() |
The Vinh Citadel moat project is under construction, however, there are still 5 households that have not received compensation, so there are still problems with the land. Photo: Xuan Hoang |
At the end of the inspection, Vice Chairman of the Provincial People's Committee Huynh Thanh Dien said that the site clearance work has achieved many results up to this point, but there are still some points that have not been completed. Therefore, the Vice Chairman of the Provincial People's Committee directed the Vinh City People's Committee to coordinate with all levels and sectors to complete the site clearance work within the next month. Contractors are speeding up the construction progress to ensure the opening of the road connecting National Highway 46 to the Lam River road (more than 8 km). Because the remaining time is not much, especially at the end of the year when the weather is not favorable.
The Vinh Sub-Urban Development Sub-Project, funded by the World Bank, includes four components: Improving services and upgrading basic infrastructure; improving environmental sanitation; building bridges and urban roads and enhancing technical infrastructure capacity. The total investment of the project is 152.922 million USD, equivalent to 3,180 billion VND, of which the World Bank loan is 98 million USD. |
Xuan Hoang