Strive to complete the renovation of Nguyen Thi Minh Khai Street in July 2024

Quang An DNUM_CFZAGZCACE 08:53

According to the original plan, the upgrading of Nguyen Thi Minh Khai Street, Vinh City would be completed during the past April 30 - May 1, however, up to now, this street still has some items that have not been completed due to many difficulties.

Nguyen Thi Minh Khai Street has a total length of nearly 1.4km, including 2 sections: Le Loi to Le Hong Phong intersection is 289m long and the section from Le Hong Phong intersection to the Provincial Post Office intersection is nearly 1.1km long. This is the central and busiest business street in Vinh City.

Dù tuyến đường đã được nâng cấp hầu hết các hạng mục nhưng các cây cột điện cũ, cuộn dây cáp vẫn nguyên trạng. Ảnh: Quang An
Although most of the road has been upgraded, the old electric poles and cable coils remain intact. Photo: Quang An

At the end of 2023, Vinh City started construction to renovate and upgrade this road with a total cost of over 80 billion VND. The upgrade is expected to be completed during the period from April 30 to May 1.

According to the reporter's records, many items on this route such as sidewalk renovation, curb construction, ditch weaving, renovation of communication systems, lighting, drainage ditches, and tree planting were basically completed in early May 2023.

Nhiều cuộn dây cáp sà xuống lòng đường vỉa hè trên đường Nguyễn Thị Minh Khai. Ảnh: Quang An
Many rolls of cable hung down on the road and sidewalk on Nguyen Thi Minh Khai Street. Photo: Quang An

Currently, on this street there are about 100 old electric poles, and a tangled network of telecommunication cables, which is both dangerous and unsightly. This is also a part of the road improvement plan, but for over a month, according to the reporter's records, there has been no construction work to complete the road, causing concern among the people.

Mr. Nguyen Phi Hai, a business owner on Nguyen Thi Minh Khai Street, said: The electric poles and meter boxes on this street have been there for decades and are now old and damaged. Many telecommunication cables hang low, posing a danger to pedestrians.

Hơn 100 cột điện trên tuyến đường này đã có từ lâu đời, dây mạng viễn thông quấn chằng chịt. Ảnh: Quang An
More than 100 electric poles on this route have been around for a long time, and telecommunication cables are tangled together. Photo: Quang An

The characteristic of this road is that there are many businesses and government agencies, the hot season increases the electricity consumption, posing a risk of fire and explosion for the old electrical system. It is worth mentioning that some electrical boxes mounted on the electric poles have been broken and damaged, the protection from the rainy and sunny weather is no longer guaranteed, plus the tangled telecommunication network coils increase the risk of electrical short circuit.

Discussing this issue, Mr. Pham Sy Hoang - Director of Vinh City Electricity said: The dismantling of old electric poles and the renovation of the electrical system on Nguyen Thi Minh Khai Street depends on the unit in charge of constructing the road. Currently, the unit has not received a specific plan on this issue, so it is not possible to coordinate the dismantling. In addition, before dismantling the electric poles, there will be a rotational power outage, so it is necessary to carefully consider and calculate a reasonable time to carry out the work, limiting the impact on households and units during the hot season.

Nhiều hộp điện đã bị hư hỏng, xuống cấp theo thời gian. Ảnh: Quang An
Many electrical boxes have been damaged and degraded over time. Photo: Quang An

According to the Vinh City Project Management Board - the construction unit of this road, the renovation of the electrical system is slower than expected because this is a rather complicated project, requiring coordination with the electricity sector to implement. According to the plan, the city will remove 102 old electric poles, transfer 180 electric meters of households into 20 new compact electrical cabinets, ensuring aesthetics, and bury all electric wires and telecommunications cables underground.

Hệ thống điện, dây viễn thông trên tuyến đường này đấu nối chằng chịt. Ảnh: Quang An
It is expected that the electricity and telecommunication cable system on Nguyen Thi Minh Khai Street will be completed in July 2024. Photo: Quang An

The unit has sent a document to Vinh City Electricity, requesting the electricity side to accept items such as burying the 22KV line, renovating transformer stations, burying the 0.4KV power system, from which a plan and estimated construction time for this item can be made. However, the unit will also strive to complete the renovation of Nguyen Thi Minh Khai Street in July 2024.

Mr. Nguyen The Anh - Deputy Director of Vinh City Project Management Board