Standing Vice Chairman of the Provincial People's Committee Le Hong Vinh inspected the progress of key projects in Quynh Luu district.

Thanh Toan DNUM_BJZAGZCACE 19:51

On the afternoon of June 19, a working delegation of the province led by Mr. Le Hong Vinh - Member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee inspected the actual progress of construction of key projects in Quynh Luu district. Accompanying were representatives of provincial departments and branches.

Permanent Vice Chairman of the Provincial People's Committee Le Hong Vinh and the working delegation went toCheck construction progressQuynh Nghia bridge project at Km6+00 on provincial road 537B. The project scale belongs to group B with a total investment of 205 billion VND.

Up to now, the project has disbursed over VND91 billion out of the total allocated capital of over VND136 billion. Of which, the provincial budget allocated VND130 billion; the district budget allocated over VND6 billion.

In 2024, the project was allocated 60 billion VND in capital, of which more than 15 billion VND has been disbursed, with nearly 45 billion VND remaining undisbursed. It is expected that by June 30, 2024, 16 billion VND will continue to be disbursed, and the remaining amount will be disbursed before November 30, 2024.

Phó Chủ tịch Thường trực UBND tỉnh Lê Hồng Vinh kiểm tra tiến độ thi công dự án cầu Quỳnh Nghĩa tại Km6+00 trên tuyến đường tỉnh 537B
Standing Vice Chairman of the Provincial People's Committee Le Hong Vinh inspected the construction progress of the Quynh Nghia bridge project at Km6+00 on provincial road 537B. Photo: Thanh Toan

Regarding construction progress, up to now, the contractor has completed 5 piers from T1 to T5, drilled bored piles for M1, M2 abutments, poured concrete for M1; completed casting 15/24 super T beams; completed 1,100/2,060m of K98 roadbed embankment; completed construction of 6/16 culverts of various types and precast more than 1,000 bridge components, culvert items across roads and drainage ditches.

Currently, the project is still stuck with the land clearance, 36 residential land plots of affected households have been inventoried and priced. Of which, 1 plot has approved the compensation plan, while 35 plots have not agreed, the land price is recommended to be low, the land price is proposed to be higher, so the project site clearance has not been completed.

Công nhân đang đẩy nhanh tiến độ thi công trụ cầu tiếp theo
Workers are speeding up construction of the next bridge pier. Photo: Thanh Toan

Next, Permanent Vice Chairman of the Provincial People's Committee Le Hong Vinh and the delegation inspected the construction progress of the National Highway 1A bypass road, Quynh Hau - Quynh Hong - Quynh Dien - Quynh Giang section. The project is 7.13 km long, with a total investment of VND 200 billion, of which the construction estimate is nearly VND 170 billion.

Up to this point, the district has completed the compensation and site clearance for households in Quynh Giang and Quynh Dien communes. The project is still stuck with the site clearance for 2 residential plots in Quynh Hong commune at the location of the road leading to pier M1 (households have requested that the land price is low, so it has not been approved).

Currently, the construction unit is actively speeding up the progress of dredging and filling the roadbed and making efforts to complete each item of the project on time and according to the set plan. Strive to complete the first layer of asphalt in 2024 from Minh An General Hospital to the intersection of National Highway 48B through Quynh Hong commune.

Phó Chủ tịch Thường trực UBND tỉnh Lê Hồng Vinh kiểm tra tiến độ thi công tuyến đường tránh Quốc lộ 1A
Standing Vice Chairman of the Provincial People's Committee Le Hong Vinh inspected the construction progress of the National Highway 1A bypass road, Quynh Hau - Quynh Hong - Quynh Dien - Quynh Giang section. Photo: Thanh Toan

Through the actual inspection of each item of the project, the Standing Vice Chairman of the Provincial People's Committee highly appreciated the active participation and coordination of the investor, departments, branches and localities of Quynh Luu district, in just a short time, a large amount of work was completed to hand over the site to the construction units; the construction progress is ensuring the set plan.

Comrade Le Hong Vinh also requested construction units and supervision consultants to always uphold their sense of responsibility and seek support from Party committees and authorities to resolve difficulties and problems during the construction process.

Regarding the Quynh Nghia bridge project, he requested the construction unit to mobilize human resources, machinery, equipment and necessary conditions, carry out the items to ensure the disbursement of capital on schedule; urgently carry out construction to clear the riverbed, complete before the rainy season to avoid the situation of water flow blockage, causing flooding when there is prolonged heavy rain.

Công nhân đẩy nhanh thi công để hoàn thành cầu Sông Thái
Workers speed up construction to complete the Thai River Bridge. Photo: Thanh Toan

Regarding the National Highway 1A bypass project, the Standing Vice Chairman of the Provincial People's Committee requested the construction unit to spread the roadbed stone and promptly resolve the existing problems in site clearance work, to hand over the site to the contractor to carry out the construction on schedule.