Vice Chairman of the Provincial People's Committee Dinh Viet Hong inspects key drainage reservoirs and dams ahead of typhoon No. 4.

Nguyen Hai August 29, 2019 15:30

(Baonghean.vn) - Requiring dam and reservoir operating units to promptly notify residents when releasing floodwaters and maintain a 24/7 duty roster, this was the spirit of Deputy Chairman of the Provincial People's Committee Dinh Viet Hong during an inspection of critical irrigation works on the morning of August 29th.

Ahead of the forecast that typhoon number 4 will make landfall in the provinces from Nghe An to Quang Binh tomorrow noon (August 30), this morning, the working group of the Provincial Steering Committee for Disaster Prevention and Search and Rescue inspected key reservoirs and dams.

Kiểm tra vận hành cống Diễn Thành, xã Diễn Thành, huyện Diễn Châu. Ảnh: Nguyễn Hải
Inspecting the operation of the flood discharge at Dien Thanh sluice gate, Dien Thanh commune, Dien Chau district. Photo: Nguyen Hai

During an inspection at the Dien Thanh sluice gate in Dien Chau district, based on an understanding of the operational situation and regulations of the sluice gates, the Vice Chairman of the Provincial People's Committee requested the project's command board to coordinate closely with the Northern Irrigation Company to ensure effective operation in the event of heavy rain and flooding.

Cống Diễn Thành khi vận hành thử xã lũ, phía dưới có hàng trăm thuyền bè nên đoàn công tác yêu cầu cùng với thông báo thì phải tổ chức lực lượng kiểm tra, nhắc nhở người dân khi nước dâng cao phải xả lũ 3/3 cửa. Ảnh: Nguyễn Hải
Hundreds of boats are moored below the Dien Thanh sluice gate, so the inspection team requested that, along with announcing when the sluice gates are opened, the management unit must organize a force to inspect and remind people to ensure the safety of their vessels. Photo: Nguyen Hai

At the Vuc Mau Reservoir project in Hoang Mai town, the inspection team reviewed the repair of leaks and the operational measures for opening the reservoir's spillway gates. Accordingly, although the water level is not yet high, to ensure safety for the downstream area, Bac Irrigation Company Limited has not implemented water storage and is proceeding with normal spillway gate operation.

Đoàn công tác kiểm tra tiến độ xử lý các điểm rò rỉ dưới chân đập Vực Mấu, xã Quỳnh Trang, Tx Hoàng Mai. Hiện tại, đơn vị thi công đa xử lý được 70/150 điểm rò rỉ. Ảnh: Nguyễn Hải
The inspection team checked the progress of addressing leaks at the base of the Vuc Mau dam in Quynh Trang commune, Hoang Mai town. Currently, the construction unit has addressed 70 out of 150 leaks. Photo: Nguyen Hai

The delegation visited the Khe San Reservoir irrigation project in Quynh Thang commune (Quynh Luu district) and the Do Luong Weir upgrade project in Do Luong district to conduct on-site inspections. Here, representatives from the Khe San Dam construction site management board stated that the upgrade project, which began in September 2018, has a capacity of 1.2 million cubic meters.3 The project, which is scheduled for completion within two years, is now 80% complete.

Hiện trường thi công công trình đập Khe Sân tại xã Quỳnh Thắng có công suất chứa 1,2 triệu m3 nước. Ảnh: Nguyễn Hải
The construction site of the Khe San dam in Quynh Thang commune, Quynh Luu district, has a storage capacity of 1.2 million cubic meters.3Construction began in September 2018 and is expected to be completed by August 2020. Photo: Nguyen Hai

Meanwhile, the Do Luong weir project has completed 50% of its construction volume, and the elevation markers ensure flood discharge requirements are met, preventing obstruction or disruption to ongoing construction or drainage.

Currently, in response to the threat of typhoon number 4, the project management boards have implemented several measures to ensure the safety of ongoing construction items, including relocating machinery to ensure safety.

Based on the preliminary assessment of flood and storm prevention plans, Vice Chairman of the Provincial People's Committee Dinh Viet Hong acknowledged the proactive response to the storm by the units and the command boards of key drainage dams and reservoirs in the area.

Kiểm tra tình hình thi công và các biện pháp đảm bảo an toàn khi mưa bão tại cống Mụ Bà, Bara Đô Lương tại xã Tràng Sơn, huyện Đô Lương. Ảnh: Nguyễn Hải
Inspecting construction progress and safety measures during storms at Mu Ba sluice gate and Do Luong sluice gate in Trang Son commune, Do Luong district. Photo: Nguyen Hai.
However, the Vice Chairman of the Provincial People's Committee also requested the Project Management Board and the Project Command to thoroughly check the operating plan and coordinate closely with localities on response measures; the project command and the dam operating unit need to continue to raise their vigilance, maintain a strict 24/7 duty schedule; and promptly inform the Provincial Disaster Prevention and Search and Rescue Command when there is an emergency.

When storms occur, flood control units must promptly notify residents and follow proper procedures and regulations.

Featured in Nghe An Newspaper

Latest

x
Vice Chairman of the Provincial People's Committee Dinh Viet Hong inspects key drainage reservoirs and dams ahead of typhoon No. 4.
Google News
POWERED BYFREECMS- A PRODUCT OFNEKO