Vice Chairman of the Provincial People's Committee Dinh Viet Hong inspected important flood control dams before storm No. 4.

Nguyen Hai DNUM_CJZAIZCABJ 15:30

(Baonghean.vn) - Requiring dam operators to promptly notify people when releasing floodwaters and maintain a 24/7 duty regime, that is the spirit of Vice Chairman of the Provincial People's Committee Dinh Viet Hong at the inspection of weak irrigation works on the morning of August 29.

With the forecast that storm No. 4 will make landfall in the provinces from Nghe An to Quang Binh at noon tomorrow (August 30), this morning, a working group of the Provincial Steering Committee for Natural Disaster Prevention and Control inspected key dams.

Kiểm tra vận hành cống Diễn Thành, xã Diễn Thành, huyện Diễn Châu. Ảnh: Nguyễn Hải
Checking the flood discharge operation of Dien Thanh sluice, Dien Thanh commune, Dien Chau district. Photo: Nguyen Hai

Inspecting Dien Thanh sluice gate, Dien Chau district, based on the operation situation and regulations of the sluice gates, the Vice Chairman of the Provincial People's Committee requested the Project Command Board to closely coordinate with the Northern Irrigation Company to operate effectively when floods occur.

Cống Diễn Thành khi vận hành thử xã lũ, phía dưới có hàng trăm thuyền bè nên đoàn công tác yêu cầu cùng với thông báo thì phải tổ chức lực lượng kiểm tra, nhắc nhở người dân khi nước dâng cao phải xả lũ 3/3 cửa. Ảnh: Nguyễn Hải
There are hundreds of boats anchored below Dien Thanh sluice gate, so the working group requested that along with the announcement when the sluice gate is opened, the management unit must organize forces to inspect and remind people to ensure the safety of boats. Photo: Nguyen Hai

At the Vuc Mau Lake project in Hoang Mai town, the inspection team actually fixed the leaks and measures to operate the opening of the lake's spillway. Accordingly, although the water level is not high yet, to ensure safety for the downstream area, Bac Irrigation Company has not implemented the water storage regime and is opening the spillway normally.

Đoàn công tác kiểm tra tiến độ xử lý các điểm rò rỉ dưới chân đập Vực Mấu, xã Quỳnh Trang, Tx Hoàng Mai. Hiện tại, đơn vị thi công đa xử lý được 70/150 điểm rò rỉ. Ảnh: Nguyễn Hải
The working group inspected the progress of handling leaks at the foot of Vuc Mau dam, Quynh Trang commune, Hoang Mai town. Currently, the construction unit has handled 70/150 leaks. Photo: Nguyen Hai

Arriving at the Khe San Lake irrigation project in Quynh Thang commune (Quynh Luu) and the Bara Do Luong upgrade project in Do Luong district, the delegation inspected the field. Here, a representative of the Khe San Dam Construction Site Command said that the upgrade project started in September 2018, with a capacity of 1.2 million m3 Water, construction within 2 years but now 80% completed.

Hiện trường thi công công trình đập Khe Sân tại xã Quỳnh Thắng có công suất chứa 1,2 triệu m3 nước. Ảnh: Nguyễn Hải
Construction site of Khe San dam, Quynh Thang commune, Quynh Luu with a capacity of 1.2 million m3Construction started in September 2018 and is expected to be completed by August 2020. Photo: Nguyen Hai

Meanwhile, the Do Luong wharf project has completed 50% of the volume and the elevation markers ensure flood discharge requirements, without causing congestion or affecting the construction work as well as water drainage.

Currently, to cope with the risk of storm No. 4, the Construction Command Boards have taken a number of measures to ensure safety for construction items and organized the relocation of machinery to ensure safety.

Based on the preliminary situation of flood and storm prevention plans, Vice Chairman of the Provincial People's Committee Dinh Viet Hong acknowledged the proactive response to storms of units and command boards of key dams and reservoirs in the area.

Kiểm tra tình hình thi công và các biện pháp đảm bảo an toàn khi mưa bão tại cống Mụ Bà, Bara Đô Lương tại xã Tràng Sơn, huyện Đô Lương. Ảnh: Nguyễn Hải
Checking the construction status and safety measures during storms at Mu Ba culvert, Bara Do Luong in Trang Son commune, Do Luong district. Photo: Nguyen Hai
However, the Vice Chairman of the Provincial People's Committee also requested the Management Board and the Project Command to carefully check the operation plan and closely coordinate with localities on response measures; the Project Command Board and the dam operating unit need to continue to raise vigilance, strictly maintain 24/24h duty; when there is urgent information, promptly inform the Provincial Steering Committee for Natural Disaster Prevention and Search and Rescue.

When storms occur, flood discharge operators must promptly notify people and follow proper procedures and regulations./.

Featured Nghe An Newspaper

Latest

x
Vice Chairman of the Provincial People's Committee Dinh Viet Hong inspected important flood control dams before storm No. 4.
POWERED BYONECMS- A PRODUCT OFNEKO