Overtime, shorten Tet holiday, speed up progress of Bac Vinh Bus Station

Tien Hung DNUM_CJZABZCABI 17:36

(Baonghean.vn) - Believing that the progress is still slow while there are only two months left until the deadline for putting the project into operation, comrade Huynh Thanh Dien suggested that the investor increase the means and let workers work night shifts.

On the afternoon of January 29, Mr. Huynh Thanh Dien - Vice Chairman of Nghe An Provincial People's Committee led a working delegation to inspect the construction site of Bac Vinh Bus Station (Nghi Kim Commune, Vinh City).

Accompanying the delegation were leaders of the Department of Transport, leaders of the Provincial Police and a number of related units.

Theo chủ đầu tư, sân nền gặp nhiều khó khăn khi thi công do trời mưa. Ảnh: Tiến Hùng
According to the investor, the ground construction encountered many difficulties due to the rain. Photo: Tien Hung

At the site, there are more than 30 workers working. However, there are still many unfinished items such as: wall painting, partition installation, plaster ceiling. The motorbike garage is only 90% complete. Meanwhile, the bus station entrance has only completed pouring pillars, the roof system and other items have not been installed yet...

Bên trong nhà điều hành bến xe. Ảnh: Tiến Hùng
Inside the bus station's management office, materials are scattered. Photo: Tien Hung

In particular, the investor said that due to the prolonged rain, the ground is still very wet. Meanwhile, the weather from now until March will often be rainy, so the construction of the yard will encounter many difficulties, making it difficult to meet the set schedule....

After directly inspecting the site, comrade Huynh Thanh Dien chaired a working session with relevant units to listen to reports and plans to put this project into operation soon.

Phó Chủ tịch UBND tỉnh nghe báo cáo tiến độ tại hiện trường. Ảnh: Tiến Hùng
Vice Chairman of the Provincial People's Committee listens to progress report at the scene. Photo: Tien Hung

Considering this a very important project in ensuring traffic safety and urban order, comrade Huynh Thanh Dien concluded that the project's construction progress is still slow. The cause of the delay as well as the responsibility lies with the investor.

“In the coming time, the investor and contractor must increase equipment and vehicles, work overtime at night, and shorten the Tet holiday to ensure the acceptance progress before March 10, and the project will be put into operation by March 31,” the Vice Chairman of the Provincial People's Committee emphasized.

Tầng 2 nhà điều hành chưa có lan can trong khi đã lát gạch. Ảnh: Tiến Hùng
The second floor of the administration building has no railing. Photo: Tien Hung

Comrade Huynh Thanh Dien also noted the need to ensure labor safety after directly inspecting the construction site. “There is no railing on the second floor of the administration building, while the tiles are paved. The tiles are very slippery and the lighting is dark,” Comrade Huynh Thanh Dien requested the construction unit to quickly install railings as well as enhance the lighting system to ensure the safety of workers.

Regarding the problem of weak soil and difficulties encountered during the construction of the stadium, the Vice Chairman of the Provincial People's Committee said that this is also the responsibility of the investor and at the same time suggested finding a solution. "If necessary, this weak soil layer must be leveled to another place and replaced with hard soil."

Featured Nghe An Newspaper

Latest

x
Overtime, shorten Tet holiday, speed up progress of Bac Vinh Bus Station
POWERED BYONECMS- A PRODUCT OFNEKO