Create conditions for contractors to complete construction on schedule

DNUM_BJZAEZCABE 18:23

(Baonghean.vn)-On April 19, the Provincial People's Committee organized a delegation to inspect the progress of site clearance and ensure traffic safety at the site of the project to upgrade National Highway 1A through Nghe An province. The delegation was led by Mr. Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee.

(Baonghean.vn)-On April 19, the Provincial People's Committee organized a delegation to inspect the progress of site clearance and ensure traffic safety at the site of the project to upgrade National Highway 1A through Nghe An province. The delegation was led by Mr. Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee.

Đồng chí Huỳnh Thanh Điền và đoàn công tác kiểm tra công tác GPMB tại xã Nghi Kim - TP Vinh
Comrade Huynh Thanh Dien and the working delegation inspected the site clearance work at Nghi Kim commune - Vinh city.
Nút giao thông cầu vượt đường sắt tại địa bàn xã Nghi Kim đang được đẩy nhanh tiến độ
The railway overpass intersection in Nghi Kim commune is being accelerated in construction progress.

In Vinh City and Nghi Loc, households subject to clearance and relocation have received compensation and moved to new places, creating conditions for construction units to speed up progress. In Hoang Mai Town, in recent days, the entire political system has joined in, supporting people to dismantle structures, trees, and houses to hand over the site to construction units.

Kiểm tra công tác GPMB tại khu vực đường tránh kênh nhà Lê ở huyện Nghi Lộc
Checking the site clearance work at the Le canal bypass area in Nghi Loc district
Đường tránh kênh nhà Lê đoạn qua huyện Nghi Lộc đã được bàn giao mặt bằng và đơn vị thi công đã hoàn thành nhiều hạng mục
QL1A section avoiding Nha Le canal in Nghi Loc has had its site handed over, and the construction unit has also completed many items of the project.

Up to now, Nghe An has had 3 localities complete the handover of land: Vinh City, Nghi Loc, Hoang Mai Town with a route length of 73.27km/73.8km, reaching 99%. Currently, Quynh Luu and Dien Chau still have some households that have not handed over land.

In places where the site has been handed over, construction units are concentrating all their forces and machinery to work in 3 shifts, regardless of holidays, so that the project can be put into use soon.

Lãnh đạo huyện Diễn Châu báo cáo về những
Leaders of Dien Chau district pledged to focus on propaganda and mobilization to complete site clearance work in the next few days.
Huyện Diễn Châu vẫn còn 33 hộ dân chưa bàn giao mặt bằng, lãnh đạo huyện cam kết sẽ hoàn thành công tác giải phóng mặt bằng trong vài ngày tới
Dien Chau district still has 33 households that have not yet handed over their land.

Đồng chí Huỳnh Thanh Điền yêu cầu chính quyền địa phương Quỳnh Lưu phải nỗ lực hơn nữa trong công tác vận động, tuyên truyền
Comrade Huynh Thanh Dien requested the Quynh Luu local government to make more efforts in advocacy and propaganda work. When the locality hands over the site, the contractor must promptly start construction.
Một số hộ dân ở Quỳnh Văn (Quỳnh Lưu) vẫn chưa chấp hành chủ trương của nhà nước
Some households in Quynh Van (Quynh Luu) have not yet complied with the state's policy and have not yet handed over the site to construction units.

Comrade Huynh Thanh Dien praised the spirit and positive attitude of the authorities at all levels and the people in the places where the land was handed over on schedule and the policies of the State were well implemented. At the remaining points, Comrade Huynh Thanh Dien requested that local departments, branches and organizations continue to mobilize people to understand that the State's policy in expanding National Highway 1A is to contribute to the industrialization and modernization of the country, for a rich people and a strong country; all must be for the national interest, and no difficulties or obstacles must be caused in the land clearance work.

Đồng chí Huỳnh Thanh Điền biểu dương sự nỗ lực của chính quyền TX Hoàng Mai, đã hoàn thành công tác GPMB
Comrade Huynh Thanh Dien praised the efforts of Hoang Mai Town authorities in completing the site clearance work for National Highway 1A.
Người dân và đơn vị thi công đang tích cực tháo dỡ các công trình, bàn giao mặt bằng cho đơn vị thi công
People of Hoang Mai town are actively dismantling constructions and handing over the site to the construction unit.

After propaganda and mobilization, in difficult areas, we will coordinate to organize construction protection and create conditions for contractors to keep up with construction progress.

Video Clip of the working group inspecting land acquisition and clearance in localities:

.

News, photos:Duc Chuyen