Removing obstacles and urgently completing site clearance work for Hoang Mai II Industrial Park

Thanh Le DNUM_BHZADZCACF 18:57

Vice Chairman of Nghe An Provincial People's Committee Bui Thanh An requested Hoang Mai town to closely coordinate with departments, branches and investors to urgently achieve site clearance progress of Hoang Mai II Industrial Park.

On the afternoon of March 17, Comrade Bui Thanh An - Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee inspected the progress of site clearance at Hoang Mai II Industrial Park. Accompanying him were leaders of provincial departments, branches and sectors and Hoang Mai town.

 quang cảnh làm việc
Comrade Bui Thanh An and the delegation worked with leaders of Hoang Mai town and Hoang Thinh Dat Joint Stock Company. Photo: TL

The project "Investment in construction and business of infrastructure of Hoang Mai II Industrial Park" invested by Hoang Thinh Dat Joint Stock Company in Quynh Vinh commune, Hoang Mai town with an area of ​​nearly 335 hectares, total registered capital of 1,900 billion VND.

By December 2024, 183.1 hectares had been approved for measurement. However, so far, only more than 32 hectares have been decided to be reclaimed; Land for lease with an area of ​​20 hectares. Of which, 1 project has been put into operation; 1 project of Thien Nang Group is under construction, expected to be put into operation in August this year; the remaining 150 hectares have not yet approved the compensation and site clearance plan.

 Phạm Văn Hào
Comrade Pham Van Hao - Vice Chairman of Hoang Mai Town People's Committee reported on the progress of site clearance work of the town. Photo: TL

The reason is that people have not agreed and requested to increase agricultural land prices higher than 55,000 VND/m2.2, increase the unit price of trees and crops and compensate according to the density of crops, intercropping; compensate for assets and arrange resettlement for households subject to population dispersion by household into new economic zones.

The remaining area of ​​nearly 152 hectares that has not been approved for measurement has now completed its documents and is preparing to submit for measurement approval with an area of ​​nearly 129 hectares; more than 23 hectares are still stuck with overlapping boundaries, incorrect locations, areas, land types... and are not qualified to be completed and submitted for measurement approval.

 Hoàng Thịnh Đạt
Representative of Hoang Thinh Dat Joint Stock Company speaking at the meeting. Photo: TL

At the meeting, leaders of departments, branches, Hoang Mai town and Hoang Thinh Dat Joint Stock Company focused on exchanging, analyzing, discussing and proposing solutions to solve problems and difficulties in compensation and site clearance.

Concluding the meeting, Vice Chairman of the Provincial People's Committee Bui Thanh An acknowledged the efforts and responsibilities of departments, branches, localities, and investors in implementing the project. He also emphasized that the urgent clearance of Hoang Mai II Industrial Park and other industrial parks in the province is an important task to achieve the province's growth target in 2025 and the following years; at the same time, implementing the provincial leaders' viewpoint of caring for, standing side by side, and accompanying businesses.

bna_-bui-thanh-an-5ea0a0cbabaa9030cd975d51c91ae965(1).jpg
Comrade Bui Thanh An - Vice Chairman of the Provincial People's Committee concluded the meeting. Photo: TL

To ensure the progress of handing over the site to investors and implementing essential infrastructure items within and outside the scope of the projects, Vice Chairman of the Provincial People's Committee Bui Thanh An requested departments, branches, localities and investors to coordinate and focus on implementing more drastic land clearance work based on 4 principles in compensation and site clearance work: Do not let people suffer but do not take advantage; Compensation funds come from the State budget, so they must be economical, effective and in accordance with regulations; Price and payment must be made immediately after each file is completed; Close coordination between investors and departments, branches and localities to have timely handling plans, in accordance with regulations and specific progress. The goal is to complete the site clearance work for the entire area of ​​the Hoang Mai II Industrial Park project before May 31, 2025.

 lanh đạo thị xã Hoàng Mai
Leaders of Hoang Mai town attended the meeting. Photo: TL

Regarding the problems in site clearance, he suggested that the leaders of Hoang Mai town, together with the leaders of the Department of Agriculture and Environment, the Department of Finance, and members of the provincial working group, discuss a clear solution. Hoang Mai town proposed a solution and sent it to the provincial working group for study.

 quang cảnh
Delegates listened to an introduction about the progress, difficulties and obstacles in the site clearance work of the Hoang Mai II Industrial Park Project. Photo: TL

Regarding property compensation, migration and resettlement of households subject to population dispersal by household to new economic zones, the Vice Chairman of the Provincial People's Committee assigned the People's Committee of Hoang Mai town to urgently review the records of each household, propose plans, and consult the Department of Construction and other sectors to determine the correct subjects to implement appropriate compensation plans.

Regarding the drainage system around Hoang Mai II Industrial Park, comrade Bui Thanh An requested that departments, branches, localities and investors coordinate to complete it soon, within 2 years, and by the end of 2025, the wastewater drainage project of the factories will be put into operation.

Vice Chairman of the Provincial People's Committee Bui Thanh An suggested that Hoang Thinh Dat Joint Stock Company should study and propose the implementation of a third industrial park so that the province can include infrastructure investment projects in the public investment plan for the next period. At the same time, attract more highly automated projects to reduce labor, focusing on projects that increase local budget revenue.

 kiểm tra dự án
Provincial leaders, departments, branches and Hoang Mai town inspected the Hoang Mai II Industrial Park project. Photo: TL

The Vice Chairman of the Provincial People's Committee assigned the Departments of Agriculture and Environment, Finance, and Construction, according to their functions and tasks, to promptly resolve difficulties and problems upon receiving recommendations and proposals from the Hoang Mai Town People's Committee. The Management Board of the Southeast Economic Zone regularly monitors and urges relevant departments, branches, localities, and agencies to implement and ensure progress; promptly report to the Provincial People's Committee on existing problems, difficulties, and arising issues (if any).

"The urgent completion of site clearance for industrial parks in general and Hoang Mai II Industrial Park in particular is an important task to achieve the province's growth target; accompanying businesses to create a breakthrough mechanism for private economic development," the Vice Chairman of the Provincial People's Committee emphasized.