Standing Committee of Provincial People's Council supervises public investment in Con Cuong district

Plum Blossom DNUM_AIZBAZCACE 12:30

On the morning of October 8, the Standing Committee of the Provincial People's Council had a working session with Con Cuong district according to the monitoring program on the results of 3 years of implementing the medium-term public investment plan, period 2021-2025 in Nghe An province.

Comrade Nguyen Nhu Khoi - Member of the Provincial Party Committee, Vice Chairman of the Provincial People's Council chaired the meeting. Also attending the meeting were Comrade Thai Thi An Chung - Member of the Provincial Party Committee, Deputy Head of the Provincial National Assembly Delegation; leaders of the Provincial People's Council Committees and the Office of the National Assembly Delegation and the Provincial People's Council, and leaders of Con Cuong district.

 Đoàn giám sát HĐND tỉnh khảo sát Dự án
The Provincial People's Council's monitoring delegation surveyed the Project to Upgrade the tourist route from National Highway 7 to Khe Kem Waterfall tourist area. Photo: Mai Hoa

Before working with Con Cuong district, the monitoring delegation of the Provincial People's Council directly surveyed the progress of a number of projects in the district. These include the Thanh Nam Bridge Project across the Lam River; the Project to Upgrade the Tourist Route from National Highway 7 to Khe Kem Waterfall Tourist Area; and the Project to Build a Secondary Boarding School for Ethnic Minorities in Con Cuong District.

Con Cuong district has 67 public investment projects and works in the period 2021 - 2025

 Quang cảnh cuộc làm việc. Ảnh- Mai Hoa
Working scene. Photo: Mai Hoa

According to the report of the People's Committee of Con Cuong district, the locality has closely followed the regulations of the Law on Public Investment, the Law on Construction, the Law on Bidding, etc., along with the directive documents of the Provincial People's Committee on public investment management for serious implementation.

The district also promptly implemented capital allocation plans and resolutions of the Provincial People's Council on the Medium-term Public Investment Plan from the State budget, period 2021-2025; Decision on allocating the Medium-term Public Investment Plan for the period 2021-2025 of the People's Committee of Nghe An province. Strengthening investment management from the State budget and Government bonds, associated with handling outstanding debts in basic construction.

 Đồng chí
Mr. Tran Anh Tuan - Vice Chairman of Con Cuong District People's Committee reported on the results of implementing the public investment plan in the district for the period 2021 - 2023. Photo: Mai Hoa

Accordingly, basic public investment capital is allocated for the right purpose, focused, and implemented in accordance with the district's growth target; debt for basic construction volume of completed projects is prioritized for debt repayment, priority is given to capital allocation for transitional projects, especially projects that can be completed within the year.

According to the public investment plan for the period 2021 - 2025, the central budget capital is allocated to Con Cuong district to implement 6 projects. In 3 years (2021 - 2023), the allocated capital is more than 205 billion VND and the disbursement result reached 100% with 4 completed projects put into use; the remaining 2 projects are expected to be completed in 2024.

Đ
Comrade Thai Thi An Chung - Member of the Provincial Party Executive Committee, Deputy Head of the Provincial National Assembly Delegation spoke at the meeting. Photo: Mai Hoa

Regarding the public investment plan, the provincial budget capital is allocated to Con Cuong district to implement 9 projects. In 3 years (2021 - 2023), the total capital plan is more than 123 billion VND and the disbursement result reached 100% and 3 works and projects have been completed and put into use; 6 projects are continuing to be implemented in 2024 - 2025.

Notably, during the implementation of the medium-term public investment plan for the 2021-2023 period, Con Cuong district did not incur any outstanding debts for basic construction. During the project implementation process, the district was also proactive and flexible in adjusting capital sources from low-disbursement projects to projects with good implementation volume.

 Dự án cầu Thanh Nam, bắc qua sông Lam hiện đang tập trung thi công hoàn thành khâu cuối cùng, đoạn đấu nối từ Quốc lộ 7A vào mố cầu. Ảnh Mai Hoa
The Thanh Nam Bridge project across the Lam River is currently focusing on completing the final stage, the connecting section from National Highway 7A to the bridge abutment. Photo: Mai Hoa

Regarding the National Target Program for Socio-Economic Development of Ethnic Minorities and Mountainous Areas, with a total medium-term planned capital for the period 2021 - 2025 in the district of nearly 395 billion VND, 52 projects and works are arranged to be implemented; of which, 35 projects and works are invested by the district and 17 projects and works are invested by the commune level. The disbursement results for 2 years (2022 - 2023) reached nearly 100% and in 2024, it is currently low compared to the general level of the whole province, only reaching 29.1%.

At the meeting, Con Cuong district raised a number of difficulties and problems in compensation and site clearance, especially for projects related to agricultural and forestry land in determining the subjects to be compensated, because land from agricultural and forestry land was contracted to workers and laborers of agricultural and forestry land, but was later transferred, so it took more time to determine the exact subjects.

 Đoàn giám sát của HĐND tỉnh
The Provincial People's Council's monitoring delegation surveyed the site for the project to build a secondary school for ethnic minorities in Con Cuong district. Photo: Mai Hoa

On the other hand, the mountainous region is characterized by a lack of raw materials. Con Cuong district proposed to allow the district to exploit local materials, both to ensure timely project implementation and to reduce investment costs. The conversion of forest use to other purposes to implement the project still faces many difficulties, because the conversion must go through many ministries and branches, so it has not yet been completed to hand over the entire site to the construction unit.

Based on the district's report, at the meeting, members of the Provincial People's Council's monitoring delegation also raised many issues related to shortcomings in implementing public investment plans; quality of investment policy consultation; implementation of investment policy procedures; investment construction; difficulties in decentralizing to the commune level to be the investor of some works and projects; principles and criteria for allocating public investment capital...

 Đồng chí Lô Văn Thao - Phó Bí thư Huyện uỷ, Chủ tịch UBND huyện Con Cuông nêu một số khó khăn trong thực hiện đầu tư các dự án. Ảnh- Mai Hoa
Comrade Lo Van Thao - Deputy Secretary of the District Party Committee, Chairman of the People's Committee of Con Cuong district pointed out some difficulties in implementing investment projects. Photo: Mai Hoa

Speed ​​up construction progress of key projects

Concluding the meeting, on behalf of the monitoring delegation, comrade Nguyen Nhu Khoi - Member of the Provincial Party Executive Committee, Vice Chairman of the Provincial People's Council highly appreciated the efforts of Con Cuong district in implementing the investment plan.

Many projects and works were implemented quickly, disbursed well, without outstanding debts, even with surplus investment capital; of which, some projects and works were completed and put into use, contributing to promoting socio-economic development in the district.

 Đồng chí Nguyễn Như Khôi
Comrade Nguyen Nhu Khoi - Member of the Provincial Party Executive Committee, Vice Chairman of the Provincial People's Council concluded at the meeting. Photo: Mai Hoa

Acknowledging the reflections on difficulties, obstacles and proposals of the district; The Vice Chairman of the Provincial People's Council requested Con Cuong district to continue to focus on thoroughly resolving the existing problems and obstacles in each project to ensure construction progress, promote project effectiveness soon and avoid project adjustment. Pay attention to clearing and settling completed projects in accordance with legal regulations.

Regarding the Project to Upgrade the Tourist Route from National Highway 7 to Khe Kem Waterfall Tourist Area, through a direct survey, Comrade Nguyen Nhu Khoi said that although the project has been completed, currently, due to the impact of rain causing landslides on many sections of the route, there is a risk of traffic safety loss; he suggested that the district proactively repair and overcome the problem to promote the effectiveness of the project in the long term.

 Đoàn giám sát của HĐND tỉnh khảo sát thi công Dự án cầu Thanh Nam, bắc qua sông Lam. Ảnh- Mai Hoa
The Provincial People's Council's supervision delegation surveyed the construction of the Thanh Nam Bridge Project across the Lam River. Photo: Mai Hoa

Along with that, focus on removing difficulties, speeding up the construction progress of the Thanh Nam bridgehead connection section, and putting the project into use soon. In particular, focus on resolving difficulties and problems in site clearance for the construction of the Con Cuong District Boarding Secondary School for Ethnic Minorities; and recommend the province to prioritize allocating sufficient capital to start the project and put it into use as soon as possible.

Vice Chairman of the Provincial People's Council Nguyen Nhu Khoi also requested Con Cuong district, based on the practice and experience of implementing public investment in previous stages, to proactively advise, propose, and develop a quality and effective public investment plan for the 2026 - 2030 period.