Construction work continues day and night on the Than Vu tunnel on the North-South expressway.

Pearl January 9, 2023 08:21

(Baonghean.vn) - The Than Vu Tunnel is one of the most challenging sections of the North-South Expressway due to its mountainous terrain and considerable length. Taking advantage of favorable weather conditions, construction units are working three shifts to complete this crucial section as soon as possible.

The Than Vu road tunnel in Dien Phu is 1,280m long, xuyên through Than Vu mountain to connect Dien Phu commune, Dien Chau district and Nghi Dong commune, Nghi Loc district (both in Nghe An province). Photo: Tran Chau

This is one of the most challenging sections of the North-South Expressway, specifically the Dien Chau - Bai Vot segment. Therefore, the construction unit is working tirelessly to meet the deadline. Currently, Hoa Hiep Co., Ltd. has mobilized over 200 people, including experienced engineers and skilled workers from various corporations. In addition, they have deployed four modern tunnel boring systems, dozens of concrete spraying machines, wheel loaders, excavators, and are working three shifts continuously. (Photo: Tran Chau)

To ensure safe working conditions for engineers and workers, companies must continuously pump oxygen into the tunnels. Photo: Tran Chau

Mr. Dao Van Thong, from Do Luong, who drives an excavator for Hoa Hiep Co., Ltd., said: Currently, eight excavators are working all day. Each machine is driven by two people in shifts, each person working one and a half shifts a day, equivalent to 12 hours of continuous work. Construction at a height of 70 meters requires experienced driving skills and safety is paramount. Photo: Hai Viet

The Than Vu Tunnel has a permanent design, with a reinforced concrete tunnel lining. It also includes Than Vu Bridge 1 and Than Vu Bridge 2, crossing a mountain pass and Xuan Duong Lake. Phase 1 will involve the complete construction of the first tunnel tube. Photo: Tran Chau

The North-South Expressway project, the section passing through Nghe An province, is approximately 87.84 km long and comprises two sub-projects: the Nghi Son - Dien Chau section and the Dien Chau - Bai Vot section. It passes through Hoang Mai town and the districts of Quynh Luu, Yen Thanh, Dien Chau, Nghi Loc, and Hung Nguyen. (Photo: Engineers regularly discussing work on the construction site. Photo: Tran Chau)

The North-South Expressway is being built as a Class 100-120 highway, with a design speed of 100-120 km/h, except for the section through Than Vu Mountain which has a design speed of 80 km/h. Photo: Construction vehicles continuously operate to ensure the progress of the North-South Expressway project, specifically the section through Dien Chau - Bai Vot, according to schedule. Photo: Quang An