(Baonghean.vn) - Although it has been handed over to the electricity industry for management, it has not been upgraded synchronously and has been in use for a long time, so the power grid system in Yen Thanh is seriously degraded, posing a potential safety risk.
 |
According to incomplete statistics, currently in the whole Yen Thanh district there are nearly 2,000 seriously damaged electric poles that must be replaced. In the photo: The electric pole of Road 4, which leads the power line from Hamlet 4 to Hamlet 9, Vien Thanh, passing through his family's house, was broken in half and had to be supported by a bamboo pole. |
 |
The herringbone power line running along the inter-hamlet road through Hamlet 6 is increasingly degraded, the exposed wires are sagging down, very dangerous. During the rainy season, people have to avoid going through this road because of the risk of electric shock. |
 |
Mr. Vu Xuan Hong - Head of Hamlet 5, Vien Thanh Commune reported: The large capacity transformer station, located next to the Hamlet Cultural Center, with a makeshift protective fence, has caused many cases of electric shocks to cattle and people. |
 |
Many commune-planned lands have been approved by authorities to be auctioned to the people, but because of the power poles and lines passing through, many households cannot complete their houses. |
 |
The power pole on Highway 4 located at the intersection between Cau Mang hamlet and Hamlet 6A, Tien Thanh commune, Yen Thanh district has been in a state of being both supported and braced for more than 6 months. |
 |
Exposed iron core electric pole can collapse at any time. |
 |
The electrical wires are tangled like a spider web. |
 |
Because the power line system has not been upgraded for many years, it has sagged and fallen very low. |
 |
With no other choice, people have to use wooden poles to support themselves, which is both unsightly and obstructs traffic. |
 |
According to Mr. Ho Sy Vinh - Director of Yen Thanh Electricity,Since taking over, the electricity industry has taken advantage of investment projects of over 200 billion VND to install stations, upgrade from ground stations to suspended stations, and replace power lines. In the first 6 months of this year alone, Yen Thanh Electricity has allocated nearly 500 million VND to replace 5,000 - 6,000 m of power lines for people, but the quality of electricity has not yet met the demand. In the photo:The electricity quality is not guaranteed, compact lamps cannot light up so people have to buy rechargeable bulbs to use. |
 |
During peak hours, the electricity quality in Nhan Tien hamlet, Tien Thanh commune is unusable, incandescent bulbs only flicker like this. |
Anh Tuan - Phan Hien