Close-up of landslide treatment construction on National Highway 46B through Nguoc Mountain, Thanh Chuong District

Huy Thu DNUM_CGZAGZCACE 17:42

When the rainy season comes, National Highway 46B, through Nguoc Mountain, Thanh Chuong District, often experiences serious landslides. The landslide treatment project currently under construction here will help eliminate traffic black spots in Nguoc Mountain.

bna_1..jpg
Nguoc Mountain is located along the Lam River in Thanh Ngoc and Ngoc Son communes (Thanh Chuong). It has 3 peaks, 109m high. National Highway 46B through Nguoc Mountain is quite dangerous because one side is high mountain, the other side is deep river. During the resistance war against the US, the route through Nguoc Mountain was fiercely bombarded by the enemy. Today, this route is still a traffic black spot. Photo: Huy Thu
bna_2.jpg
In recent years, during the rainy season, landslides have frequently occurred at Nguoc Mountain. In particular, in 2020, Nguoc Mountain suffered a serious landslide with a length of nearly 2 km, completely blocking National Highway 46B. After each landslide, the authorities have handled and resolved the incident, such as blasting rocks, erecting steel nets, embanking rivers, making ditches, adjusting roads, etc. Photo: Huy Thu
bna_3.jpg
The handling of landslides in Nguoc Mountain on a large scale, to create a safe road section, minimizing landslides every rainy season is not only the expectation and expectation of traffic participants on this route but also of local people. Photo: Huy Thu
bna_4.jpg
Currently, the project "Landslide treatment section KM39 +200 - KM39 +750 National Highway 46B, Nghe An province" invested by Road Management Area II is under construction in Nguoc mountain. The construction site is located in Thanh Ngoc commune (Thanh Chuong). Photo: Huy Thu
bna_5(2).jpg
A representative of Road Management and Construction Joint Stock Company 470, which is working at the landslide treatment site, said: The project has many items, directly constructed by 3 companies. The units are urgently mobilizing human resources and labor vehicles. The project started on May 18 and is expected to be completed in 6 months. Photo: Huy Thu
bna_6(2).jpg
According to this project, the protruding points of Nguoc Mountain, which dominates National Highway 46B on the section KM39 +200 - KM39 +750, will be deeply cut, clearing soil and rocks to widen the roadway. Photo: Huy Thu
bna_7.jpg
A landslide-prone area at Nguoc Mountain (which used to be protected by steel mesh) is being lowered. According to construction units, machinery and equipment are currently working quite smoothly. During the process of cutting the mountain, if large rocks are encountered, a permit will be requested from the authorities to blast rocks. Photo: Huy Thu
bna_8.jpg
Nguoc Mountain will be leveled in steps (from 2 to 6, 7... steps) depending on the location and height of the mountain to prevent landslides. Power lines on the mountain that affect the construction work will be moved up. Photo: Huy Thu
bna_9(2).jpg
Some solid concrete sections blocking the riverbank of Highway 46B have been demolished for construction. There are large rocks that have rolled down the mountain into the river, not stuck on the road. People and vehicles passing through here need to observe carefully. Construction units also need to increase water spraying to prevent dust and environmental pollution. Photo: Huy Thu
bna_10(1).jpg
To ensure the safety of life and property of traffic participants, every day from 7am to 11am and 2pm to 5pm, construction units have erected barriers on National Highway 46B through Nguoc Mountain, prohibiting people and vehicles from passing at specific times, and opening the barriers every 15 minutes. Strictly following the regulations of the construction site will contribute to maintaining general safety for everyone. Photo: Huy Thu
bna_11.jpg
Mr. Le Dinh Thanh - Vice Chairman of Thanh Chuong District People's Committee said: "The anti-landslide project at Nguoc Mountain is very important for the travel of Thanh Chuong district people, because this is the main road connecting Thanh Chuong district with Vinh city and neighboring areas. For that reason, when the Department of Roads had a policy to handle this section, the District People's Committee actively coordinated to clear the site and hand over the clean site to the investor for implementation. The completion of the project will help vehicles to travel through this section more conveniently, especially when the rainy season comes". Photo: Huy Thu
Handling landslides in Nguoc mountain. Video: Huy Thu