Need to speed up disbursement of public investment capital plan in 2016
(Baonghean.vn) - The Provincial People's Committee issued Official Dispatch No. 100032 on accelerating the disbursement progress of the 2016 public investment capital plan according to Official Dispatch No. 2144/CD-TTg of the Prime Minister.
The content of the document clearly stated that, despite many efforts and attempts, the disbursement result of the 11-month public investment capital plan of Nghe An province only reached 67.85%.
Some capital sources have low disbursement rates such as: Government Bond capital only reached 51.57% (of which the health sector has the lowest disbursement, only 38.99%), foreign capital only reached 51.93%, and national target program capital only reached 64.11%.
![]() |
Construction of Nghi Thiet Port. Photo: PV |
Meanwhile, there is not much time left from now until the end of the year to disburse the 2016 public investment plan and the plan extended from 2015 to 2016. In order to strive to complete 100% of the assigned plan in 2016 in accordance with the spirit of Resolution No. 60/NQ-CP dated July 8, 2016 of the Government, Official Dispatch No. 2144/CD-TTg of the Prime Minister, the Provincial People's Committee requests units to promptly and seriously carry out the following tasks:
- Units resolutely direct investors to urgently accelerate the implementation and disbursement of the 2016 public investment capital plan, accelerate compensation, site clearance, bidding, proactively remove difficulties and obstacles, ensure construction progress; promptly complete documents, make immediate payments to the State Treasury when there is a volume of acceptance, especially projects using government bond capital, foreign capital and capital of the national target program for new rural areas.
- Units must take full responsibility before the Provincial People's Committee if they do not disburse all the assigned planned capital. At the same time, strictly review and clarify the responsibilities of individuals and organizations that cause delays in disbursement of projects, leading to failure to disburse all the assigned planned capital, resulting in loss of capital in accordance with the spirit of Official Dispatch No. 2144/CD-TTg dated November 29, 2016 of the Prime Minister.
- The Department of Finance ensures sufficient capital and imports tamis for timely disbursement projects.
- Nghe An State Treasury shall make payments to investors in accordance with current regulations, promptly guide and remove difficulties and obstacles for investors to ensure disbursement of all assigned plan targets.
- Request units to urgently and seriously carry out assigned tasks. If there are any difficulties or problems during the implementation process, report them to the Department of Planning and Investment for synthesis and advice to the Provincial People's Committee for timely handling to ensure the completion of the 2016 public investment plan with quality and efficiency./.
Provincial People's Committee
RELATED NEWS |
---|