Chairman of the Provincial People's Committee inspected the construction progress of Ho Tong Thoc road
(Baonghean.vn) - Directing at the scene, comrade Thai Thanh Quy requested the investor of the project to renovate and upgrade Ho Tong Thoc street to speed up the construction progress so that the project can be completed in August 2019.
On the afternoon of July 12, Comrade Thai Thanh Quy - Alternate Member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee directly inspected and checked the construction progress of Ho Tong Thoc road. Accompanying him were Major General Nguyen Huu Cau - Member of the Provincial Party Committee, Director of the Provincial Police; representatives of relevant departments, agencies and Vinh city.
![]() |
Comrade Thai Thanh Quy requested the Project Management Board of Nghe An General Hospital Phase 2 to coordinate with the construction unit to adjust the underground water tank of the hospital to move back inside to ensure the road is constructed according to the design. Photo: Thanh Cuong |
This is one of the moves showing that the People's Committee of Nghe An province is determined to completely resolve the problems related to this traffic route. A day earlier, at the discussion session of the 9th session - Provincial People's Council term XVII, responding to the opinions of voters and People's Council delegates, Chairman of the Provincial People's Committee Thai Thanh Quy affirmed that there will be many solutions to clear the road by the end of August 2019.
![]() |
Planning diagram of old and new Ho Tong Thoc street. Photo: Thanh Cuong |
Ho Tong Thoc Street located in Nghi Phu Commune (Vinh City) is a traffic route with a long history, serving the traffic activities of local people. By 2003, according to the detailed planning of Nghi Phu Commune, Ho Tong Thoc Street no longer played the role of an inter-regional road, but instead was planned as a 24m wide road. Therefore, the last section of Ho Tong Thoc Street is included in the planning project of Nghe An General Hospital, phase 2.
In March 2016, the Nghe An General Hospital Phase 2 project began construction; the construction process blocked Ho Tong Thoc Street and this was the reason why more than 100 households in Nghi Phu commune sent petitions to the provincial and city levels and branches.
![]() |
Chairman of the Provincial People's Committee Thai Thanh Quy directs the construction of Ho Tong Thoc road at the site. Photo: Thanh Cuong |
Faced with that situation, in September 2018, the Provincial People's Committee decided to reopen Ho Tong Thoc route to meet people's needs.
Implementing the direction of the Provincial People's Committee, on May 4, 2019, Vinh City People's Committee issued Decision No. 2567/QD-UBND approving the adjustment of the economic-technical report on construction investment of the project: Renovation and upgrading of Ho Tong Thoc Street. In which, the construction item of a 9m-wide planned road through the Nghe An General Hospital, phase 2, was added. This road section has a length of 264.99m, a red line of 9m, a road surface of 7m wide, and a sidewalk of 1m on each side. The construction cost is determined to come from the provincial budget, with a value of 4 billion 578 million 539 thousand VND.
According to the plan, Ho Tong Thoc route will be opened in the first quarter of 2019; however, up to now, it has not been implemented. The reason is that the hospital's water tank was built on the road about 3m.
![]() |
Ho Tong Thoc Street, the section running through Nghe An General Hospital, is over 264m long. At this point, the construction unit is spreading rocks and rolling the road. Photo: Thanh Cuong |
Directing at the scene, comrade Thai Thanh Quy requested the People's Committee of Vinh City - the investor of the project to renovate and upgrade Ho Tong Thoc Street to speed up the construction progress so that the project can be completed in August 2019.
The Chairman of the Provincial People's Committee also requested the Department of Construction, Department of Transport, Department of Natural Resources and Environment and related units to closely coordinate, support and create favorable conditions for the construction unit and the Project Management Board of Nghe An General Hospital, Phase 2 of the road to be implemented according to the design and ensure progress.
Regarding the underground water tank of the hospital, comrade Thai Thanh Quy requested the Project Management Board of Nghe An General Hospital Phase 2 to coordinate with the construction unit to adjust this item to move back in order to ensure the road is constructed according to the design. In addition, the Chairman of the Provincial People's Committee also directed the City People's Committee to install additional lighting systems along the road.
![]() |
Chairman of the Provincial People's Committee Thai Thanh Quy directed Vinh city that the process of connecting Ho Tong Thoc street with Le Nin avenue must ensure the effective operation of the traffic light system, the synchronization of the volta, sidewalks... Photo: Thanh Cuong |
In particular, for the intersection between Ho Tong Thoc Street and Le Nin Avenue, the head of the Provincial People's Committee requested that the road connection process must ensure the effective operation of the traffic light system. In addition, it is necessary to carefully study to expand this intersection, while ensuring the synchronization between the circuit breaker, sidewalk and the entire infrastructure of the area.
Chairman of the Provincial People's Committee Thai Thanh Quy inspected the construction progress of Ho Tong Thoc road. Clip: Thanh Cuong. |