There is no source of funding for land acquisition and resettlement for the Vinh-Cua Lo Boulevard project.
(Baonghean.vn)- Voters in some localities requested the province to speed up the progress of granting resettlement land to households in the Vinh - Cua Lo Boulevard project.
The relevant authorities responded to this issue as follows:
According to the report of the Department of Transport in Document No. 817/SGTVT-QLDA dated April 4, 2016, the People's Committee of Cua Lo town in Document No. 39/BC-UBND dated April 4, 2016, the People's Committee of Nghi Loc district in Document No. 493/UBND-TNMT dated April 7, 2016 and the People's Committee of Vinh city in Document No. 1475/UBND-PTQD dated April 8, 2016: The Vinh - Cua Lo Boulevard Project was approved by the People's Committee of Nghe An province in Decision No. 994/QD.UBND-CN dated March 3, 2010, the route has a length of 10.832 km, passing through 03 districts, towns and cities: Vinh city (3.4 km), Nghi Loc district (4.8 km) and Cua Lo town (2.632 km).
![]() |
Construction of Nghi Duc resettlement area to serve the resettlement of Vinh-Cua Lo avenue, photo by Chau Lan |
The Compensation Council for Land Acquisition and Site Clearance of districts, towns and cities has cleared 6.352km/10.832km, reaching 57% (of which: Residential land, gardens: 0.3km/3.3km; Agricultural land 5.932km/6.732km; Other land 0.12km/0.8km).
Since January 2014, the project has not been allocated capital, leading to a temporary suspension of compensation, support and resettlement.
![]() |
Perspective of both sides of Vinh-Cua Lo boulevard. |
Up to now, the implementation status of 16 resettlement areas (including 10 residential land resettlement areas) of districts, towns and cities is as follows:
- Vinh City: Including 05 residential land resettlement areas, 01 area for moving graves and 01 resettlement area for Nghi Phu 2 Primary School:
+ Completed compensation and support for site clearance and is implementing infrastructure construction for 02 residential land resettlement areas (No. 02,03).
+ 03 residential land resettlement areas (01,04,05) and grave resettlement area, Nghi Phu 2 Primary School: Currently, funding sources have not been arranged, so site clearance work has not been implemented.
- Cua Lo Town: Including 01 residential land resettlement area that has completed about 90% of the construction volume, but there are 18 land lots that have had their resettlement arrangement plan approved for relocated households but have not yet arranged capital to pay, so the households cannot relocate and have not yet paid the resettlement land use fee according to the plan.
- Nghi Loc District: Including 04 residential resettlement areas, 01 commune People's Committee headquarters, 01 primary school, 02 cemetery areas.