(Baonghean.vn) - On June 20, comrade Nguyen Hong Ky - Member of the Provincial Party Committee, Director of the Department of Transport inspected the progress of the Tay Nghe An road project.
 |
Leaders of the Department of Transport inspected the construction of Tay Nghe An road. |
 |
Check out the Tay Nghe An route. |
![Kiểm tra kỹ thuật cầu Na Hỷ xã Nhôn Mai - Tươ]ng Dương](https://bna.1cdn.vn/2015/06/20/uploaded-dataimages-201506-original-_images1180756_3.jpg) |
Technical inspection of Na Hy bridge, Nhon Mai commune - Tuong Duong. |
The Tay Nghe An road project has a total route length of 184 km (of which phase 1 is 78 km long, with 25 bridges completed; phase 2 is 106 km long, with 16 bridges built). The route starts at Dong Van commune (Que Phong), ends at Muong Xen town (Ky Son), passing through 3 districts: Que Phong, Tuong Duong, Ky Son.
 |
Na Hy - Tuong Duong Bridge constructed by Joint Stock Company 423 has been basically completed. |
 |
Construction units concentrate equipment and vehicles to speed up progress. |
 |
Construction of Tay Nghe An road. |
 |
Asphalt on Tay Nghe An road. |
According to the plan, phase 2 will be completed on June 30 and to ensure the progress, the construction units have focused on human resources and machinery to implement the project. Currently, the construction units have handed over 44km/106km and have paved the road surface of 94km (88.6%)...
After inspecting the Tay Nghe An road project site in Ky Son district, comrade Nguyen Hong Ky - Director of the Department of Transport had a meeting with the construction units. He acknowledged the efforts of the units in overcoming difficulties such as hot and dry weather, scarcity of raw materials, complex construction sites, etc. to speed up the project's progress, and emphasized: Currently, there are still some contractors on the route who have not focused on speeding up the progress, affecting the project. Therefore, in this final stage, the Department of Transport will organize working groups to inspect and urge contractors to implement the project, thereby handling problems during the implementation process. Currently, the units need to take advantage of favorable weather to focus on speeding up the progress of completing Tay Nghe An road by June 30.
 |
The route has been paved for 94 km so traffic is very convenient. |
 |
Tay Nghe An road is basically open. |
During the meeting, the leaders of the Department of Transport promptly resolved difficulties and problems in the implementation of the project such as: Disbursement of capital, handling of some congestion points on the route...
Hoang Vinh