Speed ​​up construction progress of Khe Bo hydropower reservoir flood avoidance road

July 7, 2015 09:53

(Baonghean.vn)- In the current situation, the section of National Highway 7 from Km 148+00 to Km 148+500 (in Tam Thai commune - Tuong Duong) is often flooded by the Khe Bo hydroelectric reservoir and landslides. Vietnam Power Development Joint Stock Company has invested in a project to avoid flooding in the Khe Bo hydroelectric reservoir worth 12.5 billion VND.

The project started in January 2015, according to the commitment to put into use within 12 months, up to this point the construction unit has mobilized many vehicles and machinery to excavate over 120,000 m3 of earth and rock, completed the roadbed, and is expected to put into use by October 2015 (2 months ahead of schedule). Currently the construction unit is focusing on constructing the roadbed, handling landslides, ensuring the completion of key items before the rainy season.

Đơn vị thi công đang tập trung xử lý các điểm sạt lở núi
Construction units are focusing on handling landslides.
Máy móc mở đường tránh ngập QL 7 đoạn đi qua xã Tam Thái-Tương Dương
Machinery opens flood avoidance road on National Highway 7 passing through Tam Thai - Tuong Duong commune
Xe cơ giới đổ đất để làm đường tránh ngập
Motor vehicles dump soil to make roads to avoid flooding
Cống qua QL 7 cơ bản đã thi công được trên 90% khối lượng công trình
The culvert across National Highway 7 has basically completed over 90% of the project volume.
Đất được đổ gia cố đoạn thường sạt lở lòng hồ thủy điện Khe Bố
Soil was poured to reinforce the landslide-prone section of Khe Bo hydroelectric reservoir.