Khe Bo Hydropower Project (capacity 100MW) belongs to the Ca River hydropower cascade system and after completion, in addition to the task of generating electricity, it also has the role of regulating the downstream flow of Ban Ve Hydropower Plant, creating water sources and pushing salinity for the downstream area of ​​Ca River in the dry season...

(Baonghean.vn) -Khe Bo Hydropower Project (capacity 100MW) belongs to the Ca River hydropower cascade system and after completion, in addition to the task of generating electricity, it also has the role of regulating the downstream flow of Ban Ve Hydropower Plant, creating water sources and pushing salinity for the downstream area of ​​Ca River in the dry season...

With such an important role, Khe Bo Hydropower Plant is currently rushing to complete the final items to generate electricity and along with that, resettlement work is also being paid attention to by all levels and sectors and the construction unit is speeding up the progress to help people in their new place feel secure and stabilize their lives.

Due to the urgent need for resettlement to serve Khe Bo Hydropower Plant, at 8 resettlement sites in the district, construction units have completed and are implementing many technical infrastructure projects such as: public works disbursed more than 14.7 billion VND, power supply system disbursed nearly 6.5 billion VND, domestic water supply works disbursed more than 3.6 billion VND, traffic roads disbursed more than 51.2 billion VND, irrigation works disbursed nearly 467 million VND.

Thanks to timely disbursement, it has created favorable conditions for construction units to speed up the construction of technical infrastructure and resettlement housing. At the resettlement areas of Tam Dinh, Yen Thang, Thach Giam, Luong Minh communes..., the basic requirements for serving people's lives and activities have been met. Because the resettlement of Khe Bo hydropower plant is a relocation, people are very excited because the living conditions at the new place are more complete and convenient, and meanwhile the agricultural land area has not changed (because the production land has not been recovered). In addition, people are also supported to invest in land reclamation, building fields to develop agricultural production, and doing business in commercial services...

Mr. Trinh Minh Chau - Vice Chairman of the District People's Committee said: "Khe Bo Hydropower Project has 585 households including 2,539 people affected and up to now, 557 households including 2,426 people have been relocated from the reservoir area to 8 resettlement areas in the district. The households after moving to the resettlement areas are all very excited and thanks to the benefits of resettlement policies, their lives have soon stabilized, production and business have been favorable, and their lives have stabilized".

However, a current difficulty in resettlement areas is the lack of capital to build an internal traffic system that meets the criteria for new rural construction, so it is in great need of continued attention and support from all levels and sectors./.