Unfinished project, road from Con Cuong town to Binh Chuan has many landslides
(Baonghean.vn) - The road from Con Cuong town to Binh Chuan through Mau Duc and Don Phuc communes is about 29 km long. In 2006, the project...
(Baonghean.vn) -The road from Con Cuong town to Binh Chuan through Mau Duc and Don Phuc communes is about 29 km long. In 2006, the road construction project was started with a total estimated cost of 128 billion VND for 4 packages including 29 km of road and 9 bridges. However, the unfinished construction project caused landslides in many places on the road, making travel very difficult and causing waste.
After more than 6 years, the project has completed 18 km of road, the remaining 11 km of road has completed the foundation; 2 bridges have been completely built, the remaining 7 bridges have only completed the bridge abutments and have had to be temporarily stopped due to lack of funds.
Observing at the present time, at the 11km of unfinished road, the roadbed and roadbed have sunk a lot, there are sections where cars can hardly pass and if Con Cuong has floods and storms this year, this road will certainly be broken. According to the staff of the Department of Industry and Trade of Con Cuong district, at the end of 2012, the estimated cost of the Con Cuong - Binh Chuan town road project was adjusted to 215 billion VND. However, due to financial difficulties, the project completion progress will be extended to 2015.
Below are some pictures of landslides at the road project from Con Cuong town to Binh Chuan:

Con Cuong - Binh Chuan town road is under construction.
Because the embankment and ditches have not been built, the road surface has been eroded by rain and floods.
In many places, the road body is eroded and cracked.
Rocks and soil from the high mountains have covered the road surface, so a construction unit is having to reinforce and temporarily level the roadbed.
In unfinished bridge projects, the iron of the bridge piers has rusted.
Nhat Lan