(Baonghean.vn) - Among the projects being implemented by the transport sector, the Tay Nghe An route investment and construction project is a key project, the vital road of the West region that the sector is focusing on accelerating progress to complete this July.

Các nhà thầu đang gấp rút thi công
Contractors are rushing to construct.

The total length of the route is 184 km with a total investment of 2,127 billion VND for both phases. The route starts at Dong Van commune (Que Phong), ends at Muong Xen town (Ky Son), passing through 3 districts of Que Phong, Tuong Duong, Ky Son. Of which, phase 1 has been completed (78 km, 25 bridges) and put into use.

Gói thầu TNA17 do Công ty Xây dựng Tây Nam thi công đang gấp rút hoàn thành tại điểm K110 đoạn qua xã Nhôn Mai- Tương Dương
Tay Nam Construction Company is urgently constructing at point K110, section through Nhon Mai - Tuong Duong commune.

Currently, phase 2 of the project is in the final stage, the Department of Transport is focusing on directing contractors to complete it as quickly as possible this July. At the construction site, engineers, workers and many machines are still focusing day and night to enter the active construction phase, working hurriedly on the long stretches of road...

Đến nay, Công ty CP 482 đã rải nhựa 3,8/3,8km (Ảnh: đoạn qua xã Mai Sơn - Tương Dương đã hòan thành)
Up to now, the contract by Joint Stock Company 482 has paved 3.8/3.8km of asphalt (Photo: the section through Mai Son - Tuong Duong commune has been completed)

Mr. Ho Viet Vinh - Deputy Director of the Department of Transport said: The Tay Nghe An route has a policy of being paved with asphalt since the beginning of March 2015. In March, April, May, and June, an additional 45km of asphalt was paved, culverts were completed on the route, and 5 more bridges were opened (although from the end of May until now, it has often rained for 1 to 2 hours a day, but the contractor still overcomes the transportation route and weather conditions to carry out the construction properly).

1
The Tay Nghe An route has a length of 184 km with a total investment of 2,127 billion VND for both phases, and has been basically completed.

“Currently, all contractors are working hard. There are 6 locations along the route where crushers are installed to take advantage of the local stone. We are focusing on directing contractors to speed up the construction progress in accordance with the direction of the Department's leaders to complete the project before July 30, 2015. Thanks to that, phase 2 of the project has completed and handed over 44km/106km; opened 15/16 bridges; paved 94km/106km of the road surface. The foundation, culverts and retaining walls of all kinds have been completed (100%).” – Mr. Ho Viet Vinh said.

The completion and use of the Tay Nghe An route is expected.create connections in trade, convenient travel for people,bring many changes to the socio-economic development of Western Nghe An.