Urgent handling of Nguoc mountain landslide on National Highway 46B in Nghe An

Van Truong August 9, 2024 06:00

Faced with the serious landslide situation on Nguoc Mountain on National Highway 46B through Thanh Chuong District, Nghe An Province, the Vietnam Road Administration is urgently implementing a large-scale landslide treatment project to ensure people's safety.

Cip: Van Truong
van truong 234
Nguoc Mountain is located on National Highway 46B in Thanh Ngoc and Ngoc Son communes (Thanh Chuong). The terrain is quite rugged, with high mountains on one side and deep rivers on the other. Serious landslides have occurred over the years. Photo: Van Truong
van truong 3
In 2020, a serious landslide on Nguoc Mountain threatened the lives of people traveling through the area. The traffic management unit has taken steps to handle and fix the problem, such as blasting rocks and erecting steel nets, but danger is always lurking. Photo: Van Truong
van truong mer
Faced with the above situation, from June 18, 2024, the Vietnam Road Administration has deployed the Project "Handling landslides on section KM39 +200 - KM39 +750 of National Highway 46B, Nghe An province" with the Road Administration Department II as the investor, expected to be completed and put into use after 6 months. Photo: Van Truong
van truong 4
Mr. Nguyen Duc Dung - Deputy Director of Road Management Area II said: According to the project, all landslides and rockfalls of Nguoc Mountain will be thoroughly treated, then create 8-12 m high shocks, with 5-6 shocks depending on the height of Nguoc Mountain. In particular, National Highway 46 B passing through Nguoc Mountain has 3 curves, now being treated to create 2 curves, widening the roadway at the foot of the mountain for safe traffic. Photo: Van Truong
van truong 5
Currently, taking advantage of favorable weather, construction vehicles are working through noon. Photo: Van Truong
van truong 1
Construction units mobilized maximum machinery and worked at full capacity, reaching over 40% of the volume at this point. Currently, the excavation and treatment of landslides and hanging rocks have been completed, and the muscles are being pulled from the high mountains, expected to be completed and put into use by the end of 2024. Photo: Van Truong
van truong 2
Mr. Le Dinh Thanh - Vice Chairman of Thanh Chuong District People's Committee said: National Highway 46B is the main route connecting Thanh Chuong District with Vinh City and neighboring areas. The implementation of the Nguoc Mountain landslide treatment project is very important to ensure the safety of local people. Therefore, the district actively coordinates with the investor to clear the land, helping the project to be completed soon for convenient traffic. Photo: Van Truong