Nghe An urges to accelerate public investment disbursement in 2019
(Baonghean.vn) - Nghe An Provincial People's Committee issued Document No. 5785/UBND-KT to provincial departments, branches, district People's Committees, investors, and project management boards requesting to accelerate the implementation and disbursement of the 2019 public investment plan.
Specifically, the People's Committee of Nghe An province requested the Department of Planning and Investment to preside over and coordinate with relevant agencies and units to advise the Provincial People's Committee to allocate all remaining capital in 2019 in accordance with regulations.
The Department of Finance shall enter the budget into the tabmis system (Budget and Treasury Management Information System) in a timely and complete manner; at the same time, direct investors to complete procedures to recover advance capital planned with the State Treasury to have a basis for control and complete procedures to recover advance capital planned in accordance with regulations.
Assign sectors and levels to direct investors to urgently and thoroughly handle projects that still have problems in site clearance to promptly hand over the site to construction contractors; promptly complete procedures for submitting design approval, cost estimates, bidding procedures, etc.; speed up the bidding process and sign contracts to send to the State Treasury where the account is opened to disburse capital early, not to let payments accumulate at the end of the year.
![]() |
Vinh City focuses on site clearance for the 95m road section through Xuan Huong hamlet, Nghi Duc commune, and urgently completes resettlement areas in Xuan Dong hamlet and Xuan Trung hamlet (Nghi Duc commune). Photo: Lam Tung |
In particular, the Provincial People's Committee requested that by September 2019, the sectors and levels be assigned to review the disbursement capacity of each project to propose transferring capital from projects that cannot fully disburse to projects that need to supplement the 2019 capital plan to the Department of Planning and Investment.
The Department of Planning and Investment is assigned to preside over and coordinate with the Department of Finance and the Provincial State Treasury to promptly synthesize and propose competent authorities to adjust the plan in accordance with the spirit of Directive 09/CT-TTg dated April 1, 2019 of the Prime Minister, Resolution No. 33/NQ-HDND dated December 16, 2016 of the Provincial People's Council and Decision No. 96/QD-UBND dated January 10, 2019 of the Provincial People's Committee promulgating the main tasks and solutions on directing and implementing the socio-economic development plan of Nghe An province in 2019.
As of July 30, 2019, the disbursement rate of public investment capital in Nghe An reached 54.48% of the plan. Nghe An is also accelerating site clearance and project progress: Vinh - Cua Lo Road Project (phase 1), Cua Hoi Bridge over Lam River, projects at Vinh International Airport, Cua Lo Port, North-South Expressway project, Eastern section of Nghe An province...