Bustling and urgent at Vinh Airport construction site

December 4, 2014 16:07

(Baonghean.vn) - The Vinh Airport construction project is invested by Vietnam Airports Corporation. The project is divided into 3 main works: passenger terminal, multi-level road, car parking lot and aircraft parking expansion.

The construction of the passenger terminal (with a total investment of 500 billion VND) was designed and built based on the idea of ​​simulating the image of a lotus flower. The terminal is designed to serve domestic flights, with a total floor area of ​​11,706 m2, which can accommodate 2-4 million passengers/year and the waiting room is arranged for 4 peak flights with the number of passengers up to 1,500 people.

Mr. Bui Van Thang - Head of the Supervisory Team - Vinh Airport Project Management Board said: "The construction of this important project is undertaken by the joint venture of contractors Luu Nguyen Construction Company Limited - Hoa Binh Development and Construction Investment Joint Stock Company - Dai Dung Mechanical Trading Joint Stock Company - European Plastic Window Joint Stock Company and Loc Phuc Company Limited. The construction of M&E and aviation technical systems is undertaken by the joint venture of VIC Construction Company Limited - HAAI Architecture Company Limited. This project started on April 26, 2013, and has so far completed over 90% of the work volume. The contractors are focusing on human resources and modern machinery and equipment to complete the project on January 15, 2015."

RELATED NEWS

Cảng hàng không Vinh hiện nay đang quá tải
Vinh airport is currently overloaded.
Trên công trường các đơn vị thi công tập trung nhiều nhân lực để triển khai việc thi công và tạo nên không khí lao động sản xuất rất nhộn nhịp, khẩn trương.
At the construction site, construction units concentrate a lot of human resources to carry out the construction and create a very bustling and urgent production atmosphere.

At the multi-level road and parking lot project, constructed by the Traffic Construction Corporation 4. According to the project design, the multi-level road is 279 m long, 9 - 14.5 m wide, accommodating 2-3 car lanes, while the parking lot and traffic system have an area of ​​19,450 m2. Although this project started on March 8, 2014, it has now been basically completed and has been highly appreciated by the investor for its quality, progress, labor safety and environmental sanitation...

Công nhân của Tổng công ty Xây dựng Công  trình giao thông 4 đang vận chuyển trụ thép
Workers of Traffic Construction Corporation 4 are transporting steel pillars.
Công nhân Công ty CP nhựa Châu Âu đang hoàn thiện sản phẩm tại công trình
Workers of Chau Au Plastic Joint Stock Company are completing products at the construction site.
Cán bộ kỹ thuật ghi nhật ký công trình
Construction diary technician
Đoàn thanh niên Tổng công ty Xây dựng Công  trình giao thông 4 đảm nhận công trình tình nguyện tại công trình thi công Cảng hàng không Vinh
Youth Union of Traffic Construction Corporation 4 undertakes volunteer work at Vinh Airport
Đoàn thanh niên Tổng công ty Xây dựng Công  trình giao thông 4 đảm nhận công trình tình nguyện tại công trình thi công Cảng hàng không Vinh
Youth Union of Transport Construction Corporation 4 undertakes volunteer work at Vinh Airport
Thi công hạng mục mở rộng sân đỗ máy bay
Construction of aircraft parking expansion project
Thi công hạng mục mở rộng sân đỗ máy bay
Construction of aircraft parking expansion
Công nhân Công ty TNHH xây dựng Lưu Nguyễn đang tích cực đẩy nhanh tiến độ
Workers of Luu Nguyen Construction Company Ltd. are actively speeding up the progress.
Diện mạo mới của ACảng hàng không Vinh
New look of Vinh Airport

Currently, at the project to expand the aircraft parking area (construction area is 44,000 m2, ensuring 6 parking positions for ATR 72, A321 aircraft), the Traffic Construction Corporation 4 is also speeding up the construction progress and has completed more than 85% of the project volume. At the project, the Traffic Construction Corporation 4 has gathered hundreds of staff and workers and many types of modern machinery and equipment to determine to complete by the end of 2014, shortening the construction time by about 2 months compared to the signed contract.

With the determination of contractors, the Vinh Airport construction project will be completed on January 15, 2015, promptly meeting the travel needs of passengers during the upcoming Lunar New Year.

Hoang Vinh

Featured Nghe An Newspaper

Latest

x
Bustling and urgent at Vinh Airport construction site
POWERED BYONECMS- A PRODUCT OFNEKO