Tien Dong DNUM_BCZAJZCACE 13:29

The project to upgrade and expand National Highway 7 was approved by the Ministry of Transport in 2022 with a total investment of more than VND1,300 billion, although localities have drastically cleared the land. However, to date, there are still many "bottlenecks" that have not been resolved.

bna_115.jpg
The project to upgrade and expand National Highway 7 passes through Dien Chau, Yen Thanh, and Do Luong districts. In Dien Chau, there are still some points that are stuck and have not completed land clearance. In particular, the North-South railway overpass in Dien Phuc commune is one of the most congested points, causing many difficulties for vehicles passing through here. Photo: Tien Dong
bna_100.jpg
According to the design, this overpass has 2 lanes and 8 spans, however, to date, some of the western abutments of the railway have not been completed due to land clearance problems. If this overpass project had been completed on schedule, vehicles passing through here would not have had to stop to avoid trains. Photo: Tien Dong
bna_85.jpg
The eastern and western sections of the North-South Expressway passing through Dien Cat commune are also among the areas where site clearance has not been completed, preventing the construction unit from implementing the project. Photo: Tien Dong
bna_78.jpg
Dien Cat is one of the locations with the most "bottlenecks" in Dien Chau district that have not been resolved as many households have not yet handed over their land, causing many sections to be constricted, affecting the traffic of vehicles. Photo: Tien Dong
bna_69.jpg
Minh Chau Commune is also a place where land acquisition and clearance have not been completed in Dien Chau District. From above, it is clear that some plots of land that have not been cleared are interspersed with sections that have been handed over. However, due to the "leopard skin" terrain, it is difficult for contractors to bring in machinery and equipment for construction. Photo: Tien Dong
58 co
In Vien Thanh commune (Yen Thanh), right near the commune People's Committee headquarters, there is a "bottleneck" that has not yet been able to clear land. Photo: Tien Dong
bna_56.jpg
In Bao Thanh commune (Yen Thanh), although the scope of upgrading and expanding National Highway 7 does not affect households (located outside the fence), many households still prevent construction units from constructing the roadbed, only agreeing to construct the water ditches on both sides. Photo: Tien Dong
bna_51.jpg
A problem at the foot of Cao bridge, Cong Thanh commune. Photo: Tien Dong
bna_37.jpg
Similar to Bao Thanh commune, in Trang Ke market area (My Thanh), people only agreed to build water ditches on both sides but did not allow construction units to construct the roadbed. Photo: Tien Dong
bna_30-24e9316ba4de3b636e3284418208b132.jpg
A section still stuck in the ground in My Thanh commune can be easily seen being narrowed from above. Photo: Tien Dong
bna_16.jpg
My Thanh is one of the localities with the most land acquisition problems in Yen Thanh district. Photo: Tien Dong
bna_ghep(1).jpg
Right at the end of My Thanh commune (from Dien Chau district to Do Luong), a "bottleneck" at a used car machinery trading facility has not been resolved. Photo: Tien Dong