N5 and D4 routes must be opened before October.

DNUM_BAZADZCABG 14:29

(Baonghean.vn) - On the morning of March 10, a working delegation of the Provincial People's Committee led by Mr. Nguyen Xuan Duong - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee visited, surveyed and directed units and localities to speed up the progress of site clearance for construction of roads D4 and N5.

Also attending were comrade Le Ngoc Hoa - Vice Chairman of the Provincial People's Committee; leaders of provincial departments, branches and sectors, leaders of Nghi Loc district and Nghi Thiet commune.

Thăm
The working group inspected the construction progress of the bridge connecting Nghi Thuan commune and Nghi Dong commune on route N5.
Rời Nghi Thuận
Officials of the Southeast Economic Zone Management Board report on the construction progress of route D4 in Nghi Thiet commune.

Currently, on these two routes, there are still some points that have not been cleared in the areas of Nghi Thiet, Nghi Yen, Nghi Thuan and Nghi Dong communes (Nghi Loc district). The reason is determined to be that people have not agreed with the compensation and support plans. Routes D4 and N5 located in the Southeast economic zone are the two main routes serving the transportation of products of Song Lam Cement Joint Stock Company and serving the people. Routes D4 and N5 connect from Song Lam Cement Factory located in Do Luong district to the Clinker Grinding Station and Nghi Thiet seaport (Nghi Loc).

Tiếp đó, đồng chí Nguyễn Xuân Đường và đoàn công tác thăm
The Vissai Group's leaders reported the scale and progress of the construction of the clinker grinding station and Nghi Thiet deep-water seaport to the provincial People's Committee delegation.

After conducting a survey at locations where the land has not been cleared and listening to explanations and recommendations from leaders of departments, branches and leaders of Nghi Loc district, concluding the working session, comrade Nguyen Xuan Duong emphasized: Song Lam Cement Factory Project is one of the major investment projects in Nghe An with a total capital of nearly 30 trillion VND approved by the Provincial People's Committee in Decision No. 1466/QD.UBND-XD dated April 16, 2015.

When the project is completed and put into operation (expected to sell the first batch of products by the end of 2016), it will not only create a large and stable source of jobs for the people, thereby promoting the development of the province's economy, but also contribute to building the image of Nghe An as a reliable destination for domestic and foreign investors.

Despite such great significance, in general, site clearance work at some locations in Nghi Thiet, Nghi Yen, Nghi Thuan and Nghi Dong communes has progressed very slowly, causing difficulties for investors and construction units.

Đồng chí Nguyễn Xuân Đường kết luận buổi làm việc.
Comrade Nguyen Xuan Duong concludedemphasize to create the most favorable conditions for investors,By all means, N5 and D4 routes must be cleared before this October so that the investor can transport clinker to Nghi Thiet Port.

In order for the project to be completed on schedule, the Chairman of the Provincial People's Committee requested the entire political system from Nghi Loc district to the commune to identify site clearance as an important political task; district leaders need to regularly inspect, review, urge, and coordinate with the media to propagate to people to understand the purpose and meaning of the project, thereby raising awareness of some households that are still procrastinating and opposing...

Regarding the remaining funding source (35 billion VND) for site clearance, it is not a funding source that has been balanced since the beginning of the year, however, the province and departments and branches will be determined to resolve it as soon as possible.

South Scene