(Baonghean.vn)- On April 1, comrade Nguyen Xuan Duong - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee and the provincial working delegation inspected the site clearance work of the project to upgrade National Highway 1A through Nghe An province. The delegation included comrade Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee and leaders of relevant departments, agencies and branches.
 |
Chairman of the Provincial People's Committee listened to the report on site clearance work in Vinh City |
 |
The construction project of the railway overpass through Vinh City is being accelerated. |
At the inspection locations in Vinh City, Nghi Loc, Dien Chau, Quynh Luu and Hoang Mai Town, the Chairman of the Provincial People's Committee and the working delegation listened to local leaders and construction units report on the site clearance situation, difficulties and problems in the implementation process.
 |
Inspecting land acquisition and clearance work in Nghi Loc district |
 |
Nghi Loc district still has 2.03/13.96km of land clearance left. |
 |
Chairman of Dien Chau District People's Committee reports on land acquisition and compensation situation in the district |
 |
Currently, Dien Chau still has 2.3km/28.05m that has not been liberated. District leaders have committed to completing the liberation this week. |
According to preliminary reports from localities, currently, along the entire National Highway 1A passing through our province, there are still nearly 10 km of land that have not been cleared. The main reason is that some households still have questions about compensation during the clearance process, along with the lack of determination and decisiveness of some local authorities.
 |
Quynh Luu district leaders report on existing problems in land acquisition and clearance in the locality |
 |
The Chairman of the Provincial People's Committee requested localities, including Hoang Mai Town, to complete site clearance work before April 15, 2014. |
 |
Quynh Giang and Quynh Van communes (Quynh Luu) are localities that are behind in land acquisition and clearance. |
 |
By April 1, Hoang Mai Town had cleared 14.4/15.4 km of land. |
After listening to the reports of the localities, departments and branches on the progress of land acquisition and clearance, the Chairman of the Provincial People's Committee concluded: The project to upgrade and expand National Highway 1A is a national key project, therefore, the authorities at all levels must take drastic action to mobilize and explain to the people about the policies of the Party and the State, all must focus on site clearance, creating conditions for construction units to speed up the completion of the project. Localities are required to complete the site handover (including places where the site must be resettled) before April 15, 2014.
Video of the working group inspecting the progress of National Highway 1A site clearance:
.