Speed up disbursement of basic construction capital, ensure construction quality
(Baonghean.vn) - That was the opinion of Chairman of the Provincial People's Committee Thai Thanh Quy at the conference on implementing the basic construction investment plan for the first 6 months of the year, tasks and solutions for the last 6 months of 2019 organized by the People's Committee of Nghe An province on the afternoon of June 18.
![]() |
Delegates attending the conference. Photo: Viet Phuong |
Disbursement reached 50% of the plan
Reporting at the conference, Director of the Department of Planning and Investment Nguyen Van Do said: Although there are still many difficulties, with the strong direction of the Provincial People's Committee, the efforts of all levels in implementing the project to improve the provincial competitiveness index (PCI), improve the investment and business environment, especially reforming administrative procedures, creating conditions to attract investment; at the same time, synchronously implementing socialization solutions, speeding up the progress of land use rights auctions, preventing revenue loss, implementing cost savings, preventing investment losses to create resources for investment development.
The 2019 public investment plan was assigned to over 3,038 billion VND, reaching over 1,563 billion VND in the first 5 months of the year, reaching 51.45% of the plan; disbursement was 1,281 billion VND, reaching 42% - higher than the same period, in the top 14 provinces with high disbursement in the country (the national average disbursement only reached 23.25% compared to the National Assembly's assignment). It is estimated that in the first 6 months of the year, the volume of basic construction works in Nghe An reached 57.7%, disbursement reached 50% of the plan.
![]() |
Comrade Thai Thanh Quy - Alternate member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee spoke and proposed to speed up the disbursement progress of capital construction but must ensure the quality of the works, strengthen inspection and supervision of the works. Photo: Viet Phuong |
There are 2 sources of disbursement that are quite good and have increased significantly compared to the same period: local budget sources according to scoring criteria are nearly 50% (same period in 2018 is nearly 34%); source of national target program for new rural construction is more than 49% (same period in 2018 until June, capital allocation was completed).
There are 9 districts with good disbursement rates (over 50%): Dien Chau 80.2%, Quynh Luu 73.78%, Nghi Loc 68.46%, Thanh Chuong 66.86%; Yen Thanh, Thai Hoa, Tan Ky, Hung Nguyen, Cua Lo. The sectors with good disbursement rates are Transport (over 55%); Department of Agriculture and Rural Development 52.53%.
In 2019, up to this point, 46 new projects have been granted with a total registered investment capital of more than 5,858 billion VND.
However, some capital sources have not yet been assigned plans for implementation. The disbursement progress of some capital sources and projects is still slow.
Speaking at the conference, some delegates shared some of the reasons for the slow disbursement. According to investors, the reason is that many new projects and packages are implementing bidding procedures, which takes a long time. Some projects are adjusting projects, changing investment scale and location. Some projects have to carry out compensation for site clearance or are stuck with compensation for site clearance...
Chairman of Tuong Duong District People's Committee Phan Duc Son said: In 2019, the total investment in the area was 163 billion VND, disbursement reached nearly 24%. Mr. Son suggested: Tuong Duong has 103 households affected by flood discharge last year and are currently living temporarily. Currently, the district is implementing 3 resettlement projects in Luong Minh and Yen Na communes, but the capital is only 3/25 billion VND, requesting the province to continue creating favorable conditions.
![]() |
Director of the Department of Planning and Investment Nguyen Van Do reported on the disbursement of investment in construction in the first 6 months of the year. Photo: Viet Phuong |
Need to develop specific disbursement scenarios
Speaking at the conference, Chairman of the Provincial People's Committee Thai Thanh Quy highly appreciated the results of capital construction disbursement in the first 6 months of the year, recognizing the efforts of departments, branches and localities in capital construction investment.
However, some capital sources and localities have low disbursement rates. Compensation for site clearance is difficult and needs to be overcome. The target set for 2019 is to achieve a disbursement progress of 96-100%. To speed up the progress, it is recommended to review the entire project to have a solution for direction.
![]() |
Construction unit of the Vinh - Cua Lo asphalt route through Nghi Loc district. Photo: Viet Phuong |
In the coming time, it is necessary to focus on site clearance, especially on key projects that are stuck in site clearance. Strengthen supervision of disbursement progress; establish interdisciplinary teams and working groups; resolve any slow-down stages. Some sectors and districts with slow disbursement or high planning targets need to develop specific monthly and quarterly disbursement scenarios for implementation.
All levels and sectors direct investors and project management boards to continue to strictly implement Resolution 70 of the Government on tasks and solutions to accelerate the progress of implementation and disbursement of public investment capital plans. At the same time, accelerate the progress of key projects, strengthen the appraisal of investment projects and bidding work; have solutions to handle outstanding debts in basic construction arising after December 31, 2014 in accordance with the provisions of the Law on Public Investment. Assign the Department of Planning and Investment to review the projects at the end of September, for projects that are slow to implement and disburse, report to the Provincial People's Committee to transfer capital to other projects.
"Speed up the disbursement of capital construction but must ensure the quality of the works, strengthen inspection and supervision of the works" - the head of the Provincial People's Committee emphasized.