Speed up construction progress of Yen Xuan bridge
(Baonghean.vn) - On the afternoon of March 15, the working delegation of the Provincial People's Committee led by comrade Le Ngoc Hoa inspected the construction progress of the Yen Xuan Bridge Project and directedsite clearance work twobridgehead.
Also attending were representatives of provincial departments and branches; leaders of Hung Nguyen and Nam Dan districts and leaders of construction units.
![]() |
Comrade Le Ngoc Hoa and the delegation of the Provincial People's Committee came to the construction site to inspect the progress of the Yen Xuan Bridge Project. |
Yen Xuan Bridge was started on October 2, 2015 with a total length of about 3.6 km, of which the bridge is 1.89 km long and the approach roads at both ends of the bridge are 1.40 km long. The total investment of the project is over 900 billion VND.
When completed, the project will end the isolation of 9 communes in Nam Dan district and 5 communes in Duc Tho district, Ha Tinh province during the flood season. At the same time, Yen Xuan bridge will connect with Provincial Road 558, National Highway 15A, Linh Cam bridge to create a complete and shortest traffic network connecting Vinh with the Vietnam - Laos Border Gate.
Up to this point, after 5 months of construction, the units have achieved 48.8% of the work volume. It is expected that the North bank approach bridge will start laying girders on March 20 and be completed on May 30. The South bank approach bridge will start laying girders on March 25 and be completed on July 10, 2016.
![]() |
Cienco4 Corporation's staff reported the construction progress on the diagram to the Vice Chairman of the Provincial People's Committee and the working delegation. |
![]() |
The construction unit mobilized many machines and equipment on the North bank to ensure the bridge's completion on July 20. |
![]() |
Workers of Tuan Loc Construction Investment Joint Stock Company are driving piles on the south bank of Yen Xuan bridge. |
After checking the actual situation at the site and listening to the progress report, comrade Le Ngoc Hoa assessed that the workload and items in the North had exceeded the schedule by 20-25 days, while the South bank was on schedule.
To ensure the bridge's inauguration and use on the occasion of National Day, September 2, comrade Le Ngoc Hoa requested the construction units on the South bank to speed up the progress to avoid flooding, and must complete the beam launching by mid-May at the latest.
Regarding the land clearance work on the North bank of Hung Nguyen district, payment must be completed to the remaining household by March 20 at the latest to hand over the clean land to the construction unit. Nam Dan district (South bank) must complete the procedures and compensation documents to pay compensation and reclaim land from the people, and must hand over the clean land by March 25 at the latest.
![]() |
Comrade Le Ngoc Hoa requested that construction units must concentrate maximum human and material resources to ensure and exceed progress, especially before the flood season, they must complete the construction of the overpass over Lam River. |
.