Solving problems in Southeast Economic Zone projects

DNUM_BBZBAZCABH 17:49

(Baonghean.vn) - The Chairman of Nghe An Provincial People's Committee requested that investors submit specific reports on a number of provincial proposals so that the Provincial People's Committee can give opinions and assign them to sectors and localities to resolve the proposals at the projects.

On the afternoon of October 11, comrade Nguyen Xuan Duong - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee inspected and resolved a number of problems at a number of projects in the Southeast Economic Zone. Accompanying him were comrade Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee and related departments and branches.

With a sense of urgency, in the afternoon, the provincial working delegation inspected and grasped the situation at the Vissai Seascape Project; DKC Petroleum Port; Project of Wharf No. 5, 6 - Cua Lo Port; the relocation of fishing boats at Cua Lo Port and the planning project of Cua Lo International Port Cluster, in the Southeast Economic Zone.

 Đồng chí Nguyễn Xuân Đường - Phó Bí thư Tỉnh ủy, chủ tịch UBND tỉnh kiểm tra Đồ án quy hoạch cụm cảng Quốc tế Cửa Lò. Ảnh: Xuân Hoàng
Comrade Nguyen Xuan Duong - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee inspected the planning project of Cua Lo International Port Cluster. Photo: Xuan Hoang

At Vissai seaport, invested by Song Lam Cement Joint Stock Company, the representative of the unit requested the local government to completely resolve the issue of a household at the port entrance; relocate and clear the graves located in the project; and completely resolve the issue of 4 households in Nam Thinh village obstructing the Company from opening a dedicated road to the crushing station.

At the DKC Petroleum Depot, the investor proposed that there are still 3 land lots of 3 households that have not yet relocated, hoping that the locality will create favorable conditions to create a site for the project; the unit also proposed that the province approve the policy of building a road to the depot under the BT form.

 Đoàn thăm dự án Tổng kho xăng dầu ĐKC. Ảnh: Xuân Hoàng
Provincial working delegation inspects DKC Petroleum Depot project. Photo: Xuan Hoang

Cua Lo Port One Member Co., Ltd. believes that currently, at Cua Lo Port, there are often many fishing boats of fishermen occupying 2 wharves No. 3 and No. 4... as a place to anchor, exchange products... causing unsafety when loading and unloading goods at Cua Lo Port. Therefore, it is requested that the locality and the authorities take measures to resolve this issue soon.

Recommend that the relevant authorities coordinate to promptly complete the procedures and documents, announce the port according to regulations; the province promptly deploys investment in building the road to exploit the port in the area of ​​wharfs 5, 6, 7, 8 according to the approved plan.

Sau khi kiểm tra thực tế, Chủ tịch UBND tỉnh Nguyễn Xuân Đường làm việc với chính quyền các địa phương: Thị xã Cửa Lò, huyện Nghi lộc và các sở ngành, các dự án thuộc Khu kinh tế Đông Nam. Ảnh: Xuân Hoàng
After the on-site inspection, Chairman of the Provincial People's Committee Nguyen Xuan Duong worked with local authorities: Cua Lo Town, Nghi Loc District and departments, projects in the Southeast Economic Zone. Photo: Xuan Hoang

After conducting field inspections and grasping recommendations from investment units, the provincial working delegation had a working session with relevant parties.

Chairman of the Provincial People's Committee Nguyen Xuan Duong requested that investors immediately after this meeting submit specific proposals to the Provincial People's Committee for the departments and localities to promptly resolve, in order to speed up the progress of the projects. The Chairman of the Provincial People's Committee assigned the Provincial People's Committee Office to issue a notice assigning localities, departments and branches to resolve problems related to site clearance.

Xuan Hoang

RELATED NEWS

Featured Nghe An Newspaper

Latest

x
Solving problems in Southeast Economic Zone projects
POWERED BYONECMS- A PRODUCT OFNEKO