Law

Hear, see in Chau Binh...

Nhat Lan DNUM_CHZAHZCACF 07:18

We went to Chau Binh commune on July 22 - the time when storm No. 3 made landfall, with continuous heavy rain; with what we heard and saw, we somewhat sympathized with the concerns of the cadres and people in the reservoir area of ​​the Ban Mong irrigation project...

chaubinh-cover.png

Nhat Lan• 07/26/2025

chaubinh-tit1.png

Paying attention to the national key project of Ban Mong irrigation reservoir, therefore, since the beginning of May 2025, we have heard about the consequences arising in this locality. That is, after the auxiliary dam 1 blocked the flow, the water rose up and flooded the cemetery and the people's production area; the drainage canal system was damaged, blocked, causing landslides affecting the residential land and garden land of households on both sides of the canal; there was a concern that when the Ban Mong reservoir area accumulates water, there will be a situation where the residents and production areas will be isolated...

Toàn cảnh cụm công trình đầu mối hồ chứa nước bản Mồng
Panoramic view of the headworks of Ban Mong reservoir. Photo: CSCC

After the meeting with voters of Chau Binh commune by the Provincial People's Council delegates on May 23, 2025, we connected with a Provincial People's Council delegate to get more information. He said that the meeting mostly revolved around issues related to the Ban Mong Irrigation Reservoir Project.

The provincial People's Council delegate said: “Reality shows that, in the Ban Mong Irrigation Reservoir Project, from the initial design to the implementation process over the past many years, the negative impacts on the production and living conditions of the people have not been fully assessed and correctly assessed. Now the shortcomings have been clearly revealed, and we need to focus on handling them with the spirit of serving the people…”

A few days later, we were able to access Document No. 26/BC-MTTQ-BTT dated May 26, 2025 "Synthesizing opinions and recommendations of voters at the mid-year meeting of the 18th Provincial People's Council" of the Fatherland Front Committee of Quy Chau district (old). Thereby, verifying the content of the discussion of the Provincial People's Council delegate. Because in the dozens of opinions of voters of Chau Binh commune, their full names, places of residence, phone numbers, etc. were clearly stated, more than half were about issues from the Ban Mong Irrigation Reservoir Project.

gen-h-z6841189711056_9672d46837ae3a2c7373e03f906e9860.jpg
Officials of Ke Tam village, Chau Binh commune in front of the boundary marker of Ban Mong irrigation reservoir. Photo: Nhat Lan

Voter Phan Ba ​​Chien (Secretary of the Party Cell of Ke Tam village) informed on March 30, 2025 that due to the construction of auxiliary dam 1, Tam village cemetery 1 with 180 graves was flooded; not to mention that some graves were flooded and could not be counted. He said that the reason was due to the inaccurate determination of the boundary markers and flood elevation, leading to the cemetery area not being counted and relocated before the construction of auxiliary dam 1.

Therefore, he recommended that superiors should give opinions so that the project investor can have a plan to compensate and relocate all the flooded graves to another location; pay for people to organize ceremonies according to customs and practices for the deceased; find land to arrange a new cemetery for the people...

At the same time, voter Phan Ba ​​Chien also informed that in Ke Tam village, there are about 30 hectares of agricultural land (including 6 hectares of 2-rice land) that have been isolated but are not included in the area recovered by the State, and requested to build a road so that people are not affected in production...

gen-n-z6841208329892_129551b44605e3f56fa92c9bba3bca03.jpg
The burial area of ​​Ke Tam village people, Chau Binh commune is flooded. Photo: Tien Dong

Voter Lang Viet Dan (Ke Khoang village) said that in the village, there are 74 households affected by the construction of auxiliary dam No. 3, Chau Binh drainage canal; of which, 14 households lost their houses, gardens, and land; 9 households were isolated due to flooding with no way to move. Voter Lang Viet Dan requested that superiors pay attention and have a plan to clear the land; for households that are flooded and have no way to move, he requested that there be a plan to build bridges and upgrade roads so that people can move around.

Voter Nguyen Van Phong (Quynh 1 village) reported that the two banks of Chau Binh drainage canal through Quynh 1 village were eroded, affecting land outside the compensated project land area, affecting the lives of households living on both sides of the canal. He requested that competent authorities have a plan to prevent erosion of Chau Binh drainage canal so that households on both sides of the canal can live in peace...

Along with the opinions of voters, the Fatherland Front of Chau Binh commune (old) also reported on the people's petition regarding the State granting forest land in the Bu Do area that overlaps with the planning of the Mong village irrigation reservoir project. This incident involves 94 households in Quynh 1, Quynh 2, 3/4, Dong Phau, Ke Mong, Ke Khoang, and Ke Nam villages; and the people petitioned to change the overlapping granted area to production land for economic development...

On June 4, we went to Chau Binh commune (old). At this time, although we are focusing on preparing for the operation of the 2-level local government, for the Party Committee and the commune government, handling issues arising from the Ban Mong Irrigation Reservoir Project is of special concern.

The Secretary of the Chau Binh Commune Party Committee (formerly), Mr. Le Van Toan, said that the proposal regarding the flooded area of ​​Ke Tam Cemetery has been focused on by Quy Chau District (formerly) and the Management Board of Ban Mong Irrigation Reservoir Project. However, there are many complicated and difficult problems arising in the area. For example, the flooding situation is not only in Ke Tam Village, but also in the two cemeteries of Ke Mong Village...; resettlement areas are still unfinished; when the reservoir area of ​​​​Bang Mong is filled with water, there will be more isolated and divided areas...

Xã Châu Bình nhìn từ trên cao. Ảnh: Tiến Đông
Chau Binh Commune seen from above. Photo: Tien Dong
chaubinh-tit2.png

On July 22, we went back to Chau Binh commune. At this time, affected by storm No. 3, the whole Chau Binh commune was in heavy rain. Stopping at 2 resettlement areas, including the resettlement area on slope 77 and the resettlement area after the auxiliary dam 1, there was still a lot of work to do.

It is worth mentioning that due to heavy rains causing flooding in some households, a large ditch 70-80m long had to be dug on the resettlement area after the auxiliary dam 1 to drain the water. Visiting the drainage canal system in Ke Khoang and Quynh 1 villages, the canal bed has been and is being dredged of layers of mud and soil that cause blockages, but landslides on both sides of the canal are clearly visible. In Ke Mong village, both Ke Mong and Tong Ho cemeteries located near Co Ba bridge are in a state of flooding...

Nạo vét bùn đất kênh tiêu Châu Bình trong ngày 22/7/2025. Ảnh: Nhật Lân
Dredging mud and soil from Chau Binh drainage canal on July 22, 2025. Photo: Nhat Lan

We visited the household of Mrs. Pham Thi Chinh in Quynh 1 village to understand the situation of landslides in residential and garden land caused by the drainage canal system. Mrs. Chinh's house and garden are only about 8-9m from the drainage canal. In the garden, she only grows acacia trees "to prevent landslides and to have more income after about 5 years". However, the land adjacent to the drainage canal has been eroded.

Standing on the cracked ground, Ms. Chinh said that since the drainage canal was built, every time it rained heavily, water would rush back and push the garden soil into the canal, causing landslides. If there were no preventive measures, landslides would continue, affecting people's land and houses, causing congestion and damage to the state canal system.

Bà Phạm Thị Chinh ở bản Quỳnh 1, đứng tại vườn nhà bị sạt lở sát kênh tiêu Châu Bình. Ảnh: Nhật Lân
Ms. Pham Thi Chinh in Quynh 1 village, standing in her garden that was eroded near Chau Binh drainage canal. Photo: Nhat Lan

In concern, Ms. Pham Thi Chinh said: “I have represented the people here to reflect this content many times but it has not been resolved. The households living along the canal are very worried. Every night when there is heavy rain, they dare not sleep. I hope this problem will be resolved so that the people's property and the State's property will not be damaged…”.

According to Mr. Bui Hoang Tung - Deputy Head of the Economic Department of Chau Binh Commune, the reflection of people living along the drainage canal about the landslide of residential land and garden land is correct. The landslide causes silting of the drainage canal, blocking the flow, and preventing water from draining.

This issue has been proposed by the commune to the superiors, the investor, the Ban Mong Irrigation Reservoir Project Management Board, has directed the construction unit to dredge the soil, clear the flow, and prevent flooding for Chau Binh commune.

However, this is a temporary measure, because the drainage canal is an earthen canal, and over time it will continue to experience heavy rains, causing erosion, landslides, sedimentation, and blockage of the flow. Therefore, Chau Binh commune is continuing to petition the investor to study and overcome these shortcomings.

“In our opinion, we need to continue lowering the canal roof and dredging to widen the canal bed…”, Mr. Bui Hoang Tung said.

Ông Bùi Hoàng Tùng, Phó phòng Kinh tế xã Châu Bình tại khu vực kênh tiêu Châu Bình. Ảnh: Nhật Lân
Mr. Bui Hoang Tung - Deputy Head of Chau Binh Commune Economic Department in Chau Binh drainage canal area. Photo: Nhat Lan

Arriving at Chau Binh commune headquarters, we were able to access Report No. 04/BC-MTTQ dated July 17, 2025 "Synthesizing voters' opinions before the 14th session of the 20th term People's Council of the commune, term 2021 - 2026" of the Standing Committee of the Fatherland Front of Chau Binh commune.

In this Report, there are 14 items in the field of investment - construction; 10 items in the field of land - environment. In each item, there are many recommendations, mainly related to the Ban Mong Irrigation Reservoir Project.

According to Mr. Lo Van The - Chairman of Chau Binh Commune People's Committee, the Ban Mong irrigation reservoir project has been going on for many years, so there are many problems. Particularly in the reservoir area of ​​Chau Binh Commune, after the first auxiliary dam was built, new problems have arisen. Currently, the commune government and the Ban Mong Project Management Board are focusing on handling them. However, many tasks are still unfinished and it is predicted that more complicated problems may continue to arise.

For the flooded cemeteries, Chau Binh commune has agreed with the people on a plan to move graves; and has also determined the land location to build a new cemetery. However, to build essential infrastructure such as roads to the new cemetery, more time will be needed to organize land use planning.

Regarding the records of measuring the reservoir area, Chau Binh commune has received them recently, but after some rains, it was found that the water level had risen and flooded some areas outside the boundary that had been handed over to the commune. In these areas, there are production areas and households that are isolated, affecting daily life and production.

The commune's wish is that the Management Board of Ban Mong Irrigation Reservoir Project and higher-level agencies urgently re-measure the discovered locations to soon put those areas into the land clearance and recovery area, or have a plan to build an access road so as not to affect the people.

Regarding the two resettlement areas, they are still not completed, while many households have a need for residential land, so the progress needs to be accelerated. Because without the resettlement area, Chau Binh commune will face difficulties in site clearance...

gen-n-z6841175057807_8322461aa2b6d570d40572e708f537b8.jpg
The graves of Ke Mong villagers were flooded on July 23, 2025. Photo: Nhat Lan

According to Chairman of Chau Binh Commune People's Committee Lo Van The, the areas identified to be isolated when the reservoir is filled with water are concentrated in Ke Tam village, Ke Khoang village, and Binh Quang village with a total of 34 households. In Binh Quang village alone, 19 households and about 1,000 hectares of production forest land will be isolated.

“This is a content that needs to be surveyed soon, and there is a solution. In addition, we hope that the superior agencies will direct the design consulting unit to accurately determine the water level of the Ban Mong irrigation reservoir area, to avoid new problems arising after the water is stored, then the handling will be very passive and difficult…”, Mr. Lo Van The shared.

Chủ tịch UBND xã Châu Bình, ông Lô Văn Thế trao đổi với PV Báo và phát thanh, truyền hình Nghệ An. Ảnh: Nhật Lân
Mr. Lo Van The - Chairman of Chau Binh Commune People's Committee talked with reporters of Nghe An Newspaper and Radio and Television. Photo: Nhat Lan

Contacting the Management Board of Nghe An Agricultural and Rural Development Construction Investment Project (a unit under the Department of Agriculture and Environment - the investor of the site clearance project of Ban Mong Irrigation Reservoir Phase 1), it is known that the Board has a basic understanding of the problems in the reservoir area of ​​Chau Binh commune. And it is informed that on July 11, 2025, Deputy Minister of Agriculture and Environment Nguyen Hoang Hiep visited the province to work to assess the progress and resolve problems in the implementation of the project.

On July 16, 2025, the Ministry of Agriculture and Environment announced the conclusion of Deputy Minister Nguyen Hoang Hiep, in which, it requested the consulting unit to inspect and re-evaluate the flood level, identify areas and subjects affected by flooding; at the same time, assign the Department of Agriculture and Environment to inspect and review the whole situation to propose and submit to the Provincial People's Committee a plan to build and restore residential roads...

Khu tái định cư sau đập phụ 1 xã Châu Bình ngày 22/7/2025. Ảnh: Nhật Lân
Resettlement area after the auxiliary dam 1 in Chau Binh commune on July 22, 2025. Photo: Nhat Lan

Thus, it can be seen that the problems in Chau Binh commune have been and are being paid attention to by the Central and Provincial agencies, and solutions have been proposed. However, the deadline for completing the site clearance work for the Ban Mong Irrigation Reservoir Project Phase 1 is only more than 5 months (December 31, 2025). Therefore, an accurate and complete assessment and thorough handling of arising problems must be urgently carried out, so that the Ban Mong Irrigation Reservoir Project can be completed, so that the people in the Chau Binh reservoir area can be stable!

chaubinh-box.png

Featured Nghe An Newspaper

Latest

Hear, see in Chau Binh...
POWERED BYONECMS- A PRODUCT OFNEKO